RFI - Attachment 4- Advice regarding offsets from HopgoodGanim
HopgoodGanim 24 April 2019 LAWYERS Stockwell Development Group Pty Ltd BRISBANE C/- Leanne Porter Level 8, Waterfront Place Development Manager 1 Eagle Street By email: [email protected] Brisbane Qld 4000 Australia PO Box 7822, Waterfront Place Our ref: 1932235 - Robyn Lamb Brisbane Qld 4001 Australia ABN: 54 105 489 661 This electronic transmission is intended only for the use of the individual or entity to which it is addressed and may contain information that is privileged, confidential or exempt from disclosure under applicable taw. If you are not the intended recipient, any dissemination, distribution or copying of this communication is strictly prohibited. If you have received this communication in error, please notify us immediately by telephone, return the original electronic transmission to us at the address below by post and delete or destroy any electronic or other copies. Thank you. Dear Leanne Advice - Council's power to impose environmental offset conditions 1. You have asked for our advice to assist you to respond to item 7 of the Council's information request, dated 21 December 2018 (Information Request) with respect to a development application for reconfiguring a lot (19 lots and new road) (Development Application) in relation to land situated at 28 Eenie Creek Road, Noosaville, or more particularly described as Lot 3 on SP246584 (Land). 2. By way of background, we note that: (a) On 21 August 2003, the Council issued a negotiated decision notice for a development permit (Council reference DA22803) to facilitate the development of Stage 1 of the Shire Business Centre (Stage 1 Approval). Condition 12 of the Stage 1 Approval required dedication for environmental park purposes land labelled within Precincts OS1 and OS2 of the Shire Business Centre. Other conditions required Precincts OS3, OS5 and OS7 to be protected by registered environmental covenants’. (b) On 8 October 2003, an infrastructure agreement was entered into between Mirose and the Council (Infrastructure Agreement) which relevantly: (1) applies to the entirety of Lot 2 on SP 110885 which, based on the information available to us, includes the land necessary for the full extent of the Shire Business Centre (i.e. including the Land the subject of the Development Application)’; (2) requires dedication to the Council of Open Space Areas A and B (comprising 12.63ha) of land as part of Stage 1, which BRISBANE we are instructed has occurred; T +61 73024 0000 F +61 73024 0300 PERTH : tania; . “4: T +618 92118111 * Noosa Shire Council decision notice, conditions 25, 33 and 41. F +618 92219100 ? Infrastructure Agreement, clauses 1.3, 8 and 9 www.hopgoodganim.com.au 1932235 - 19035368_1.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 2 pages
Page 2
Stockwell Development Group Pty Ltd C/- Leanne Porter Development Manager 24 April 2019 (3) provides that the Council recognises that the dedication of Open Space Areas A and B is an appropriate commitment “to meet environmental needs” of the land and is taken to be a contribution to community infrastructure; (4) requires ongoing management of private open space areas “to meet the environmental requirements”; (5) given the above, provides that applications for development approvals for future stages (namely any subsequent development of the Shire Business Centre) are immune from conditions requiring any further dedication of land or payment of contributions or charges for, inter alia, conservation reserves, conservation areas, nature conservation, bushland preservation and like purposes. 3. Under the Environmental Offsets Act 2014 (Environmental Offsets Act), the Council may impose an offset condition only if satisfied: (a) the proposed development will, or is likely to, have a significant residual impact? on a non-juvenile koala habitat tree in an area of bushland habitat, high value rehabilitation habitat or medium value rehabilitation habitat; and (b) all reasonable on-site mitigation measures for the proposed development have been, or will be, undertaken. 4, Importantly, when making a decision about whether to impose an offset condition, the Council must consider any offset condition that has been imposed for the same, or substantially the same, impact and prescribed environmental matter’. Further, the Council may impose an offset condition only if the same, or substantially the same, impact and prescribed environmental matter has not been assessed under, relevantly, the Commonwealth Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)°. This restriction applies whether or not the assessment resulted in the imposition of an offset condition, but significantly, is only enlivened where the proposal has been assessed as a controlled action under the EPBC Act. 5. Pursuant to condition 12 of the Stage 1 Approval and clause 4.1 of the Infrastructure Agreement, the Council has previously received a land dedication of 12.63 hectares for open space and nature conservation. 6. Firstly, given that clause 4.2 of the Infrastructure Agreement acknowledges that this land dedication is an appropriate commitment of land to satisfy the environmental needs of the land within the Shire Business Centre, it is arguable that the Council has previously assessed and accepted that any impact caused by the development of later stages, including the proposed development, is appropriately offset and counterbalanced by the land dedication provided, such that development of later stages should not be regarded as resuiting in significant residual impact. 7. Secondly, it is also arguable that the imposition of an offset condition on an approval of the proposed development would only serve to address the same, or substantially that same, impact and prescribed environmental matter for which condition 12 of the Stage 1 Approval was imposed (and in respect of which the Infrastructure Agreement was subsequently 3 As defined by s8(1) of the Environmental Offsets Act * Section 14(2) of the Environmental Offsets Act 5 §.45(1) of the Environmental Offsets Act 1932235 - 19035368_1.docx Page 2 of 3
Page 3
Stockwell Development Group Pty Ltd C/- Leanne Porter Development Manager 24 April 2019 entered into). It is our view that the Council must consider this condition when assessing the Development Application, as required by section 14(2) of the Environmental Offsets Act. 8. Finally, the Infrastructure Agreement remains in effect under the Planning Act 2016 (Planning Act) according to the terms and conditions of the document, even if the terms and conditions could not be imposed under the Planning Act. The Planning Act applies to the document as if the document had been made under the Planning Act. 9. In all of the circumstances, it is our opinion that the Council is precluded from imposing an environmental offset condition on an approval of the Development Application. In summary: (a) condition 12 of the Stage 1 Approval and the Infrastructure Agreement provided for dedication to the Council of Open Space Areas A and B (comprising 12.63ha) of land as part of Stage 1, which has been done; (b) in the Infrastructure Agreement, the Council recognised that dedication to the Council of Open Space Areas A and B was an appropriate commitment “to meet environmental needs” of the Shire Business Centre land (including the subject Land); (c) the Infrastructure Agreement provided for ongoing management of private open space areas “to meet the environmental requirements”; (d) given the above, the Infrastructure Agreement provided immunity from conditions in development approvals for future stages (namely any subsequent development of the Shire Business Centre) requiring any further dedication of land for, inter alia, nature conservation, bushland preservation and like purposes; (e) having regard to the above, the Council could not be satisfied that the proposed development the subject of the Development Application will, or is likely to, have the requisite significant residual impact; (f) further, the Council must, in determining whether to impose an environmental offset condition, consider condition 12 of the Stage 1 Approval and clause 4.1 of the Infrastructure Agreement which resulted in the dedication of land for substantially the same matter and impact, being the ultimate development of the Shire Business Centre. Having considered the condition (and Infrastructure Agreement), the Council could not reasonably form a view that an environmental offset condition is required for the Development Application. Yours faithfully [Fy HopgoodGanim Lawyers Contact: Sarah Macoun Partner T 07 3024 0367 F 07 3024 0067 E [email protected] 1932235 - 19035368_1.docx Page 3 of 3