Decision Notice - Change to an Existing Approval - 010.2004.00004206.001 [As Published] · 132004.4206.02
2004/4206
3. In accordance with the Environmental Protection (Water) Policy 1997, all sand, silt, mud, paint,
cement, concrete, builders waste or rubbish shall not be permitted to enter or be placed where
it could reasonably be expected to move into a roadside gutter, stormwater drain or a water
course. On the spot fines apply for such offences.
4. The Building shall comply with the requirements of the Building Code of Australia Section C
with respect to Class 2 Buildings.
5. Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if
the cost of operational works exceeds $80,000, then a portable long service leave levy is
required to be paid. In accordance with Section 77.(1) of the Act, Council is required to sight
the approved form issued by the Building and Construction Industry (Portable Long Service
Leave) Authority that confirms that the requirements of the Act have been satisfied. A statutory
declaration outlining the cost of the operational works must be submitted to Council with the
lodgement of any application for operational works over the site.
6. We advise ‘interested parties’ i.e. ‘developer’, ‘owner’, ‘tenant’ to consider their responsibilities
under the Disability Discrimination Act (DDA) in regard to the installation of disabled access
and the provision of disabled facilities, and that access to this building and the provision of
sanitary facilities may need to comply with the requirements of Section D Part D3 and Section
F Clause F2.4 of the Building Code of Australia.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act
can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural
heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.
8 PROPERTY NOTES
Not applicable
9 PRELIMINARY APPROVAL OVERRIDING SCHEME
Not applicable
10 FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit required Subject of the required Development Permit
Development Permit for Operational Access, Carparking, Site Civil Works, Site Filling,
Works Stormwater Drainage, Frontage Works, Sewer
Reticulation (Including New Mains) and Landscaping
Development Permit for Building Works All Building Works
11 SELF ASSESSABLE CODES
Not applicable
Page 11 of 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Change to an Existing Approval - 010.2004.00004206.001 [As Published]Related documentApplication case desk ↗
Decision Notice - Change to an Existing Approval - 010.2004.00004206.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 81 KB (small file)
- File type
No other editions are linked here.