Council archive · source document
07/1849 - Op Works - Residential Subdivision [As Published] · 142007.1849
APPLICATION AND ) GENERAL FEES
DEVELOPMENT FEES & CONTRIBUTIONS
giuirn fo Admin Officer, Development)
(Cashier: Please
Application Fees
Road / Drainage Plan Exam
Road / Drainage Field Inspection
Pre-lodgement Meeting Fee
| CONTRIBUTIONS |
Developer Contribution — Other Parks and Community
ICS — Community Land (Not currently active)
ICS — Public Transport
ICS - Sewerage (PSP Rural)
ICS — Sewerage (PSP Coastal)
Legal Document Examination’
Sealing Fee - Survey Plans, Legal Documents
Sale of Documents, Policy Lists, Mise
Bonding Admin Fee (Contributions, uncompleted works)
Closed Circuit TV inspection
54
~ | -AMOUNT | RECEIPT.T
RECEIPT TYPE | BONDS - BondBiuna Details
| __40___—| Payee Name:
Address:
CALCULATIONS
Lot Calculation SO
{tS
AGS
ICS - Sewerage - South Peregian (PSP Maroochy)}
ICS — Water Supply (PSP)
ICS - Sport and Recreation Land (PSP Parks)
ICS - Drainage (PSP Noosaville Master & Ward Street)
ICS — Road (CMRNIGP) If BA not entered then use 594
ICS - Pathway (PSP)
a RS
CASTeL Cam
TUGW) Qo &k22y4
Total of Fees Paid (Including Bonds)
P-Land DevelopmentFEES & CONTRIBUTIONS/DEVELOPMENT FEES. doc
Total of Fees Paid (Excluding Bonds) $
CPI Date: _ AMOUNT _
Security Deposils/PerformancelMaintenance/Uncompleted Works Bond]
Development Location: | LACUIA ST - bax ca)
RECEIPT TYPE File Numbers or Reference:
th. 2woT. KA. |
ReceiptNo: {en i? | Receipt Date: 14 /9/O7] |
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 22 pages
Page 2
INTEGRATED PLANNING ACT 1997 , Part A, Version 2.4, 29 May 2006
WW Form 1 Development Application
Common details &
a.
The completion of all applicable questio ns on Part A is mandatory for ail applications, Part A must be accompanied by the completed IDAS Assessment Checklist if
Fequired, and by one (1) or more other completed parts of the Form as required. For more information on the parts of the Form refer to www.ipa.ak.gov.au.
Any information requested in the form may be provided in an attachment to the application. For further information about completing the folowing details, refer to Guide 1.
} Description of land 1 Te address: fnetudinghouse number, street name, suburtvlocality name & postcode) (if applicable) 5
{ All land the subject of the application, must be / LAGUNA SREET 2 a/ p MT
{dentifed, However, a description of the tand is not 2 QREE OF
Habiahialarwnamlrend yeild 2. a of water body or watercourse, within which the development is proposed: (if appiicable) :
j Advice for comnleting Q2 - 02 appiies if ~
r | development is proposed within a water body or
j watecourse. 3. Lot on plan description (eg. Lot 123 on RP 4567)/ GPS coordinates:
‘Advice for completing Q3 - Most land can be
Oey hee | Lor § SP 19/ 680 ]
can documents of through the
4. The above description is for: (tick applicable box) .
‘ocal government,
« However, i the land on which the development is wi the land on which the development is proposed; or
;rosed does pat have alt on pan destin fey. Oi) the land a adjoining the water body or watercourse, within which the development is
} watercourse) provide — ; Proposed; or
0 eto Ban Serre fe he Li) the water body or watercourse.
AD stolons te ‘oa ir theeton Bay). 5. Shop / tenancy number: 6. Storey / level: 7. Total area of land: (mr? or ha):
<Siomaamayton | [- ) | =n |
_ development is within a water body or watercourse.
. Sete a Oe see rea 8. Local goverment area in which the land is situated: (eg. Esk, Hervey Bay, Woocoo etc.) (if applicable)
Wate: Aas teow igh watermark om natwinne | 6 | NOOSA [A (RE
. government's area
to Government Act 1993, / 9. Port authority for the strategic port land or strategic port land tidal area on which the
Preeccrerarerrer vote stop development is proposed: (eg. Port of Brisbane, Port of Townsville) (if applicable)
[Pra al area. For more deta refer to Guido 11 | - |
' Proposal detalls 10. Existing use of the land: (eg. vacant, single house, shop etc.)
| ther insufcent room avaiable, detais may be [ VACANT |
_ ) provided in an attachment to the application.
@:; 11. Proposed use of the land: (eg. 6 unit apartment building, 30 lot residential mubtieson, ERA for aquaculture in
ponds with a total area of 7 ha for which wastes are released into waters etc).
[2 LOT RESWENTIAL — SABD/VMON/ 1
Other applicable parts of Form 1 12. Other parts of Form 1 completed as part of this application: (eg. Part D, Part J, etc)
tatheutumateocmmivens | [Pak E. CHEKLIY« __ |
{when a part of Form 4 may apply refer to Guide 1,
| Applicant details 43. Applicant's name: 15. Contact person:
‘ppeninmieiorenae [PeS PTY KD | [Codvn/ PY WKELE |
! When slgntng and lodsna tis apoication 14, Contact number: 16. Facsimie-pemy ail address: ,
|Meapkatisesosbomresugte = | [ogo9-7-79 263
i referral & the Chief Executive
{here appfeabe) wit ly on hs fomation when 17. Postal address:
[eseea nd ae en — (6 Cache Court Ket 4 RRCEIVEA2
{ must be shown, 18. Signature sl
Page 3
INTEGRATED PLANNING ACT 1997
_ Land owner's consent (if applicable)
‘Section 3.2.1(3) of the IPA prescribes that an
. pplication must contain, oc be supported by, the
vatten consent told owners, if tha application
tan material change of use;
{il} reconfiguration of a lot:
/ work on Land below high-water mark & not within a
canal as defined under the Coastal Protection and
Management Act 1995;0r
“ha work on rall corridor land defined under the
* Transport infrastructure Act 1994.
Saction 3.8.1(2)(a) of the IPA provides that
landowner’s consent is not required for a mobile or
- temporary ERA .
+ For more information refer to Guide 1.
20. Land owner's consentto the making of this application:
Part A, Version 2.4, 29 May 2006
Name
Signature
“Resource entitlement (if applicable)
j Section 3.2.1(5) of the IPA requires evidence of
* resourme entitiement be given for applications that
involve a prescribed State resource.
* Section 3.2.1(10)(e)(i) of the IPA prescribes that an
application cennot be taken to be properly made
.. Without evidence of the resource entitlement.
. Advice for completing Q21 & 22
Refer to schedule 10 of the integrated Planning
Regulation 1998 that prescribes the nature of evidence
tequired by the State in support of tha lodging of this
development application,
Advice for completing Q273
The information in (i) ~ (v) is mandatory if evidence is
required under 022 {ii) or (iii) above.
* The official stamp of the Department of Naturat
Resources, Mines and Water is mandatory where the
; application involves any water or riverine quarry
material under the Water Act 2000.
_ Section 3.2.1(5A) allows the resource manager to limit
+ the time the evidence may be used, 023 (vi) must be
completed if the evidence is time Kimited,
Assessment triggers
21.
23,
Does this application involve a State resource prescribed under a regulation (other than involving
quarry material on State coastal Jand under the Coastal Protection and Management Act 1995)?
[X] NO - goto a24
(DYES - go to 022
This application is accompanied by evidence: (tick applicable box)
(1 ()) ofthe allocation of, or entitlement to, the resource - attach evidence and goto a23(09
1 {ii) the chief executive of the department administering the resource is satisfied the
development is consistent withan allocation of, or entitlement to, the resource - go
to Q23
(1 (iii) the chief executive of the department administering the resource is satisfied the @
development application may proceed in the absence of an allocation of, or
entitlement to, the resource - go to Q23
Evidence of the resource entitlement:
(i) Resource entitlement / ane details
(i) Name of cle officer
(iii) Position of seas officer” _- .
{iv) Signature of delegated officer
(vii) Official stamp of the department
administering the resource (é
applicable)
(¥) Date
(vi) fran-see olen eat :
24, Is the IDAS Assessment Checklist completed and attached to this application?
This checklist does not epply if he pplcaton requires ] Yes C].No- ~ the assessment manager may refu ls
' the completion of Parts A and B of the Form only. tt iy refuse to accept this application on the
“munya oma Sora fer epeatons: grounds thet the application has nat been properly made ;
‘Plans f drawings / reports 25. Plans/drawings/reports accompanying this application:
“apenas pte needy aa Plan / Drawing / Report Number Title
i manager, referral and viewing ;
on anpisabon auing pablo tarde or pub () O7093( — Of Acca PLAn)
notification to understand the scope ofthe proposal fo [oom mtn ont t rc Src o nrc nese e eee r nnn a donno ns aenwnenrercerewaccewaccane
* and any potential impact. (ii)
/ (iii)
(w)
i
PLEASE NOTE: The assessment manager may refuse to accept an application that, at the time of lodgement, fails to provide all applicable information required by Part A
and any other relevant part of Form 4.
OFFICE USE ONLY (eppticable to assessment manager's)
FEE(S) DATE RECEIVING OFFICER'S | SereRENCE
RECENED 2 WAMEIS WUMBERIS
Notification of Engagement of Private Certifier (Optional fonnat) ,
To, Council. | have been engaged as the private certifier for the building work referred to in this application.
Date ofengagement / { Accreditation Number. ___. Name. Signature:
Page 4
INTEGRATED PLANNING ACT 1997 Part E, Version 2.1, 18 June 2007 YS Form 1 Development Application Operational &/or building work ‘tI assessable against a local government's planning scheme PA Completion of afl question on Part E is mandatory for all applications involving the assessment of operational work. and/or building work assessable against a local govemment's planning scheme (including detailed engineering plans and other plans, detailed engineering plans for subdivisional works and conceptual design plans for engineering & building work when the application does not involve assessment of e material change of use of premises at the same time). Nature of the works The types of work that are assessable against a planning scheme are determined by the scheme for a particular local goverment and will vary across the State. To determine the types of work that are assessable under a particular planning scheme, contact the retevant local goverment. The information in Q2 ts necessary for 1. The application is seeking approval of (tick one (1) or both if applicable): (] Building work assessable against a planning scheme - provide details of the aspects of building work (e.g. building height greater then 8.5m; building work on high landslip risk area) [ | LN Operational work assessable against a planning scheme - provide details of the nature of the operational work (e.g. roadworks; landscaping; drainage works; Stormwater, water infrastructure; sewerage infrastructure; earthworks; clearing vegetation; signage) [A&CEEr ZA LUOUING VEGETATION CLEARING | statistical and planning purposes. 2. _ Is the application for operational work involving the creation of new lots? LINO [XL YES - specify number of new lots to be created below ONE NEW LOT 3. Does the proposal involve the construction of a canal that is associated with reconfiguring a lot? C)No- (YES Nature of the application 4, This application is for: (tick one (1) or both if applicable) A development permit authorises . hea ankle oO Preliminary approval provide details of the type of work eg, roadwork, stormwater, water and sewerage approval is a step in the approval process - - and does not authorise development to occur. | | & Development permit - provide details of the type of work eg. roadwork, stormwater, water and sewerage infrastructure, etc | ACESS 5. Are the works subsequent to a previous development permit or preliminary approval? CINO YES - provide details of ail previous approvals - ;___ List of approval referencals Date. approved... |; _. “Date approval lapses... oe JIFSY. fof if Portable Long Service Leave levy (if |6. Is payment of a Portable Long Service Leave Pst) levy applicable to the proposal? applicable) - * Prior to issuing a development permit forthe CI YES - compiete 7 works, the assessment manager is required BX NO ~ 07, 8 & 9:do not apply by law to “sight” an approved form, Issued by . (leave, yi signifies thatthe PLSLlevy 17. Has the PLSL levy been paid? For futher information refer to C1 YES - compete 08 __ hitodAwew gleave.ald gow.ay (NO - ite applicable levy must be poi before ¢ devekoment pent can be given for the works , 8. How much was paid? . 9, Whatis the receipt number of the payment?
Page 5
INTEGRATED PLANNING ACT 1997 PLEASE NOTE Part E, Version 2.1, 18 June 2007 This application cannot be accepted unless accompanied by Part A of Form 1. The assessment manager may refuse to accept an application that, at the time of lodgement, fails to provide all applicable information : requested by Part A and any other relevant part of Form 1. OFFICE USE ONLY (appticabie to assessment manager) (ii) Has the approved form (issued by QLeave and which signifies that the PLSL levy has been paid) been sighted by the assessment ?- Nate pees 2, * REFERENCE jr “DATE RECEIVED .. -- NUMBERIS (i) 's aPLSL tevy applicable in this instance? . (JNO 1 YES - compiete a1 manager / private certifier at the time of lodgement of this application? CiNo 1 YES - provide receipt detais
Page 6
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 20, 2 April 2007
ALS el PLN ele) e Vee [Corel tCeN8
_ IDAS Assessment
Checklist
(Formerly the “Referrals Checklist”)
IMPORTANT NOTE FOR ALL APPLICANTS:
1.
2.
This checklist was formerly referred to as the "Referrals Checklist’. Some of the ‘Guides’ to using the IDAS Application Forms continue to refer to this document as the
“Referrals Checklist’. The name of this checklist was changed from 25 July 2005 to more accurately describe its function.
Under the IPA and IDAS framework, an application may require assessment by the local Council and/or certain Queenstand State entities {e.g. Environmental Protection
Agency, Dept. of Natural Resources and Water, Queensland Heritage Councit etc.).
This checklist is provided to assist applicants to determine when an application requires assessment by a Queensland State entity and may also assist the applicant to
determine the assessment manager’ for the application. .
Therefore, the completion of all questions in section 1 of this checklist is mandatory for all applications (other than those requiring the completion of Parts A & B only}.
{tis the responsibility of the applicant to accurately complete this checklist.
Section 2 is mandatory only if the proposed development is located in any part of a wild river area declared under the Wild Rivers Act 2005.
Depending on the nature of the application, an applicable State entity may be either the assessment manager or an IDAS referral agency for the application,
The assessment manager for the application will rely on the information provided in this checklist (as well as any material lodged in support of the application) to identify
any applicable referral agencies for the application in the Acknowledgement Notice. The assessment manager will also rely on this information when identifying if the
application triggers referral coordination?.
To assist you in answering the following questions a series of guides are available free from the IPA website www. ipa.ald.gov.au. Guide 25 explains the role of the [DAS
Assessment Checklist in the IDAS application process, and its telationship to the Form 1 development application.
Any other parts of Form 4 that this checklist requires to be completed are available from the Council or the applicable State entity, or can be downloaded free from
Section 3 provides advice about the referrals that can be required for applications for building work assessable against the Building Regulation 2008.
r
\ . SECTION 1 - STATE ASSESSMENT (completion mandatory) "
jNote: The following state assessment triggers apply to development other than for building work assessable against the Building Regulation 2006. ..,
Environmentally relevant activity 1. The application involves: (tick applicable box/es) .
For more inforrnation refer to Guide 4. \O(i) an environmentally relevant activity (ERA) for which a code for environmental compliance
Unless you answered “none of the above" to Q1, \ has not been made - complete Part G of Form 1
the application requires assessment by the se a. . . .
administering authority®. UO (ii) a mobile or temporary ERA for which a code of environmental compliance has not been
@ If an entity, other than the administering made - complete Part G of Form 4
authority, is the assessment manager for the {iii) none of the above
application, the administering authority is a
concurrence agency for the application in relation
to this matter. .
Note: An application involving ERA 19 and/or 20
will also require completion of Part Kz of Form 1
for approval where an allocation under the Water
Act 2000 is required.
Continued overteat
PLEASE NOTE: The assessment manager may refuse to accept an application, which, at the time of lodgement, fails to provide the
completed IDAS Assessment Checklist (if applicable).
OFFICE USE ONLY (appticabie to assessment manager)
__DATE RECEIVED +
REFERENCE NUMBERIS — |
1 The assessment manager is responsible for assessing and deciding an IDAS apptication. The assessment manager for an application is prescribed in schedule 8A of the IPA.
2 For additional information refer to Guide 6 ‘Does my application trigger the referral coordination process?”
3 The ‘administering authority’ may be either the Environmental Protection Agency, the relevant local government (for a devolved ERA) or the Queensland Department of Primary Industries and
Fisheries (for a delegated ERA).
Page 1
Page 7
INTEGRATED PLANNING ACT 1997
State-controlled road matters
For more information refer to Guide 3.
Unless you answered “none of the above" to Q2,
the application triggers referral to the Department
of Main Roads (DMR) as a referral agency.
In certain circumstances DMR will be an advice
agency, while in other circumstances DMR will
be a concurrence agency.
Schedule 2 of the IP Requlation will assist you to
determine where DMR is an advice or
concurrence agency for the application.
. IDAS Assessment Checklist, Version 20, 2 April 2007
2: The application involves: (tick applicable box/es)
[1 @ development on land contiguous* to a State controlled road and for -
(2 (a) material change of use assessable against the planning scheme;
LD (b) reconfiguring a fot unless -
« the total number of lots is not increased; and
« the total number of lots abutting the State-controlled road is not increased:
(1 © operational work (not associated with a material change of use assessable against the
planning scheme or reconfiguring a lot mentioned in (b) above)
¢ associated with access to a State-controlled road; or
for filling or excavation; or
« involving the redirection or intensification of site stormwater from the land, through a
pipe with a cross-sectional area greater than 625 cm’ that directs stormwater to a
State-controlied road.
CO (ii) development on land not contiguous to a State-controlled road and -
(0 (a) material change of use -
* assessable against the local government's planning scheme; and
* mentioned in schedule 5 of the IP Regulation and exceeding the thresholds set by
that schedule;
C (b) reconfiguring a lot for a purpose mentioned in schedule 5 of the IP regulation,
“* and exceeding the thresholds set by that schedule;
Cc) operational work (not associated with a material change of use assessable against the
planning scheme or reconfiguring a lot mentioned in (b) above}-
* assessable against the local government's planning scheme; and
* mentioned in schedule 5 of the IP Regulation and exceeding the thresholds set by
that schedule.
KX] (iii) none of the above
Clearing vegetation
For more information refer to Guide 12.
Unless you answered “none of the above” to Q3,
the application requires assessment by the
Department of Natural Resources and Water
(NRW).
If an agency other than NRW is the assessment
manager for the application, NRWis a
concurrence agency for the application in relation
to this matter.
Ifyou ticked Q3(i) or (ii), your application requires:
referral to NRW for assessment regardless of
whether vegetation clearing is proposed or not.
3. The application involves: (tick applicable box/es)
(1 (i) material change of use -
(a) assessable against the planning scheme;
(b) on a tot containing -
* acategory 1, 2 or 3 area shown ona property map of assessable vegetation; or
+ if there is no property map of assessable vegetation for the lot - remnant vegetation;
(c) where the existing use of the land is a rural or environmental use; and
(d) where the size of the land is 2 hectares or larger - complete Part J of Form 1
reconfiguring a lot —
(a) on alot containing a category 1, 2 or 3 area shown on a property map of
“assessable vegetation or, if there is no property map of assessable vegetation to
the lot, remnant vegetation;
(b) -where the size of the lot before the reconfiguration is 2 hectares or larger;
{c) where 2 or more lots are created; and
(d) where the size of any lot created is 25 hectares or smaller - compete Part J of Form 1
operational work -
{a) for the clearing of native vegetation where the vegetation clearing is made
assessable under Schedule 8 of the IPA; and
(b) not associated with a material change of use assessable against the planning
scheme mentioned in (i) or reconfiguring a fot mentioned in (ii) - complete Part J of
Form 1
D1 (iv) none of the above.
[bd
wy
1 iii)
Strategic port land
For more information refer to Guide 41.
Hf you ticked (i) - the relevant Port Authority is the
assessment manager for the application.
if you ticked (il) Queensland Transport is a
concurrence agency for the application.
4. The application involves:
(1 (i) development on strategic port land as defined in the Transport Infrastructure Act 1994 (TI
Act) - complete Part | of Form 1
C1 (ii) a material change of use that is inconsistent with the land use plan approved under the
TI Act for the strategic port land - complete Part | of Form t
[X (ii) none of the above
4 Land contiguous to a State-controtied road is defined in schedule 14 of the IP Regulation to mean land - if part of the land is within 100m of the State-controlled road; or that is part of a future State-
controlled road.
Page 2
Page 8
INTEGRATED PLANNING ACT 1997
Acid sulfate soils 5.
For more information refer to Guide 10,
Unless you answered “none of the above" to 05,
the appfication requires assessment by
Department of Natura! Resources and Water
(NRW).
lian agency other than NRW is the assessment
Manager for the application, NRW is an advice
agency for the application in rélation to this
matter.
IDAS Assessment Checklist, Version 20, 2 Aprit 2007
The application involves development on land situated in an identified’ locat govemment area
and where the surface of the land is: (tick applicable box) .
[14 below 20m AHDS and the development will involve the excavation of 1000m? or more of
soil or sediment at or below 5m AHD, or mo
D1 (i) at or below 5m AHD and the development will involve filling the site with 1000m3 or more
of material
[DX (ill) none of the above
Major hazard facilities or possible 6.
major hazard facilities
For more information refer to Guide 17.
Ifyou answered “YES” to Q6, the application
fequires assessment by the Department of
Emergency Services (DES).
if an agency other than DES is the assessment
manager for the application, DES'ts a
concurrenca agency for the application in
relation to this matter.
Does the application involve a material change of use for a major hazard facility or possible
major hazard facility as defined under the Dangerous Goods Safety Management Act 2001?
J No
[YES - complete Part L of Form 1
Water related development under the | 7.
Water Act 2000
For more inforriation about items (a) - (f), refer
to Guide 15, For more information: about item
(9), sefer to Guide 14 Does my application
involve assessment of a referable dam?
Unless you answered “none of the above” to Q7,
the application requires assessment by the
Department of Natural Resources and Water
(NRW).
if an agency other than NRW is the assessment
manager for the application, NRWisa -
concurrence agency for the application in
relation to this matter.
The application involves:
2 (i) operational work, for taking or interfering with water under the Water Act 2000, that is:
(tick applicable box/es)
Oo {a) in a watercourse, lake or spring, (eg. a pump, gravity diversion, stream re-direction, weir or
dam) - complete Part K, K3, Ka Ks, or Ke of Form 1 whichever is applicable;
(1 (b) for an artesian bore anywhere in the State, no matter what the use - ‘complete Part
K; of Form 1; .
oO {c) for a subartesian bore, in declared subartesian area’, or in a certain area covered
by a water resource plan, for use for purposes other than stock and/or domestic
use - complete Part K; of Form 7,
(1 (d) for a subartesian bore, in certain declared subartesian areas, for use for stock
and/or domestic purposes - complete Part K: of Form 1;
LJ (e) for taking overland flow water in certain areas covered by a water resource plan
oO
for constructing a referable dam® or works that will increase the storage capacity
- complete Part Ke of Form 1;
for interfering with overland flow water in a drainage and embankment area .-
O@)
of a referable dam by more than 10% - complete Part Ks of Form 1; or
§XJ (ii) none of the above.
complete Part Kioof Form 4
Removal of quarry material from a 8.
watercourse
For more information refer to Guide 16,
Ifyou answered "YES" to Q8, the application
requires assessment by the Department of
Natural Resources and Water (NRW).
lfan agency other than NRW is the assessment
manager for the application, NRW is a
concurrence agency for the application in
relation to this matter.
Note: Part G of Form 1 is required to be
completed as the activity of removing quarry
material from a watercourse is also an
Environmentally Relevant Activity (ERA).
Does the application involve development for the removal of quarry material from a watercourse?
Tequiring an allocation notice under the Water Act 2000?
Rj No
(YES - complete Parts Kr and G of Form 1
5. The identified local government areas are: Aurukun, Bowen, Brisbane, Broadsound, Bundaberg, Burdekin, Burke, Burnett, Caboolture, Caims, Calliope, Caloundra, Cardwell, Carpentaria, Cook,
Cooloota, Dounglas, Fitzroy, Gladstone, Gold Coast, Hervey Bay, Hinchinbrooke, Isis, Johnstone, Livingstone, Logan, Mackay, Maroochy, Maryborough, Mirium Vale, Mornington, Noosa, Pine Rivers,
Redcliffe, Rediand, Rockhampton, Sarina, Thuringowa, Tiaro, Torres, Townsville, Whitsunday.
Australian Height Datum {AHD),
The declared ground water areas are listed in Guide 13 Development in a declared catchment area.
6
7
8 Referable dam is defined under the Water Act 2000,
9 Watercourse is defined in sch 10 of the IPA.
Page 3
Page 9
INTEGRATED PLANNING ACT 1997
Operational! work that is tidal work or
work in coastal management district
For more information refer to Guide 18. For
more information about prescribed tidal work in
local government tidal areas refer to Guide 24.
Unless you answered "none of the above” to Q9,
the application requires assessment by the
Environmental Protection Agency (EPA).
(fan agency other than EPA is the assessment
manager for the application, EPAisa
concurrence agency for the application in
relation to this matter.
Local government is the assessment manager
for all prescribed tidal work,
9.
IDAS Assessment Checklist, Version 20, 2 April 2007
The application involves operational work that is: ( tick the applicable bowes)
C1 (i) tidal work’ as defined under the Coasta! Protection and Management Act 1995 (the
Coastal Act) that is not prescribed tidal work - complete Part M of Form 1; or
C1 (ii) tidal work that is prescribed tidal work" other than in a canal? -complete Part P of Form 1;0r
(1 (iii) carried out within a coastal management district under the Coastal Act and for - complete
Part M of Form 1 if any boxes (a) to (i) below are ticked.
(1{a) constructing or installing works in a watercourse between MHWS and HAT (ie.
other than those works in tidal water) where the development has been determined not
to be assessable against the Water Act 2000 ;
Oo (b} constructing a canal12 intended to be connected to tidal waters;
(ec) constructing an artificial waterway;
(J (d) reclaiming land under tidal water;
C1 (e) disposing of dredge spoil or other solid waste material in tidal water;
CJ (f)” interfering with quarry material on State coastal land above high-water mark;
(1 (g) draining or allowing drainage or flow of water or other matter across State
‘coastal land above high-water mark;
(J (bh) removing or interfering with coastal dunes on land, other than State coastal land,
‘that is in an erosion prone area and above high-water mark;
CU (i) constructing a bank or bund wall to establish a ponded pasture on land, othe
than State coastal land, above high-water mark: or
[3 (iv) none of the above.
Operational work below high water
mark
For more infarmation reter to Guide 18. For
more information about prescribed tidal work in
local government tidal areas refer to Guide 24,
Untess you answered “none of the above’ to
Q10, the application triggers referral to
Queensland Transport (QT) (Maritime Safety
Qld) as a concurrence agency.
Local government is the assessment manager
for all prescribed tidat work.
10. The application involves operational work that is: ( tick the applicable box/es)
C1 (i) tidal work’ as defined under the Coastal Protection and Management Act 1995 (the
Coastal Act) that is not prescribed tidal work = complete Part M of Form 1; or
C1 (ii) tidal work that is prescribed tidal work'4 - complete Part P of Form 1; oF
(1 (ii) carried out within a coastal management district'S under the Coastal Act and for -
(1 (a) disposing of dredge spoil or other solid waste material in tidal water - complete Part
M of Form 7;
(1 (b) reclaiming land under tidal water - complete Part M of Form 1; or
(J (c)_ constructing a canal12, if the canal is associated with reconfiguring a lot -
complete Part M of Form 1; .
X (iv) none of the above.
Coastal management
For more information refer to Guide 48.
Unless you answered “none of the above" to
Q11, the application requires assessment by the
Environmental Protection Agency (EPA).
It an agency other than EPA is the assessment
manager for the application, EPA is a
concurrence agency for the application in
relation to this matter.
11,
The application involves: (tick the applicable box/es) .
C(i) a material change of use assessable under a planning scheme involving operational
work carried out completely or partly in a coastal management district*s
(J) (ii) a material change of use assessable under a planning scheme involving building
work, carried out completely or partly in a coastal management district that is —
« the construction of a new premises with a GFA" of at least 1000m?2
« the enlargement of the GFA of existing premises by more than 1000m2
C1 (ili) reconfiguring a lot assessable under schedule 8 of the IPA where the land is situated
oS completely or partly in a coastal management district
L{iv) reconfiguring a lot'” assessable under schedule 8 of the {PA and in connection with
the construction of a canal12 - complete Part M of Form 1
(v) none of the above
10 Tidal work is defined in sch 10 of the IPA.
11 Prescribed tidal work is defined in the Coastal Protection and Management Regulation 2003 and includes certain tidal works completely or partly within a local government tidal area,
12 Canal means canal as defined under the Coastal Protection and Management Act 1995 .
13 Tidal work is defined in sch 10 of the IPA.
14 Prescribed tidal work is defined in the Coastal Protection and Management Regulation 2003 and includes certain tidal works completely of partly within a local government tidal area.
15 Coastal management disticl is defined in sch 10 of the IPA and means a coastal management district under the Coastal Protection and Management Act 1995, other than an area declared as a ~
coastal management district under section 47{2} of that Act.
16 GFA Is defined in sch 14 of the IPA to mean the gross floor area. For a definition of haw lo catculated GFA, go to the planning scheme agains! which the application is being assessed.
17 Under $117 of the Coastal Protection and Management Act 1995, an application for reconfiguration, where the reconfiguration is associated with the construction of an artificial waterway, must be
accompanied by the application for the operationat works to construct the artificial waterway.
Page 4
Page 10
INTEGRATED PLANNING ACT 1997
Development within the limits of a
port
For more information refer to Guide 18. For
‘infermaticn about prescribed tidal work refer to
Guide 24.
Hyou answered "YES" to Q12, the appfication
tiggers referral to the Port Authority.
The Port Authority is.a concurrence agency if the
development is —
* ‘within 200m of a shipping channel or an entry
and exit shipping corridor for the port
© within 1000m of a swing basin, a commercial
shipping- wharf, a mooring, anchorage or spoil
grounds; - . 1
within 1000m of a planned port facility
Identified in a tand use plan approved under
the Transport infrastructure Act 1994.
in all other situation the Port Authority is an
advice agency.
Marinas
For more information refer to. Guide 18. For
information about whether a marina is prescribed
tidal work refer to Guide 24. The local
government is the assessment mariager for alll
prescribed tidal work.
If you answered "YES" to Q13, the application
triggers referral to Queensland Fire and Rescu
Service as an advice agency. :
12.
13.
IDAS Assessment Checklist, Version 20, 2 April 2007
Does the application involve development below high water mark’8 and within the limits of a port
under the Transport Infrastructure Act 1994?
NO
(DYES - complete Part M of Form 1, or Part P of Form 1 if the work is prescribed tidal work
Does the application involve operational work that is tidal work for a marina! with more than 6
- vessel berths? - :
[XINO |
[1 YES - complete Part M of Form 1, or Part P of Form 4 if the tidal work is prescribed tidal work
Tidal works in strategic port land.tidal
* areas
For fhore Information refer to Guide 18,
Unless you answeted “NO” to Q14, the relevant
Port Authority is the assessment manager for the
application and the Environmentat Protection
Ageney (EPA) and Queenstand Transport (QT)
are concurrence agencies for the apptication.
Heritage :
For further information refer. to Guide 19.
lf you answered “YES” to Q15, the application
triggers referral to the Queenstand.Heritage
Council as concurrence agency for the
application.
Unless you answered “none of the above" to
Qt5(b), the application invotves referral to the
Environmental Protection Agency as an advice
agency for the application
15.
Does the application involve tidal works within a strategic port land tidal area20?
[X] NO
oO YES - complete Part M of Form 1
Does the application involve development in a heritage registered place as defined under the
Queensland Heritage Act 1992?
NO :
[1 YES - complete Part C of Form 1
15(b)The application involves: (tick applicable boxes)
(i) a material change of use assessable against the planning scheme and the lot shares a
common boundary with a protected area or registered place under the Queensland
Heritage Act 1992;
Oi iii) reconfiguring a lot if the lot shares a common boundary with a protected area or
registered place under the Queensland Heritage Act 1992;
Ci (iii) none of the above.
Declared catchment areas
For more information, including a list of the
dectared catchment areas within Queensland,
Fefer to Guide 13,
Uniess you answered “none of the above” to
Q16, the application requires assessment by the
Department of Natural Resources and Water
(NRW).
if an agency other than NRW is the assessment
manager for the application, NRW is a
concurrence agency for the application in
relation to this matter.
16.
The application is in an area declared to be a catchment area under the Water Act 2000 and
involves: {tick the applicable boxes)
Ci (i) reconfiguring a lot if any lot resulting from the reconfiguration is less than 16 hectares;
QO (ii) devetopment assessable against the planning scheme involving the establishment or
expansion of a waste water disposal system, other than a disposal system for carrying
out an environmentally relevant activity under the Environmental Protection Act 1994:
XJ (iii) none of the above
18 High water mark-is defined in the Coastal Protection and Management Act 1995 and means the ordinary high water mark at spring tide,
19 Marina is defined in the Transport Operations (Maritime Pollution} Regulation 1995.
20 Strategic port land tidal areas are the areas generally 50 metres seaward of high water mark adjacent to strategic port land,
Page 5.
Page 11
INTEGRATED PLANNING ACT 1997
IDAS Assessment Checklist, Version 20, 2 Aprit 2007
infrastructure
Applications involving development on tand
designated forcommunity infrastructure may
trigger this referral.
For more information refer to schedule 2 of the
IP Regulation.
If you answered “YES" to Q19, the application
fequires assessment by the chief executive of
the department administering the Act authorising
the development for the designated purpose.
If an agency other than the designator is the -
assessment manager for the application, the
designating agency will be a concurrence
agency for the application in relation to this
mater.
Contaminated land 17. The application involves: (tick the applicable box/es)
Applications involving material change of use F 2 7 - _
andl or reconfiguring a lt may tioger this Oi reconfiguring alot for which all of part of the premises are
referral, (a) premises mentioned in the IPA, schedule 8, part 1, table 2—
For more information refer to Guide 5. « item 5, including the exemption otherwise provided for by paragraph (d);
Unless you answered “none of the above" to + item 6, including the exemption otherwise provided for by paragraph (e); or
Q17, the application requires assessment by the ei i i i i i ini ivi
imental Protection Agency (EPA). tan tem 7, including the exemption otherwise provided for a mining activity or petroleum
agency other than EPA is the assessment s vity, or . . .
manager for the application, EPA wil! be a (b) in an area for which an area management advice has been given for unexploded
Concurrence agency for the application in ordnance - complete Part N of Form 1 .
felation to this matter. a .
Di (ii) a material change of use -
(a) made assessable under the IPA, schedule 8, part 1, table 2, items 5 to 7; or
(b) assessable against the planning scheme and if all or part of the premises is in an area
. for which an area management advice has been given for unexploded ordnance -
complete Part N of Form 1
/ reat (iii) none of the above
Electricity infrastructure 18. The application involves: (tick the applicable box/es}
For more information refe to Schedule 2of the [P LI (i) reconfiguring a lot where any part of the lot is ~
« subject to an easement in favour of a distribution entity or transmission entity under the
. Unless you answered “none of the above’ to
18, the application triggers referral to the Electricity Act 1994 and the easement is for a transmission grid or supply network under
agency to which the easementis granted In that Act; or : @
favour of as advice agency. « situated within 100m of a substation site;
Di (ii) a material change of use, assessable against a planning scheme and not associated
with reconfiguring a lot if -
* any part of the premises is subject to an easement in favour of a distribution entity or
transmission entity under the Electricity Act 1994 and the easement i is for a transmission
grid or supply network under that Act; and - .
+ any structure or work that is the natural and ordinary consequence of the use is, or will be,
located wholly or partly in the easement;
Li (iii) a material change of use, assessable against a planning scheme and not associated
with reconfiguring a lot if any part of the premises is situated within 100m of a substation —
site;
C1 (iv) operational work that is filing or excavation assessable against the planning scheme,
not associated with reconfiguring a lot, if -
* any part of the premises is subject to an easement in favour of a distribution entity or
transmission entity under the Electricity Act 1994 and the work is located wholly or partly in
the easement;
« the work is located wholly or partly within 10m of a substation site;
(v) none of the above.
Land designated for community 19. Does the application involve development assessable against the planning scheme and on nl
designated for community infrastructure?
(i) intended to be supplied by a public sector entity; and
{ii} on land not owned by or on behalf of the State; and
(iii) other than development -
{a) for the designated purpose; or
(b) carried out by, or on behalf of, the designator.
bs] NO
Cl yYes
Page 6
Page 12
INTEGRATED PLANNING ACT 1997
SEQ Regional Pian
For more information refer to schedute 2 of the
IP Regulation.
Refer to Chapter 2, part 5A and schedule 10 of
the Intecrated Planning Act 1997, and schedule
2 af the Regulatory Provisions for relevant
definitions.
Unless you answered “none of the above’ to
Q20, the application requires assessment by the
Office of Urban Management (OUM).
Fisheries matters
For more information refer to schedule 2of the 1P
_ Regulation.
Unless you answered “none of the abave” to
* Q21, the application requires assessment by the
Department of Primary Industries and Fisheries
(OPI8F),
If an agency other than DPI&F is the assessment}
Manager for the application, DPI&F is a
concurrence agency for the application in
telation to items (i) - (iv) and an advicé agency
in retation to iter {v).
IDAS Assessment Checklist, Version 20, 2 April 2007
20. The application involves (tick applicable box/es) - ,
J (i) a material change of use of premises —
(a) ina Major Development Area in the Urban Footprint for -
DD (i) anurban activity -
(1 inan area included in a structure plan where the IPA, section 3.1.6
applies;
(11 in an area not included in a structure plan where -
" the IPA, section 3.1.6 applies to the application for the material change
of use; or
the premises exceeds 10,000m2; or
« the gross floor area (GFA) on the premises will exceed 10,000m2; or
+ impact assessment is required under the relevant planning scheme
C1 (ii) intensive animal husbandry, or
~ £) (iii) residential development involving a rural residential purpose
(b) in the Regional Landscape and Rural Production Area for -
C) (i) an urban activity and not specified in section 2.4(2); or
(1 (ii) residential development involving a rural residential purpose and not
specified in section 2.6(2)
(c) in the Rural Living Area for an urban activity and not specified in section 2.8(2);
(d) in the investigation Area for -
C) () anurban activity and not specified in section 2.10(2);
1 (ii) residential development involving a rural residential purpose and not _
specified in section 2.12(2); or
J (ii) intensive animal husbandry
CJ (ii) reconfiguring a tot-
On land in a Major Developnient Area in the Urban Footprint that is:
(a) not included in a structure plan; and
(b) not specified in section 3.1(2).
The application involves: (tick the applicable box/es)
LD (i) an assessable material change of use for aquaculture - complete Part Os of Form 1;
C1 (ii) assessable operational work that is the construction or raising of a waterway barrier -
complete Part O3 of Form 1;
assessable operational work completely or partly within a declared fish habitat area.
(iii) none of the above
21,
Di
complete Part O2 of Form 1;
(C1 (iv) assessable operational work that is the removal, destruction or damage of a marine
plant - complete Part O2 of Form 1;
[1 (v) development assessable under the IPA, schedule 8, part 1, on land that adjoins a
declared fish habitat area;
(vi) none of the above.
Page?
Page 13
INTEGRATED PLANNING ACT 1997
Integration of land use and public
transport
For more information refer to Guide 23, schedule
8A of the IPA, & schedule 2 of the [P Regulation.
Unless you answered “none of the above’, the
application triggers referral to QT as a
concurrence agency.
22. The application involves: (tick the applicable box/es)—
C1 (i) a material change of use assessable against the planning scheme for a purpose
IDAS Assessment Checklist, Version 20, 2 April 2007
mentioned in schedule 13C of the IP Regulation and exceeding the thresholds set by that
schedule.
(1 (ii) reconfiguring a fot—
(1a) ontand that is completely or partly within a apublic transport corridor, and the
total number of lots increases;
(1 (b) on land that is completely or partly within a future public transport corridor or
an airport's public safety area;
(0c). on land that is within 400m of a public passenger transport facility or a future
public passenger transport facility, and the total site area is 5000m? or greater;
(1)(d) . for a residential purpose within the 25 ANEF contour for an airport;
((e) _ for a residential purpose resulting in 100 or more allotments.
CO (iii) operational work assessable against the planning scheme, but not associated with a
material change of use mentioned in (i) above or reconfiguring a lot mentioned in (ii)
above, on land that—
(1 (a) is completely or partly within a public transport corridor or a future public
transport corridor;
(J) (b) will result in work that encroaches into an airport's operational airspace.
I (iv) none of the above.
Railway safety and efficiency
For more information refer to Guide 23, schedule
_ 8A of the IPA & schedule 2 of the IP Requlation.
Unless you answered “none of the above", the
application triggers referral to QT as a
concurrence agency.
23.
The application involves: (tick the applicable box/es)—
( (i) a material change of use assessable against the planning scheme for a purpose
mentioned in schedule 13D of the IP Regulation and exceeding the thresholds Set by that
schedule.
CI (ii) reconfiguring a fot—
(J (a) onland that is completely or partly within a future public transport corridor,
future railway land or a railway tunnel easement;
(4 (b) on land that is within 400m of a Citytrain passenger railway station or a future
Citytrain passenger railway station, and the total site area is 5000m? or
greater;
: {J (c) on land that abuts rail corridor land, commercial corridor land or future railway
land, and the total number of lots increases;
(Jd) on tand that abuts rail corridor fand, commercial corridor land or future railway
Jand and an easement abutting the corridor or future railway land is created;
L1(e) on land that is completely or partly within 100m of, and abutting an approach
to, a railway level crossing, and the total number of lots increases;
[4 (f) for a residential purpose resulting in 100 or more allotments.
( (iii) operational work assessable against the planning scheme, but not associated with a
material change of use mentioned in (i) above or reconfiguring a lot mentioned in (ii)
above, involving extracting, excavating or filling greater than 50m’, on land that—
(] (a) _ is completely or partly within rail corridor land or commercial corridor land, and
the work is not for rail transport infrastructure or other rail infrastructure;
[1 (b) _ is completely or partly within future railway land, or a railway tunnel easement;
[J (c) abuts rail corridor land, commercial corridor land or future railway land, and
. the work is within 25m of the railway boundary.
(iv) none of the above.
Moonie to Brisbane pipeline
For more information refer to schedule 2of the IP
Regulation.
Unless you answered “none of the above”, the
application triggers referral to the halder of
pipeline licence No 1 issued under the Petroleum!
Act 1923, currently Santos QNT Pty.Ltd, for
advice.
24.
The application involves the easement for the construction or operation of the Moonie to
Brisbane strategic pipeline, and involves: (tick the applicable box/es)—
(1 (i) a material change of use assessable against the planning scheme and not associated
with reconfiguring a lot, and any structure or work will be located wholly or partly in the
easement.
C1 (ii) reconfiguring a lot
C1 (ii) operational work assessable against the planning scheme, that is filling, excavation,
compaction, drilling, boring or piling not associated with a reconfi iguring alot, and the
work is focated wholly or partly in the easement.
[sd (iv) none of the above.
Page 8
Page 14
INTEGRATED PLANNING ACT 1997 Koala habitat area For more information, refer to Guide 26 and schedule 2 of the IP Reavtation. Unless you answered “none of the above”, the application requires referral to the Environmental Protection Agency as a concurrence agency. : IDAS Assessment Checklist, Version 20, 2 April 2007 25. The application involves: (tick the applicable box/es}— OD (i) a material change of use of premises in a koala conservation area or koala sustainability area made assessable under a planning scheme, that is not for a domestic activity and will result in - . (1 (a) clearing of native vegetation over an area greater than 2500m?; (1 (b) anew building and any reasonably associated structure with a total footprint greater than 1000m2; (J (c) an extension to an existing building and any reasonably associated structure if the extension has a total footprint greater than 1000m2; (1 (4) extracting gravel, rock or sand from an area greater than 5000m?; LT (e) excavating or filling an area greater than 5000m?; (1 (f) additional traffic in a koala conservation area or koala sustainability area, between 6p.m. on a day and 6a.m. on the following day. Li (ii) reconfiguring a fot in a koala conservation area or koala sustainability area that will result in - (1 (a) an increased number of lots; . (J (b) “clearing of native vegetation over an area greater than 2500m?. (C1 (iii) operational work ina koala conservation area or koala sustainability area made assessable under Schedule 8, Part 1, Table 4, items 1A to 1G (not associated with reconfiguring a lot mentioned in (ij) above) that will result in the clearing of native vegetation over an area greater than 2500m?. 1 (iv) operational work in a koala conservation area or koala sustainability area made assessable under a planning scheme (not associated with a material change of use mentioned in (i) or reconfiguring a lot mentioned in (ii) above) that is not for a domestic activity and will result in - L (a) clearing of native vegetation over an area greater than 2500m?; (1 (b) extracting gravel, rock or sand from an area greater than 5000m?; Lc) excavating or filling an area greater than 5000m2, (v) none of the above. Wild river area For more information, refer to Guide 27 If you answered YES to 026, you must also complete section 2 of this checklist. This witt enable you to determine if your application can proceed in a wild river area and which referral agency will assess your application against the Wild Rivers Cade, or if the proposed development is “prohibited” in a wild river area. Note: Development can be ‘prohibited’ in a wild river area because the application cannot be accepted by the assessment manager. 26. Does the application involve development in a wild river area declared under the Wild Rivers Act 2005? Preliminary Approval If you answered YES to 027, the application triggers referral to the Department of Local Government, Planning, Sport and Recreation as an advice agency. 27. Does the application involve a development for which preliminary approval is sought under Section 3.1.6 of the integrated Planning Act 1997? IF INe) : Cl Yes Wetlands Domestic activity means the construction or use ofa single residence on a lot and any reasonably associated building or structure. Examples of a building or structure that could be reasonably associated with a single residence include: caretaker's residence, granny flat, building or structure used for a home business. Note: Wetland is defined in the integrated Planning Regulation 1998, Unless you answered “none of the above" to Q28, the application involves referral to the Environmental Protection Agency as an advice agency for the application. 28. The application involves: (tick the applicable boxes) - (1 (i) — amaterial change of use, other than for a domestic activity, assessable against the planning scheme that is in or within 100m of a wetland; C1 (ii) reconfiguring a tot - In or within 100m of a wetland that will result in C1 (a) more than 10 lots being created; or 1 (b) lots tess than 5 hectares; ® (ii) none of the above Page 9
Page 15
INTEGRATED PLANNING ACT 1997, Conservation Estate Urban purposes is defined in the Integrated Planning Act 1997 as “purposes for which land is used in cities of towns, including residential, industrial, sporting, recreation and commercial purposes, but not including environmental, conservation, rural, natural or wildemess area purposes”. Unless you answered “none of the above" to Q29, the application involves referral to the Environmental Protection Agency as an advice agency for the application. IDAS Assessment Checklist, Version 20, 2 April 2007 29. The application involves: (tick the applicable box/es}— C1 (i) a material change of use for urban purposes that is in or within 100m of any of the following - O(a) aprotected area, forest reserve, critical habitat or area of Major interest under the Nature Conservation Act 1992;; , (11 (b) a State forest or timber reserve under the Forestry Act 1959; C1 (c) amarine park under the Marine Parks Act 2004; (1 (d) arecreation area under the Recreation Area Management Act 1988; (1 (e) aworld heritage area listed under the World Heritage Convention; (1 (f) Brisbane forest park under the Brisbane Forest Park Act 1977. O1 (ii) reconfiguring a lot if - (1 (@) any part of the lot is situated in, or within 100m of, any of the following - (1 (i) — aprotected area, forest reserve, critical habitat or area of major interest under the Nature Conservation Act 1992; (CJ (ii) a State forest or timber reserve under the Forestry Act 1959; C1 (ili) amarine park under the Marine Parks Act 2004; (I (iv) arecreation area under the Recreation Area Management Act 1988; CJ) aworld heritage area listed under the World Heritage Convention; Brisbane forest park under the Brisbane Forest Park Act 1977; and (11 (b) the reconfiguration involves more than 10 lots being created, or any lot e@ resulting from the reconfiguring is less than 5ha; (iii) none of the above. Page 10
Page 16
INTEGRATED PLANNING ACT 1997
SECTION 2 - ASSESSMENT IN A . WILD RIVER AREA — a
IDAS Assessment Checklist, Version 20, 2 April 2007
(completion mandatory if he proposed development i is located i in a wild river area) —_ . = |
Wild River Area
It the responsibility of the applicant to
detennine if the development is proposed in
a wild river area,
Information about wild river areas inctuding the
geographicat location and position of
management areas in relation to propefties, can
be accessed by contacting the Department of
Natural Resources and Water (NRW), accessing
the department's website www.nrw.qid.gov.au or
contacting the department by email on:
wild [email protected]
Note on Referrals
Referrals for development in a wild river area
(other than for agricultural activities and animat
husbandry activities) are not changed from the
-existing referral arrangements.
Notes on development assessable
against the Wild Rivers Code
For information regarding development in a wild
fiver area, see the relevant wild river declaration
and Guide 27. The relevant wild river
declaration will provide information regarding
which types of development must be assessed
against the Wild Rivers Code, and in some
cases which types of development are exempt
from wild river requirements.
The notes on development assessable against
the Wild Rivers Code in this section of the
checklist provide some guidance however this
may vary between wild fiver areas. The relevant
declaration will provide the information applying
to each wild river area.
Applications for some new developments will not |
be accepted if the proposed development is ina
high preservation area (HPA). Most appfications
for development activities which may be made
including those in a preservation area (PA), must
be assessed against and must comply with the
Witd Rivers Code where indicated in a relevant
wild river declaration.
1.
Which wild river area is the development proposed in?
The proposed development is to.be located in: (tick the applicable box/es)
(1) a high préservation area (HPA);
(ii) a preservation area (PA) ; .
Oo iti) a wild river floodptain management area (FMA);
oO iv) a wild river nominated waterway,
(1) v) a designated urban area (DUA).
Environmentally relevant activities
({ERAs) in a designated urban area
Ifyou answered YES, your application fer an
ERA is exempt from any wild river requirements
and provided there are no other aspects of this
development that require assessment against
wild rivers, you do not need to complete the
Temaining questions in Section 2.
Ifyou answered NO to Q2, please complete the
femaining questions in Section 2.
2.
Does the proposed development only involve any of the following environmentally relevant
activities (ERAs) in a designated urban area (as mapped in the relevant wild river declaration)?
i) An ERA 28 or ERA 14; or
ii) A level 2 ERA except ERA 1, 2, 3, 4, 20, 22 or 59.
Cno | YES {ensure you have completed Part G of Form 1)
Clearing native vegetation
If YES, there are a limited number of purposes
for which an application to clear native
vegetation may be accepted in a HPA. See
Guide 27 for a jist of relevant purposes for
which an application may be made in a HPA.
if YES and you ticked Q4 box i) the application
may be made and is assessable against the Wild
Rivers Code. If YES and you ticked Q4 box ii)
the application will not be accepted.
Note: If clearing native vegetation is in a PA,
there are no wild fiver requirements and
provided there are no other aspects of this
development where wild river requirements
apply, do not complete the remaining questions
in Section 2.
Is the application operational work for clearing native vegetation in a HPA?
O NO | YES (ensure you have completed Part J of Form 1)
If YES, is the clearing?
O i) clearing regrowth (as defined in the Vegetation Management Act 1999) in a registered
area of agriculture in a HPA (see Guide 27); or
Ol ti) in a HPA outside a registered area of agriculture?
Page 11
Page 17
INTEGRATED PLANNING ACT 1997
Works in tidal areas, coastal
management districts and fish habitat
areas
If you answered YES to Q5, and ticked any
boxes in Q6), your application is required to be
assessed against and must comply with the Wild
Rivers Code.
lf you answered YES to Q5 and ticked box i} in
Q6, your application is required to be referred to
the EPA.
Note: If specified works are proposed in a local
goverment area, it is prescribed tidal work - the
relevant local government will be the
assessment manager with the EPA as a
coneurrence agency
if you answered YES to Q5, and ticked box i) or
iil) in Q6, your application requires referral to
OPIF.
if you answered NO to O5 and ticked box j) in
Q6, the application will not be accepted.
If you answered NO to Q5, ticked box ii} in Q6
and the development is necessary to install
authorised works or infrastructure where a
development permit is not required, or if a
Fequired permit is held, the application must be
assessed against and must comply with the Wild
Rivers Code. Applications for purposes other
than specified works or as described above will
Not be accepted.
{f you answered NO at Q5 and ticked box iil) in
Q6, the application may be made if the works are
ina PA. These applications must be assessed
against and must comply with the Wild Rivers
Code. The application will not be accepted if the
development is proposed to be located in a HPA.
For more information about specified works refer
to Guide 27
IDAS Assessment Checklist, Version 20, 2 April 2007
Is the development for specified works? (see definition in the Wild Rivers Act 2005 and Guide 27-
Development in a wild river area)
(no Clyes
The application is for one or more of the following:
0 i) Operational works that is tidal works or works in a coastal management district (ensure you
have completed Part M and/or Part P of Form 1); of
oO ii} Operational works for the removal, destruction or damage of marine plants (ensure you have
completed Part O2 of Form 4); or
(7 ili) Buitding or operational works in a fish habitat area (ensure you have completed Part Oz of Form 1).
Residential, commercial or industrial
development
If you answered YES to Q7, your application is
Not subject to wild river requirements. Provided
there are no other aspects of this development
that require assessment against the relevant wild
river declaration or Wild Rivers Code, you do not
need to complete the remaining questions in
Section 2.
if you answered NO to Q7 and ticked either box
#} or ii) in Q8, the assessing agency is the
relevant toca! govemment, The application must
be assessed against and must comply with the
Wild Rivers Code.
8.
ls the application for residential, commercial or industrial development in a designated urban
area?
(no Dyes
If NO, does the application for residential, commercial or industrial development involve:
Ol i) a material change of use made assessable in a local government planning scheme
(ensure you have completed Part D of Form 1); or
im it) operational works associated with reconfiguring a lot (ensure you have completed Part F
of Form 1}.
Animal husbandry activities
If you answered YES to Q9 your application
requires assessment against and must comply
with the Wild Rivers Code.
The assessing agency is NRW.
Note: Applications for animal husbandry
activities will not be accepted if proposed in a
HPA. For more details and a definition of animal
husbandry activities see the Wikd Rivers Act
2005 and refer to Guide 27.
Does the application involve a material change of use for animal husbandry activities (as defined
under the Wild Rivers Act 2005) in a PA?
NO Oo YES (ensure you have completed Part R of Form 1)
Agricultural activities
if you answered YES to Q10, your application
requires assessment against and must comply
with the Wild Rivers Code.
The assessing agency is NRW.
Note: Applications for agricultural activities will
hot be accepted if proposed in a HPA. For more
details and a definition of agricultural activities
see the Wid Rivers Act 2005 and refer to Guide
27.
The production of fodder in a PA, and pasture
improvement using low impact soil disturbance
fechniques Is not an agricultural activity as
defined under the Wid Rivers Act 2005. For
more infomation see Guide 27.
10.
Does the application involve agricultural activities (as defined under the Wild Rivers Act 2005) in
a PA?
O NO (1 YES (ensure you have completed Part Q of Form 1)
lf YES is the application for:
(1 i) a material change of use; or
LJ ii} operational works.
Page 12
Page 18
INTEGRATED PLANNING ACT 1997 Works that take overland flow water The relevant wid river dectaration wil state works that take overland flow water are either self assessable or assessable, or are exempt from wild river requirements. you tcked Q13 i), your appfication must be assessed by NRW against the Wild Rivers Code and must comply with the code. If you ticked Q13 i) an application is not required to be made however the works must comply with the relevant self-assessable section of the Wild Rivers Code, otherwise the works become assessable development for which an application is required and must be assessed by NRW against the relevant part of the Wild Rivers Code and must comply with the code. if you ticked Q13 il) your application is not subject to wild river requirements. Applications for development that Is other than that stated to be assessable, self-assessable or exempt will nat be accepted. Works that interfere with overland flow water ‘The relevant wild river declaration wilt state works that interfere with overland flow water that jare either sélf assessable, assessable or exempt from wild river requirements, Wt you ticked Q15 i), your application must be assessed by NRW against the Wild Rivers Code and must comply with the code. if you ticked Q15 ii) an application is not required to be made however the works must comply with the relevant setf-assessable section of the Wild Rivers Code, otherwise the works becarne assessable development for which an application is required and must be assessed by NRW against the relevant part of the Wild Rivers Code and must comply with the code. If you ticked Q15 ili) your application is not Subject to wild river requirements. Applications for development that is other than that stated to be assessable, self-assessable or ‘exempt will not be accepted. 12. 13. IDAS Assessment Checklist, Version 20, 2 April 2007 Does the application involve works that take overland flow water in a HPA or an FMA? Co NO O YES (ensure you have completed Part Ks of Form 1) If YES, is the application for works stated in the relevant wild river declaration to be? (_J i) assessable works ‘ ‘ O ii) self-assessable works (J it) exempt works Does the application involve works that interfere with overland flow water in a FMA? CJNno (1 YES (ensure you have completed Part Kyo of Form 1) If YES, is the application for works stated in the relevant wild rivers declaration to be? (J i) assessable works , (J ii) self-assessable works | iit) exempt works Waterway barrier works Applications for building or raising waterway barrier works in a HPA will not be accepted. Ifyou answered YES.to Q16, your application Must be assessed by OPIF against the Wild Rivers Code and must comply with the code. 16. Does the application involve building or raising waterway barrier works in a PA? O NO O YES (ensure you have completed Part Os of Form 1) Aquaculture (non ERA} Applications for aquaculture in a HPA will not be accepted. Ifyou answered YES to Q17, your application must be assessed by DPIF against the Wild Rivers Code and must comply with the code. Does the application involve aquaculture in a PA? Oo NO Ces (ensure you have completed Part O1 of Form 1) Works that interfere with water in a watercourse Note: If the development is proposed in a HPA, apptications for alt works that interfere with water in a watercourse (including dams or weirs, stream realignment or stream diversion) will not be accepted. tna PA, applications for instream dams and weirs may be accepted in nominated waterways. If you ticked box ii) in Q19, your application will Not be accepted. Note: Operational works outside a HPA or nominated waterway are not subject to wild river requirements. More information and locations of nominated waterways Is available by contact NRW, accessing the department's website www. now.ald.gav.au or contacting the department by email on: wild [email protected] the application involve operational works that interfere with water in a watercourse that is in a nominated waterway in a PA? Lino LJyYes (ensure you have completed the relevant Part K of Form 1) If YES, (_]}) The application is for an instream dam or weir; or Oj il) The application is for operational works that interfere with water in a watercourse, and is for development other than a dam or weir. Page 13
Page 19
INTEGRATED PLANNING ACT 1997
Environmentally relevant activities
Most applications for an ERA in a HPA will not
be accepted, Applications which may be made
require referral to the EPA. The assessment of
some ERAs is assessed by NRW, others have
been devolved to DPIF, NRW or delegated
local government (see EPA website for more
information on devolved ERAs)
Ifyou answered NO to Q20 you do not need to
complete Qs 21-24.
{fyou answered YES to Q20 and the
development is in a PA, your application must be
assessed by the administesing authority2*
against the Wild Rivers Code and must comply
with the code, unless the proposal is for
development where an application will not be
accepted, or is exempt from wild river
requirements (see Q2). You will be able to
determine if an application will not be accepted
for the development by answering 021 - Q24.
If you answered NO to Q21, you do not need to
complete Q22. Hf you answered YES to Q21 you
are required to complete Q22.
ff you answered NO to Q22, the application will
not be accepted. If you answered YES to Q22,
the application must be assessed by NRW
against the Wild Rivers Code and must comply
with the code.
If you answered NO to Q23 and the development;
is proposed in the HPA the application will not be
accepted. H you answered YES to Q23, the
application must be assessed by the EPA or
NRW (as prescribed in schedule 8A of the IPA)
against the Wild Rivers Code and must comply
with the code.
Ifyou answered YES to 024 the application will
not be accepted. If you answered NO to Q24,
your application must be assessed by NRW
against the Wild Rivers Code and must comply
with the code.
Exempt ERAs in a designated urban
area
If the development is proposed in a designated
urban area there may be no wild river
requirements, See Section 2 Q2.
Note; All applications that can be accepted must
be assessed against and must comply with the
Wild Rivers Code (other than exempt ERAs ina
designated urban area).
20.
21,
22.
23.
24,
IDAS Assessment Checklist, Version 20, 2 April 2007
Doés the application involve an ERA?
O NO O YES (ensure you have completed Part G of Form)
Is the application for an ERA 20 instream?
Cno Clyves
Is a quarry allocation notice held for the proposed ERA 20 instream?
Cino Dyes
Does the application involve any of the following in a HPA?
i) a level 2 ERA 11, (and is for specified works or a residential complex)
il) an ERA 49 (dredging)
iii) Low impact ERA 20 (out of stream) for specified works or a residential complex (as defined in
the Wild Rivers Act 2005, and Environmental Protection Act 1994)
iv) an ERA 22 (out of stream)
[no Clyes
Is the proposed development for ERA 20 (out of stream) and;
=~ inaFMA; and
— not low impact; and
— not for a residential complex in the area, or for specified works,
Cno Dyes
Documentation
If you answered NO to Q25, your application
may be subject to an information request and
processing of the application may be delayed.
25.
Has documentation been included with the application describing how the applicant proposes t
comply with the mandatory requirements, required outcomes, and/ or performance requirement
as set out in the relevant part/s of the Wild Rivers Code?
(no ClyYes
2' The administering authority may be either the EPA, or if devolved or delegated, the local goverment, DPIF or NRW.
Page 14
Page 20
INTEGRATED PLANNING ACT 1997
IDAS Assessment Checklist Version 20, 2 a 2007
SECTION 3 - BUILDING REFERRALS (compietion not mandatory) os
Below is a list of the referrals that can apply to an application for building work assessable against the Building Regulation 2006. This section of the IDAS
Assessment Checklist is provided for advice only. This section of the IDAS Assessment Checklist is not required to be completed and lodged with an
application for building work assessable against the Building Regulation 2006 only.
Special fire services - generally
For more information qa to schedule 2 table 1 and
schedule 2A of the [P’Requiation.
Assessment period 15 days. No response is a
deemed refusat. :
1.
An application may trigger referral to Qld Fire and Rescue Services as an advice agency if the building work
Tequires special fire services mentioned in schedule 2A part 1 of the Integrated Planning Regulation 1998
(IP Regulation) or includes an alternative solution assessed against the performance requirements of the
Building Code of Australia.
For more information go to schedute 2 of the {P
Reaulation
Fire safety for budget accommodation |2. An application may trigger referral to Qld Fire and Rescue Services as an advice agency if the building work
rer more information go to schedule 2 of the IP the subject of the application requires the installation of a fire safety system for a budgel accommodation
Reaulation building.
Spray painting 3. An application may trigger referral to the Department of industial Relations (DIR) as a concurrence agency
For more information go to schedule 2 of the IP if the application involves a workplace incorporating spray painting.
Regulation
Retail meat premises 4. An application may trigger referral to Safe Food Qld as a concurrence agency if the application involves a
For more information go to schedule 2 of the IP tetail meat premises.
Regulation .
Private health facilities 5. An application may trigger referral to the Department of Health as a concurrence agency if the application
For more information go to schedule 2 of the IP involves a private health facility.
e=
Workplace area less:than 2.3m? 6. An application may trigger referral to the Department of Industrial Relations (DIR) as an advice agency if the
For more information go to schedule 2-of the IP application involves a work place area less that 2.3m?.
Regulation
Land contiguous to a State-controlled |7, An application may trigger referral to the Department of Main Roads as a concurrence agency or advice
| road . agency if the application involves land contiguous to a State-controlled road.
For more information go to schedule 2 af the IP .
Regulation :
| Pastoral workers accommodation 8. An application may trigger refesrat to the Department of Industrial Relations (DIR) as a concurrence agency
For more information go to.schedule 2 of the IP if the application involves pastoral workers accommodation.
Regutation
Child care centre 9. An application may trigger referral to the Department of Communities as a concurrence agency if the
or more information go to schedule 2 of the IP application involves a childcare centre.
Coastal development 10. An application may trigger referral to the Environmental Protection Agency (EPA) as a concurrence agency
ror more information go to schedule 2 of the IP if the application involves tand completely or partly seaward of a coastal building line?2,
Heritage 11. An application may trigger referral to the Heritage Council as a concurrence agency if the application
For more information go to schedule 2 of the |P involves a heritage registered place.
Regulation : :
Fisheries matters 12. An application may trigger referral to the Department of Primary Industries and Fisheries (DPI&F) as a
For mare information go to schedule 2 of the IP concurrence agency if the application involves assessable building work in a declared fish habitat area; or
Regulalion as an advice agency if the application involves assessable building work on Sand that adjoins a declared fish
habitat area.
Integration of land use and public 13. An application may trigger referral to Queensland Transport as a concurrence agency if the application
transport involves existing or future public transport corridors, or airport operational airspace??.
For more information go to schedute 2 of the IP
Reaylation
Railway safety and efficiency 14. An application may trigger referral to Queensland Transport as a concurrence agency if the application
involves future railway land.
NOTE: CONCURRENCE AGENCY ASSESSMENT PERIODS
The local government, as the concurrence agency, is required to assess and provide a response for the following building applications within a prescribed
time. For applications relating to design and siting (17, 18 & 19), and building work for removal or rebuilding (23), the assessment periad is 5 days. For all
other applications the assessment period is 15 days. If no response is received from the local government for an application, it is taken to be a deemed
refusal. However for amenity and aesthetics impact of particular building work for a single detached class 1a or class 10 building or structure (15), no
response is taken to be a deemed approval.
Amenity and aesthetic impact of
particular building work for single
detached class 1 building or class 10
building or structure
For more information go to schedule 2 table 1 of the
IP Regulation.
Assessment period 15 days. No response is a
deemed approvat.
15.
An application will trigger a referral to the local government if it is :
© for asingle detached ciass 1 building or class 10 structure; and
¢ the local government has declared by resolution the following:
— the appearance of the building or structure will have an extremely adverse impact ¢ on the amenity of
the locality; and
— the appearance of the building or structure would be in extreme conflict with the character of the
locality.
2 Coastal building lines are prescribed under the Coastal Protection and Management Act 1995.
2 Operational airspace is as defined in State Planning Policy 102 "Development in the Vicinity of Certain Airports and Aviation Facilities’.
Page 15
Page 21
INTEGRATED PLANNING ACT 1997
IDAS Assessment Checklist, Version 20, 2 April 2007,
Whether particular buildings maybe | 16. An application to use an existing building that is not class 1, 2, 3 or 4 for residential purposes may trigger a
occupied for residential purposes referral to the local government as the concurrence agency.
For more information go to schedule 2 table 1 of the
IP Regutaton.
Assessment period 15 days. No response is a
deemed refusal. -
Design and siting 17. An application may trigger referral to the local government as the concurrence agency if the building work
For more information go to schedule 2 table 1 of the does not comply with the performance criteria of parts 11 and 12 of the Queensland Development Code,
JP Regulation. 18. An application may trigger referral to the local goverment as the concurrence agency if the building work
Assessment period 5 days. No response is a does not comply with the qualitative statement for building clearance and site cover.
deemed refusal. 19. An application may trigger referral to the local government as the concurrence agency if the building work
. does not comply with the qualitative statement for performance criteria 4, 5, 7, 8 or 9 of the Queensland
Development Code, part 11 or 12.
Fire safety in particular budget 20. An application may trigger referral to the local government as the concurrence agency to determine the
accommodation buildings building will comply with the fire safety standard under the Building Act 1975 when the building work has
For more information go to schedule 2 table 1 of the been completed.
IP. Regulation. .
Assessment period 15 days. No response is 2
deemed refusal. -
Higher risk personal appearance 21. An application may trigger referral to the local government as the concurrence agency to determine if the
services building work ;
For more information go to schedule 2 table 1 of the * complies with the performance criteria of the Queensland Development code part 15; and .
IP Reaylation and the QDC part 15. ¢ the work does not comply with an acceptable solution stated in the part. ]
Assessment period 15 days, No response is 2
daemed refusal. .
Building work for residential service | 22. An application for building work for premises in which residential care service under the Residential
For more information go to schedule 2 table 1 of the Services (Accreditation) Act 2002, section 4, is conducted, or is proposed to be conducted, will trigger
{P Regulation and the QOC part 20. referral to the local government as the concurrence agency. .
Assessment period 15 days. No response is a
deemed refusal,
Building work for removal or 23, An application for the removal and/or rebuilding at another site of a building or other structure, wil trigger
rebuilding referral to the local government as the concurrence agency.
For more information go to schedule 2 table 1 of the
1P Regulation.
Assessment period 5 days. No response is a
deemed refusal.
Building work for rainwater tank in 24. An application may trigger referral to the local government as the concurrence agency to determine if the
designated rainwater tank area
For more information go to schedule 2 table 1 of the
IP Requlation and the QOC part 25.
Assessment period 15 days, No response is a
deemed refusal.
building work or structure complies with the relevant performance criteria if -
« Under the Building Regulation 2006, a rainwater tank is proposed to be installed as part of relevant
building work, in a designated rainwater tank area; and
¢ Under the Queensland Development Code, part 25; the rainwater tank does not include an acceptable
solution for a relevant performance criteria.
Page 16
Page 22
PROPOSED RC DRIVEWAY (REFER NOTE 1 FOR DETAILS) PROPOSED 1.5m WIDE CONCRETE PROPOSED SERVICE CONDUITS 100 TELECOM & @80 ELECTRICAL PROPOSED KERB ADAPTOR (INC. 290 PVC SWD PIPE} STORMWATER FLOW DIRECTION EXISTING CONTOURS (1.0m INTERVALS) EXISTING 2375 STORMWATER PIPE EXISTING O/H ELECTRICITY EXISTING TELSTRA PIT EXISTING TREE 1. 2. = - FOOTPATH NOTES PROPOSED LOT 8 & 9 TO CANCEL LOT 8 ON SP 191680. KERB INVERT CROSSING, ACCESS SLAB AND R.C. DRIVEWAYS TO BE CONSTRUCTED IN ACCORDANCE WITH N.S.C. STO DRG 9005. , 1.5m WIDE CONCRETE FOOTPATHS TO BE CONSTRUCTED IN ACCORDANCE WITH N.S.C. STD DRG S01/A. |. FOOTPATH AREA TO BE FORMED, TOPSOILED & TURFED. LANDSCAPING, REVEGETATION, AND REHABILITATION IN ACCORDANCE WITH APPROVED LANDSCAPING PLAN No. LA01-8. LAYOUT PLAN SCALE §:250 1INS re ' 1IN6 o NATURAL SS" & SURFACE 4 \_F72 MESH TYPICAL DRIVEWAY CROSS SECTION 21 8 2 ‘ ‘ & Noa i: SCALE BEFORE REDUCTION anes 10 5 0 10m 20m telah deeds) 1: SCALE BEFORE REDUCTION Vee COLIN PYWELL CONSULTING | ENGINEER 6 Castle Court, TUGUN 4224. Phone (07) 55345140 PTY LTD ‘Commit MURRAY & ASSOCIATES Consulting Surveyors Gurrie NAMSOUR Phone 1218S Fax (07) $441 2801 if i “No.1 LAGUNA STREET, BOREEN POINT) (1 «+ 1) } iE zal? ri i Es SI a P_& S PTY LTD (™ ACCESS PLAN 070831_01 ) \ axte 31 auc 2007 J
Page 23
i a “a 2002 SN ig SP ee ‘ ew 4 \. A OvLSresSs (20) eu0ud ‘“¥ZZ¥ NNONL “NCD aS0D 9 NV1d SS300V a | f LOR ive (40) 4 BIE uo OL Aid S ® d _ are a ssofaaing Bunjnsueg 196 $40 010 Kaw PINIOd N3axO8 “LadulS VNNOVT VON) E== me [| SaLvloOSSW 7 AVHuCN dit Ald YISANIONSA ONILINSNOO MSMAd _ NI1QO — ( NGHLINGIY 340439 F1VIS ‘d-L0V1 ‘ON NV1d ONIGVOSGNV1 GIAOUddY HLIM JONVAHODOY NI NOLLVLIISWH3Y CNY ‘NOLLWLS93A7d ONIdVOSGNVT ’S “CSIUNL 8 GINWOSdOL ‘GAWYOS 39 OL VANV HLIWdLOO4 *P "V/L06 SU GLS °O’S'N HLIM JONVOYOOOV NI GALONULSNOD 3d OL SHLVdLOO4 SLSYONOD 3CIM WS" “E woz wot 0 s OL NOILINGIY 34059 J1VIS ad D r r T t ! 001: JIVIS NOILOSS SSOHO AVMSAIYG WWOIdAL HSAW 224 5 39vsayNS la | SAS, TWUNLLYN t ONT ‘S006 DUC GLS ‘O'S'N HLIM SONVCYOOOV NI GALONYLSNOS 38 OL SAVMAAING 08 ONY EV1S SSIOOV ‘ONISSOND LYSANI GUI _— oN ‘089161 dS NO 8 LOT TSONVO O16 28107103S0d0Ud | 000€ 052+, 31¥)S SALON NV1d LNOAV1 — ~~ AFL ONILSIXA Ld VALSTAL DNILSIXS ALIOMMLOATS H/O ONILSIXA did NALVMNYOLS S/€S ONILSIXG (STWAUALNI WO") SYNOLNOD ONILSIXA NOLLOIUIG MOT4 MaLVMAYOLS (Adid GMS DAd 068 ‘ONI) HOLdvdv Guay GaSOdONd WOIMLOI1S 088 2 WODATAL 0018 SLINGNOD SOIANSS GaSOd0ud HLVdlOO4 SLIYONOD SOIM WS} GaSOdO¥d «=f * oe (STIv130 NOS | ALON 43434) AVMGAING 4 G3S0d0ud OVO" HyMaay oS O%+
Used in these records
07/1849 - Op Works - Residential Subdivision [As Published]Related documentApplication case desk ↗
About this file
- File size
- 1.7 MB (small file)
- File type
No other editions are linked here.