Decision Notice - 172007545 · 172007.545.02

of 6

Text shows just the words. Original shows the document exactly as it was published.

NOOSA COUNCIL IDAS Development Application Decision Notice                                                         3 of 6




                                      Noosa Council Conditions
                                      INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION


1.     Development undertaken in accordance with this approval must generally comply with the approved plans
       of development. The approved plans are titled and numbered Site Plan, 9 of 9; Lower Floor Plan, 2 of 9;
       Upper Floor Plan, 3 of 9; Elevations 4 of 9; Elevations 5 of 9 prepared by Adrian Barker Computer Drafting
       and dated 2 March 2007 and as may be amended by these conditions.

2.     The development must be undertaken and operated in a manner that causes no detrimental effect upon
       the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other
       emissions.

3.     All hot water systems installed shall be either solar systems; electric heat pump systems; or gas systems
       (LPG or natural).

4.     Buildings and structures (including swimming pools, sheds, tennis courts or outbuildings) are not
       constructed under overhead electricity transmission lines, or within any easements.

5.     A geotechnical report, prepared by a registered professional engineer shall be obtained, and it should
       either:-

       5.1.   certify that the site is not at risk from landslide emanating from the site or from other land; or

       5.2.   identify methods of stabilising all buildings, accessways and uses areas; and where the
              geotechnical report identifies methods of stabilising buildings, accessways and uses areas. The
              development shall implement those methods, which are recommended.

6.     The Preliminary Approval for a building works lapses if the use has not happened by 23 April 2009, unless
       an application to extend the currency is approved by Council.




JB c:\users\jbelsham\downloads\ecm_10032434_v2_decision notice - 010 2007 00000545 001.doc

Used in these records

About this file

File size
200 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 172007545.pdf · 200 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.