                                                    Proposed Service Station – 175 Eumundi Noosa Road, Noosaville
                                                                                 Ref: 20769 C R001 Rev 06 09.02.17
                                                                                                    February 2018


10       WATER SUPPLY
10.1     Existing Infrastructure
         A Unitywater Infrastructure Mapping search and detailed survey has identified the following
         sewerage infrastructure relevant to the subject site:

          A 750mm DI trunk beneath Eumundi Noosa Road adjacent to the northern boundary of the subject
          site;

          A 100mm AC main within the Eumundi Noosa Road verge adjacent to the northern boundary of
          the subject site;

          Two (2) hydrants located along Eumundi Noosa Road adjacent to the subject sites northern
          boundary;

         For more information on the existing sewer infrastructure, refer to the detail survey in Appendix A,
         the Unitywater Infrastructure Mapping searches in Appendix H and the DBYD information in
         Appendix I for further details.

10.2     Point of Connection
         Due to the demand for the proposed development, the site will require a property connection installed
         in order to meet the expected water supply demands.

         ADG Engineers anticipate that the proposed development will be connected to the existing AC
         100mm water main within Eumundi Noosa Road, located north of the subject site within the
         development side verge. Connection to this main will be dependent on Council’s hydraulic engineer’s
         assessment.

         To understand with greater certainty the requirements from Unitywater (UW) for this development, a
         Service Advice Notice Request has been prepared and lodged with UW with an expected issue date
         November 2017. It is expected that Unitywater will condition the existing AC main to be replaced with
         a current approved pipe material for the entire length of site frontage.

         For more information on the proposed connection, refer to the Preliminary Engineering Services
         Layout Plan in Appendix C.




BRISBANE / SYDNEY / MELBOURNE / GOLD COAST / SUNSHINE COAST / DARWIN / PERTH                              Page 22
Log in to download the original file

C2. Eng Report.pdf · 8.9 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.