Log in to see the plans as drawnTable 1. Project goal, objectives and deliverables.
To improve the environmental health of the Noosa River Estuary through active restoration
Project Goal and conservation activities that engage the Noosa Community in meaningful conservation
and support economic and community wellbeing.
Expected
Party
completion date
responsible
Objectives Deliverables (from 1 July 2019 Measurable outcomes
for
unless otherwise
Deliverable
stated)
(A1.1) A Technical Advisory
Group (TAG) is established
Terms of reference for the
to provide project TNC
TAG developed, TAG is
oversight. This will include a 3 months from
established and at least one
clear terms of reference appointment of
meeting held.
and consist of Project Manager
representatives from key
Evidence of Kabi Kabi
stakeholders (NSC, TNC, TNC
involvement.
Kabi Kabi and at least two
other independent parties).
(A1.2) Appointment of
A-1 Project dedicated project manager
establishment who is a marine biologist Appointment of Project
6 months
and with extensive project Manager to oversee the TNC
management management experience, Project.
for the term of the
Establish Agreement.
effective project (A1.3) A Project
A Project Implementation
governance, Implementation Plan
Plan produced by TNC,
management, detailing at a minimum:
endorsed by Technical
communication A detailed risk assessment
Advisory Group, and
and reporting associated with the project.
delivered by TNC to Noosa
sufficient to A communications and
Council for presentation and TNC
successfully media plan, outlining media
approval by Noosa Council
implement protocols, opportunities
its approval.
shellfish and the role of TNC and 6 months
A Project Implementation
restoration NSC.
Plan presented to Noosa
project A monitoring, evaluation
Council by TNC in
and reporting plan which
conjunction with Council TNC & NSC
identified ecological and
officers for its approval, and
social monitoring programs,
(if acceptable) approved in
how they will be reported
writing by Noosa Council by
on and how this will fed
no later than two months
back into the project.
after delivery.
Participate in at least three TNC
(A1.4) Participate in public Ongoing for the
public presentations/forums
forums to provide the duration of the
in the first 12 months
Noosa community project
(ideally within first 9
11
BRING BACK THE FISH: PROJECT MANAGEMENT PLAN
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.