2020-07-07 P&E Agenda - Item 3 - Attachment 1 - TNC Project Management Plan

of 89

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Timeline: 18 months

As part of Objective A1.4, TNC will engage with the community and stakeholders through the TAG, organized
community forums, media and one-one meetings. The process involves socializing both the method and end result of
site selection and allowing the community and stakeholders to have sufficient input into the site selection process in
order to minimize the number of individuals and groups opposed to the location. Regular input and feedback will
reduce the risk of stakeholders objecting to sites.



Table 6. Deliverable checklist for Objective 2 (to be completed in six monthly, annual and final reports).

   Deliverables                               Measurable outcomes                          Status and notes
                                                                                            (Not Started/In
                                                                                     Progress/Delayed/Completed)
   (A2.1) Shellfish restoration suitability   •   Habitat suitability model
   model incorporating physical                   which incorporates industry,
   parameters of oysters and public and           Kabi Kabi and public
   industry usage, access etc. to identify        interests.
   priority sites for restoration.
   (A2.2) Obtain necessary State
   Government permits/authorities
   including particular resource              •   All relevant permits secured
   allocation authority, for shellfish
   ecosystem restoration
   (A2.3) Community, industry and             •   Records of public and
   stakeholder consultation sufficient to         stakeholder consultation,
   gain majority support for ecosystem            including one-on-one
   restoration locations.                         meetings, open forums,
                                                  media, etc.




                                                                                                                   27
      BRING BACK THE FISH: PROJECT MANAGEMENT PLAN
Log in to download the original file

2020-07-07 P&E Agenda - Item 3 - Attachment 1 - TNC Project Management Plan(PDF, 3MB).pdf · 3.5 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.