Log in to see the plans as drawn 10. Project milestones
The anticipated project milestones are presented in Table 12. Achievement of these milestones may be subject to
government requirements placed on the project that are not foreseeable at the time of writing.
Table 12. Major project milestones - anticipated
No. Project Milestone Indicative Action Date
1 Technical Advisory Group established and first quarterly meeting 13 May 2020
2 All Project Plans (Communications, Project Management, risk assessment, 31 May 2020
Monitoring, Evaluation and Reporting) completed
3 Initial round of community workshops completed 30 July 2020
4 Seagrass surveys completed 30 November 2020
5 Shellfish Restoration Suitability Index (HSI) Completed 30 July 2020
6 Shell recycling commences# 30 August 2020
7 Seagrass Restoration Suitability Index (HSI) completed 30 November 2020
8 Citizen science activities commence# 1 February 2021
5 Design for pilot sites completed 30 June 2020
6 Seagrass restoration trials commence 30 June 2021
7 All permits and approvals for pilot sites obtained 31 October 2020
8 Restoration works at pilot sites completed 31 May 2021
9 Design for large-scale restoration works completed 30 June 2021
10 All permits and approvals for large-scale restoration works obtained 31 August 2021
11 All restoration contracts and plans established 31 October 2021
12 Large-scale restoration works completed 31 May 2022
13 All post-restoration monitoring and evaluation completed 30 June 2022
14 Complete Monitoring and Evaluation Report 15 July 2022
15 Project Review 20 July 2022
16 Completion of Final Project Report 30 July 2022
47
BRING BACK THE FISH: PROJECT MANAGEMENT PLAN
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.