2020-07-07 P&E Agenda - Item 3 - Attachment 1 - TNC Project Management Plan
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn2. Introduction
2.1 Purpose and scope
The purpose of this Plan is to detail the workflow necessary to successfully deliver the Project (Bring Back the Fish,
defined in the TNC-NSC Alliance and Funding Agreement) including project timelines, activities, methodology and
budget. It provides an overview of the restoration targets, goals and objectives associated with the shellfish
restoration sub-project. It also provides the basis for the development of more detailed implementation plans such
as the Communication Plan and Monitoring Evaluation and Reporting Plan.
The Project involves the delivery of multiple objectives, each with multiple activities required to deliver the Project
goal (see below). The primary objective involves the restoration of shellfish ecosystem (created predominantly by
Saccostrea glomerata, rock oyster) initially at two locations and then subject to successful establishment at these
sites, at other locations throughout the estuary.
The Project commenced on 25th July 2019, and is scheduled to be completed by 30th September 2022.
The geographical boundaries of the project include all estuarine waters of the Noosa River Estuary including up to the
high water mark (Figure 1). The political, social and community boundaries include all parties required to successful
deliver on the project objectives including local and state governments, Commonwealth Government, community
groups, private corporations, private trusts and foundations and individuals.
7
BRING BACK THE FISH: PROJECT MANAGEMENT PLAN
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.