Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003.
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can
also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or
the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.
8 PROPERTY NOTES
Not applicable
9 PRELIMINARY APPROVAL OVERRIDING SCHEME
Not applicable
10 FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit required Subject of the required Development Permit
Development Permit for Building Works All Building Works
Development Permit for Operational Landscaping, Carparking and Access, Site Civil
Works Works (including Earthworks), Roadworks,
Stormwater Drainage, Frontage Works, Sewer
Reticulation (including New Mains, Relocations,
Diversions, Pump Stations and Rising Mains), Water
Reticulation, Site Filling, Erosion & Sediment Control
11 SELF ASSESSABLE CODES
The developer must comply with the following codes for self-assessable development related to the
development approved under this Decision Notice:
Advertising Devices Code
12 SUBMISSIONS
There were two (2) properly made submissions about the application. In accordance with Integrated
Planning Act 1997, the name and address of the principal submitter for each properly made
submission is provided and attached.
13 REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
1. There is a continuing significant planning need for a mega hardware store in the Noosa area,
which will improve the range of hardware and related services available to residents, trades
persons and businesses;
2. The proposed Bunnings Warehouse will not adversely impact upon the economic viability of
the Shire Business Centre;
16 of 20
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Decision Notice - 010.2007.00000256.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 101 KB (small file)
- File type
No other editions are linked here.