EROSION AND SEDIMENTATION MANAGEMENT PLAN ENVIRONMENTAL DIARY CONSTRUCTION MANAGEMENT PLAN
Sediment Control Weekly Visual Inspection or After Rainfall Event
Project:- Operational Works Performance
Indicators
Item Performance Indicator CONSTRUCTION MANAGEMENT PLAN DIARY
Principal:-
LINDSAY CONSULTING PTY LTD
Contractor:- CLOUT DESIGN LINDSAY CONSULTING PTY
Objective Comply with all statutory regulations and maintain erosion and sedimentation 1. Vegetation No disturbance of soil below retained vegetation due to construction Weekly Visual Inspection or After Rainfall Event LTD
Location:- NO 7 WILLIAM ST, NOOSAVILLE
controls throughout the duration of construction. Comply with the intent of the activities.
Job Ref. 20-1343 Project:- Operational Works
sedimentation management plan shown on sheet 29 of the drawings prepared
No:- No work conducted outside specified hours without satisfactory evidence Principal:-
by Noel Covey & Associates, and other measures as deemed necessary to Date:- Regular Monitoring (Weekly) 2. Hours of Work RPEQ 4928
control erosion and minimise sediment transport. of measures taken to suppress noise and other emissions / dust. Contractor:- CLOUT DESIGN
Approx Time:- am/pm Special Event Monitoring (briefly describe event) Location:- OFF. 2C/82 PARKER STREET, MAROOCHYDORE PH 54 792 118
NO 7 WILLIAM ST, NOOSAVILLE
Job Ref. No:- 20-1343 Council File Ref. No.
Management Strategy Site Foreman to identify direction of stormwater land flows and flows resulting Item
Date Condition Corrective
Control Acceptable Action Corrective Action Taken
3. Lighting No resident's complaints regarding construction security lighting. THIS DRAWING REMAINS THE PROPERTY OF
Required
from construction, and provide sediment fences, rock filter dams, turf strips, Monitored Measure
Installed ü
(Describe)
No abutting public roads contain soil, gravel, clay or other such
Date:- Regular Monitoring (Weekly) LINDSAY CONSULTING PTY LTD AND IS FOR
stormwater pit entry filters, and other measures as shown on the plan or as 4. Existing Roads
THE SOLE USE OF THE CLIENT. NO PART
û
materials originating from onsite construction activities. Approx Time:- am/pm Special Event Monitoring (briefly describe event)
deemed necessary to prevent uncontrolled stormwater flows over unprotected
areas, and avoid sediment transport to waterways and stormwater pits. Sediment
Fences 5. Signage No observed or reported incidents due to inadequacy or absence of Date Control
Condition C orrective Action
Corrective Action Taken
MAY BE USED IN PART OR WHOLE WITHOUT
signage or other control measures. Item Monitored
Measure Installed
Acceptable Required
(Describe) PRIOR EXPRESS WRITTEN CONSENT OF
Tasks and Actions Erect sediment barriers as shown on sheet 29 of the drawings, and at other LINDSAY CONSULTING PTY LTD
ü
Rock
û
6. Waste Control No complaints from local residents and site is kept tidy at all time
Required locations as deemed necessary by visual inspection. Temporary rock filter dams Filter
Dams Retained Vegetation
are to be placed at all concentrated stormwater flow outlet locations and
maintained with fresh filter screenings throughout the duration of construction. 7. Waste Minimisation No occurrence of illegal dumping onsite and all materials where possible CLIENT AND PROJECT DESCRIPTION
All earthworks areas to be topsoiled and seeded or hydromulched upon have been appropriately recycled.
CLOUT DESIGN
Air Emissions
Stormwater
completion of profiling. All footpath areas to be provided with a minimum 4m Outlets
8. Dangerous Goods No spillage or seepage of dangerous goods stored onsite.
wide turf strip behind kerb and channel immediately after footpath area
OPERATIONAL WORKS
Noise
construction and topsoil profiling is completed. Strategically place filters around
all stormwater pits. Catchpit 9. Erosion & Sedimentation No visible signs of sediment laden waters leaving the site.
Areas
NO. 7 WILLIAM ST
Security Lighting
No works are carried out without implementation of the approved Traffic
Performance Indicators Site Foreman to - 10. Traffic Management
NOOSAVILLE
Vibrations
check for erosion and sediment flows at base of all embankments Pavement Management Plan.
Areas
·
and other 11. Existing Infrastructure Existing Utilities, Roads & Drainage Infrastructure
exposed areas after rain; No unplanned damage to existing utilities and infrastructure.
· check that rock filter dams are working during rain periods; Bottom
check that all sediment fences and other erosion control of 12. Non Conformances Construction Traffic & Parking
·
Embankment All non conformances have been reported and rectified
mechanisms are
working during rain periods; and Humeceptors/ The site foreman is to monitor the performance of all construction activities and any departure from the Waste Minimisation & Recycling
clean and maintain filter fabric covers to pits after rain periods. Gross Monitoring Construction Management Plan control measures is to be immediately rectified. DRAWING TITLE
·
Pollutant
Traps Erosion & Sedimentation Control (Environmental Diary)
Monitoring Site Foreman to monitor performance of all sediment controls on a
regular weekly basis and after every rainfall event. Any damaged Detention
Basin
Responsible The site foreman is to be responsible for all inspections and maintenance of the Construction Management
Other
MANAGEMENT PLAN
sediment control item is to be rectified, and trapped silt removed and Person Plan.
deposited in an area not prone to erosion.
The site foreman is to complete the Construction Management Plan Diary (including Environmental Diary for Item Monitored
Other sediment control) on a weekly basis as a minimum, but also after every significant rainfall event (which
Responsible Person Site Foreman to be responsible for all inspections and maintenance of sediment causes site runoff) or other special event affecting the site or any watercourses traversing the site.
control measures. Any Special Comments:- Reporting The Construction Management Plan Diary (in conjunction with the Environmental Diary) shall be completed Any Special Comments:-
Signed:- and delivered to the Superintendent for record and audit purposes with each progress claim for the
Reporting Site Foreman is to complete the Environmental Diary for sediment control on a
weekly basis as a minimum, but also after every significant rainfall event or other
construction works. SCALES
special event affecting the sediment control measures. The Environmental Diary
shall be completed and delivered to the Superintendent for record and audit The site foreman is to arrange all corrective actions, controls and rectification activities, and report on Signed:-
purposes with each progress claim for the construction works. Corrective
Actions all measures taken in the Construction Management Plan Diary.
Corrective Actions The Site Foreman to arrange for installation of additional sediment
controls and/or improve maintenance controls and replacement of
screenings to filter dams as required, and report on measures taken in
the Environmental Diary.
CONSTRUCTION MANAGEMENT PLAN SURVEY DATUM
Objective To comply with all statutory regulations and relevant policies, and minimise the impact on the Construction 11. Implement the erosion and sedimentation control measures and associated management plan contained
environment whilst carrying out construction activities in a safe and sustainable manner. Management
Tasks and Actions
in the approved plans.
12. All earthwork stockpiles are to be kept moist, covered with tarpaulins or otherwise treated to
.
Required
minimise dust emissions and stored in locations which minimise the possibility of the soil entering the
stormwater system.
Management To minimise the environmental and amenity impact of construction activities through onsite proactive
approach to construction processes and consequences (cause and effect). Successful integration of
13. A construction shakedown area is to be installed at the entrance to the site to reduce unwanted ASSOCIATED CONSULTANTS
Strategy soil from leaving the site via vehicle tyres.
activities will achieve ecological sustainability which is recognised as a balance that integrates the 14. All site staff and sub contractors shall be directed to use the nominated shakedown entry / exit
protection of ecological processes and natural systems, economic development, and maintenance of point.
cultural, economic, physical and social wellbeing of people in communities. 15. Roads abutting the site and affected by the works shall be swept at regular intervals as required,
or whenever inspection shows signs of soil / pavement construction material on an abutting road or
at the nominated site entrance.
Construction The following schedule of management strategies, tasks and actions for construction works forms the
Management 16. A high level of site “housekeeping” shall be maintained to ensure that vermin are
basis of sustainable management of site construction issues. Irrespective of whether or not an item is
Tasks and Actions not attracted to poorly disposed of materials. Any waste or materials that have
Required included in the following schedule however, the Contractor shall employ best practice measures to
been illegally dumped on site shall be removed.
achieve sustainable outcomes at all times.
17. The Contractor shall provide bins for staff and sub contractors at locations
Management Strategy / Action where food is consumed and shall ensure that such bins are used and emptied
at regular intervals.
1.Ensure that all staff and sub contractors working on the site are aware of potential environmental
18. All materials, be they construction materials or used containers, shall either be
impacts and required minimum environmental control measures and responsibilities before
recycled onsite or alternatively transported to a Council approved recycling station
commencement of any site works.
or disposal point.
2.Disturbance of soils below the canopy of any retained vegetation is to be excluded or otherwise 19. Any distillate or other petroleum products or dangerous goods stored onsite are
minimised in accordance with the approved plans. to be in bunded areas, located well clear of any watercourse. Appropriate spill
3. No dust emissions shall extend beyond the boundary of the site. control kits for any chemicals or stored fuels shall also be provided onsite.
20. Best practice management techniques shall be employed to control erosion and
4. No odour emissions are detectable beyond the boundary of the site. minimise sediment transport onsite, including those details contained in the
5.Work, including plant and equipment maintenance and servicing, shall only be carried out between the approved plans and the Erosion and Sedimentation Management Plan.
hours of 6:30am and 6:30pm Monday to Saturday inclusive. Written agreement must be provided by 21. The Contractor shall prepare and implement an approved Traffic Management
neighbouring residents if any work activity with the potential to emit excessive noise is to be Plan for site construction activities. The Traffic Management Plan shall be
undertaken outside the above mentioned hours, and even with such consent, such activities are to be provided to the Council inspector and the Supervising Engineer at the prestart
minimised. meeting.
22. Comply with any conditions of Council's operational works approval applicable to
6.All equipment shall be acoustically treated with manufacturer supplied muffler systems with ensure
the works.
that equipment does not create environmental harm or excessive noise. REVISION LIST
23. All public complaints received by the Contractor must be recorded in writing,
7.Temporary security lighting for the site must be designed and located to ensure that its effects are including any investigations undertaken, conclusions reached and actions taken as A ORIGINAL ISSUE 20/11/20
not obtrusive and direct light spill does not alter the amenity of adjacent properties. a result of same. This complaints record is to be made available to the
administering authority on request.
8.All existing utilities (roads, drainage, electrical and communication) on or adjacent the site are to be
24. All site personnel are to report any significant non-conformances to the site
protected and maintained at all times, with the cost of any damage to such infrastructure to be
manager as soon as practical and within 1 hour of the occurrence of, or
met by the Contractor.
observance of same.
9. Any areas of high risk / danger on the site are to be adequately signposted. 25. The contractor shall prepare an informative letter to be dropped to
10. Vibration beyond the site boundary from construction activities is to be minimised and where there is residents/businesses adjacent to the development. The letter is to advise
a likelihood of such vibration extending beyond the boundaries to an adjoining property owner, the contact details for communications for the site manager, working hours, projected
property owner shall be advised accordingly. timing of works and any other information the contractor sees relevant.
Computer File
201343OW.DWG
DRAWING NUMBER SHEET REV.
20-1343-F3 3 A