Original source · versioned page text
APPENDIX B - Local Assessment
Attached to the e-mail MCU18/0204 - Development Application - 6 Heron Street, Peregian Beach.
Specific Outcomes Probable Solutions Response
adversely impact upon other c) for areas where flood
premises by— modelling is not available, a
i. causing ponding of water minimum of 300mm above
on the site or nearby the highest known flood
land; and level;
ii. increasing flooding, which
adversely affects the S2.2
safety or use of any land For additions of not more than
upstream and 50m2 gross floor area to an
downstream; existing building—floor levels of
iii. adversely affecting the habitable rooms are not less
flow of water in any than the level of other habitable
overland flow path; and rooms in the building;
iv. adversely affecting the
privacy or visual amenity S2.3 Filling, other than for
of surrounding properties. accessways, does not extend
more than 1m beyond the
footprint of any building,
measured from outer walls of
the building;
O3
Complies
Finished surface levels ensure S3.1
land is free draining. No solution provided Refer to plans.
O4
Filling or excavation does not S4.1 N/A
adversely affect sewer, Fill material placed over
stormwater or water utility services does not impose any
infrastructure. additional surcharge loading on
the service.
Editor’s note
Council encourages building S4.2
methods that avoid the use of Where excavation is carried out
fill, such as suspended floor c) a minimum cover of 600mm
construction and stepping down is maintained around all
slopes rather than cutting and utility infrastructure (to top,
filling. sides and base of services);
or
d) a retaining wall is provided
to support the soil
surrounding the service;
S4.3
Compaction with a vibrating
roller is not carried out within
600mm of any utility
infrastructure.
O5 N/A
Development does not adversely S5.1
impact on the Lake Macdonald Buildings or other structures
water supply. within the Lake Macdonald
catchment (indicated on Figure
14-15) are located above the
98.5m AHD level.
Electricity supply infrastructure
O6 S6.1
N/A
See the original