SC7440 – Goodchap St, Noosa                                                                             11




4.3.2   Catchment Areas
The subject site has been modelled in its existing pre-development and proposed post-development states
with the catchment areas illustrated in Tables 4.1 & 4.2. In its pre-development state the subject site was
modelled as one hydrologic node to replicate the existing drainage situation for the lot. XP-STORM model
layouts and outputs are included in Appendix C of this report.


                 Node                     Description              % Impervious       Area (Ha)

                                           Landscape                      0             0.512
                 ‘PRE’
                                              Roof                       100            0.162

                              Total Catchment (ha)                        24            0.674
                         Table 4.1 - Pre Development Node Sub-Catchment Areas


                 Node                      Description            % Impervious        Area (Ha)
                ‘TANK’                        Roof                      100             0.400
                                     Carpark/hardstand areas            100             0.085
                                           Landscape                     0              0.189
                          Total Catchment (ha)                           72             0.674
                          Table 4.2 - Post Development Sub–Catchment Areas

4.3.3   Roughness Coefficients
The conduits and links used within the model are based on the ultimate design scenario for the internal
roadways and overland flow paths. Mannings “n” roughness coefficient values are specified as 0.014 for
RCP pipes and 0.011 for uPVC pipes.


For overland flow within the sub-catchment areas a Mannings “n” value of 0.014 for concrete areas and
0.045 for vegetated areas was adopted.


4.3.4   Storm Events
Storm patterns were setup using Australian Rainfall and Runoff (ARR 1987) storm patterns for Area 3 with
intensity frequency duration data taken for the local area. Storm durations of 10, 15, 20, 25, 30, 45, 60 and
90 minutes were investigated for the pre and post developed scenarios.

Used in these records

About this file

File size
2.6 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

MCU18_001 - Referenced Document - Site Based Stormwater Management Plan.pdf · 2.6 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.