7.8 Cost estimation
Project costs (and ultimate project staging) will be dependent on many factors such as detailed design outcomes, relevant
approvals, cost estimate refinement, development stages, procurement scheduling and cash-flow management.
STAGE DESCRIPTION COST
car park redesign and construction, including the boardwalk parallel to the canal, and $1,200,000
pedestrian pathways and boat manoeuvring areas
design and construct ,covered and secure storage for coastal rowers $60,000
repurpose one of the existing amenities buildings into secure storage for outrigger canoes and $120,000
1
remove storage containers currently located adjacent the Slipway
install a pontoon in the canal as additional rowing launching $80,000-
$100,000
Stage 1 sub-total 1,480,000
renewal (and possible widening) of existing boat ramp at front of NYRC clubhouse Estimated
$400,000,
subject to design
2
replacement of fixed jetties with floating jetty/pontoon configuration $1,300,000,
subject to design
Stage 2 sub-total 1,700,000
Sub-total 3,180,000
Contingency subject to concept and detailed design (50%) 1,590,000
TOTAL 4,770,000
52
Noosa Shire Council
Page 294 of 518
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalOriginal file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.
Used in these records
Meeting papersMeeting papersMeeting 180 ↗
About this file
- File size
- 150 MB (very large file)
- File type
No other editions are linked here.