Stormwater Management Report

Attached to the e-mail Ind Bus Type 2, Reconfigure a Lot (Access Easements) & Op Works (Comm site investigation report, Vehicle access & Stormwater Mgmt) - MCU18/0120, RAL18/0013 & OPW18/0197 .msg.

of 15

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

12 ON SITE SOLID WASTE MANAGEMENT


         Person Responsible     Contractor’s Site Manager

         Operational Policy     To prevent the creation of unacceptable visual amenity due to the
                                storage of onsite solid wastes.

         Performance criteria   The target level of complaints by nearby residents is no more
                                than one in every seven day period. Regular monitoring of
                                volumes of waste generated/stored.

         Implementation         An onsite storage bin is to be provided to the receiving of
                                construction wastes.
         Strategy
                                These wastes are to be stored in a manner that prevents leaching
                                of unwanted materials into the stormwater system downstream
                                from the site. If a material that is disposed off into the bin that has
                                potential for hazardous leaching it is not to be disposed of via the
                                site waste bin. It is to be removed immediately to the council
                                waste depot or in accordance with EPA standards and guidelines.

                                When a complaint is received the complaint is to be assessed
                                and the offending waste bin removed/emptied.

         Monitoring             Solid waste bin inspections will be carried out to verify that waste
                                levels in the bins and type of waste are acceptable.

                                Monitoring will be conducted upon receipt of complaints by
                                residents.

                                If the bins are full they are to be taken away by the waste bin
                                contractor.

         Auditing               Management to review the complaints register weekly and
                                corrective action taken.

         Reporting              The contractor is to notify NSC of a possible nuisance on receipt
                                of 3 or more solid waste storage complaints in any 24hr period.

                                Reports are to be provided to NSC upon request

         Identification of      Any waste related complaints by residents will indicate a failure of
                                waste control measures.
         incident or failure

         Corrective Action      Apply the following-

                                    1. If the bin is full – have it emptied/replaced
                                    2. Waste that has not been placed in the bin must be
                                       relocated to inside the bin.




HR DESIGN                                   Reference No: 18-0165A                                        Page 12 of 14
Log in to download the original file

Stormwater Management Report.pdf · 685 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.