INFRASTRUCTURE CHARGE CALCULATION DETAILS:
The infrastructure charge is calculated in accordance with Council’s Infrastructure Charges Resolution
incorporating the charge apportionment (break-up) agreement with Unitywater in compliance with the
Sustainable Planning Act 2009 and Statutory Regulatory Provision (adopted charges) applying at the
time of issuing the notice.

Council’s infrastructure charge levied is based on the following:

                                                 Charge
   Development                                                    % Charge
                       Unit of Measure            Rate                              % Council
      Class                                                      (Clause 13 (c)                                      $ Amount
                          (Table 13.1          (Table 13.1                        Apportionment         Qty
     (Table 13.1                                                  & Table 10.3                                  (at 1 July 2014 Index)
                         Columns 3 & 5)        Columns 4 &                           (Table 10.1)
      Column 2)                                                    Note: (1))
                                                   5)

 Approved Development Defined Use & Quantity: 25 x New Residential Lots
 Residential            3+ dwelling (lot)        $28,000             100%                42%             25               $294,000.00
                                                                         Gross Infrastructure Charge =                    $294,000.00
 Discount (Credit) for Lawful Existing Defined Use & Quantity (Clause 8.4): 1 existing Non-Residential Community
 Services Lot = No lot credit available as no existing development on site & no previous payments made to
 infrastructure
                         Community
 Non-Residential       Services Vacant              -$0              100%                42%             1                          -$0
                             Lot
                                            Existing Lawful Use or Contribution Discount (Credit) =
                                                                                                                                    -$0
                                  (Clause 8.4 - Limited to and not exceeding the Gross Infrastructure Charge)
                                                             Condition 13. d – Upgrading of Elm St
 Infrastructure Offset for “trunk” infrastructure                                                                        -$16,038.00
                                                                      Pathway Frontage
                                                            * NET INFRASTRUCTURE CHARGE =                             * $277,962.00

The infrastructure charge payable will be allocated to Council “Trunk” infrastructure networks in
accordance with Council’s Resolution as follows:

                                                                                                                * Net Infrastructure
   Council “Trunk” Infrastructure Network                 Net Infrastructure                                      Charge Amount
                   (Table 10.2)                                 Charge
                                                                                           Offset
                                                                                                                      Payable
                                                                                                                (at 1 July 2014 Index)

 Transport                                                       $117,600.00                    -$16,038.00               $101,562.00

 Public Parks & Land for Community Facilities                    $147,000.00                         -$0.00               $147,000.00

 Stormwater                                                       $29,400.00                         -$0.00                $29,400.00

   * Net Infrastructure Charge Payable =                      * $294,000.00                    -$16,038.00             * $277,962.00
* Subject to Automatic Increase Provision until date of payment.

Offset Details:
    • Condition 13. d – Upgrading of Elm St Pathway Frontage




                                     PO Box 141                      P. (07) 5329 6500      [email protected]
                                     TEWANTIN QLD 4565               F. (07) 5329 6501      www.noosa.qld.gov.au          ICN - Page 3
Log in to download the original file

REC13_0148 & MCU13_0226 ICN-N1046 with Info Notice.pdf · 162 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.