09/1270 - Approved plans/Negotiated Decision Notice [As Published] · 132009.1270

of 16

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
2009/1270

 

(b) a notice under section 6.1.44? giving a decision to
change or cancel a condition of a development
approval.

(2) The appeal must be started within 20 business
days after the day the notice of the decision is
given to the person.

* (3) Also, a person who has made a request
mentioned in subsection (1)(a) may appeal to the
court against a deemed refusal of the request.

(4) An appeal under subsection (3) may be started at
any time after the last day the decision on the
matter should have been made.

Appeals against decisions to change approval conditions
under the repealed Act

4.1.33A.(1) A person who is dissatisfied with a decision
made on an application to change the conditions
attached to an approval given under section 2.19(3)or
section 4.4 of the repealed Act may appeal to the court
against-

(a) the decision; or

(b) a deemed refusal of the application:

(2) An appeal under subsection (1)(a): must ‘be
started-within 20 business days after the day notice of
the decision is to be given to the person.

(3) An appeal under subsection (1)(b) may be started
at any time after the last day a decision on the matter
should have been made.

Appeals against local laws

4.1,33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions applied
under a local law about the use of premises or the
erection of a building or other structure permitted by the
planning scheme may appeal to the court against the
decision or the conditions applied.

(2) The appeal must be started within 20 business
days after the day notice of the decision is given to the
applicant.

For Building Works Only

Rights of appeal-conferred by Section 4.2.9 of the
Integrated Planning Act 1997 as follows:

Division 3 - Appeals
development applications

Appeals by applicants

to’ tribunals relating to

4.2.9(1) An applicant for a development application may
appeal to the Building and Development Tribunal against
any of the following-

(a) the refusal, or the refusal in part, of a development
application;

“

(b) a matter stated in a development approval, including
any condition applying to the development, and the
identification of a code under section 3.1.6;>

? Section 6.1.44 (Conditions may be changed or cancelled
by assessment manager or concurrence agency in certain
circumstances)

Section 3.1.6 (Preliminary approval may override focal
planning instrument)

(c) the decision to give a preliminary approval when a
development permit was applied for;

(d) the length of a period mentioned in section 3.5.21
relevant period;
(e) a deemed refusal.

{2) An appeal under subsection (1)(a) to (d) must be
started within 20 business days (the “applicant’s appeal
period”) after the day the decision notice or negotiated
decision notice is given to the applicant.

(3) An appeal under subsection (1)(e) may be started
at any time after the last day a decision on the matter
should have been made.

The Registrar for the Building and Development
Tribunal may be. contacted at the website
http:/www.localgovernment.qlid.gov.au/

For Infrastructure Charges Only

4.1.36 Appeals about particular infrastructure
charges

(1) This section applies to a person who has. been
given, and is dissatisfied with, an infrastructure charges
notice or a regulated State infrastructure charges notice.
(2) The person may appeal to. the court against the
notice. ,

(3) The appeal must be.started within 20 business days
after-

(a) _ if the notice is given because of a development
approval or master plan approval-the day the
applicant is given notice of the decision about the
approval; or

(b) otherwise-the day the notice is given to the person.

(4) An appeal under this section may only be about-

(a) ‘whether a charge in the notice is so unreasonable
that no reasonable-relevant local government, State.
infrastructure provider or coordinating agency could
have imposed it; or ‘

(b) an error in the calculation of the charge.

{5) To remove any doubt, it is declared that an appeal

under this section can not be about the methodology

used to establish the charge in the relevant infrastructure

charges schedule or regulated State infrastructure
charges schedule.

ttofti ©

Used in these records

About this file

File size
865 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

09_1270 - Approved plans_Negotiated Decision Notice [As Published].pdf · 865 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.