               FOLLOWING CONSTRUCTION
                      Certification
               42.    Upon completion of the work a certificate must be issued by an RPEQ certifying that the
                      works have been constructed in accordance with the Operational Works permit.
               43.    A condition report of the drainage system must be completed and submitted to council prior
                      to requesting the On-Maintenance inspection. The condition report is to include:
                      a.      a CCTV inspection of the new stormwater line, extending between the existing
                              stormwater gully pit on James Street and the connecting pit on Weyba Road;
                      b.      photos of the existing stormwater gully pit on James St fronting the subject site;
                      c.      photos of the existing eastern most pit on the subject site.
                      As Constructed Plans and ADAC XML Files (Council)
               44.    Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
                      “As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
                      information must include:
                      a.      As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
                              file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
                              accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
                      b.      ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
                              prepared in accordance with industry standards and recorded in “MGA - UTM56 /
                              GDA94” projection.
                              Please Note: Further information and advice relating to the as-constructed drawing
                              presentation, as-constructed survey capture and associated guidelines for preparation
                              of a compliant ADAC XML digital file are available on the webpage titled “As-
                              Constructed Guidelines” and accessible at the Noosa Council Website: Planning &
                              Development / Development Tools & Guidelines / As-Constructed Guidelines.
                      c.      The “As-Constructed” drawings will require certification by a:
                              i.       Qualified experienced Civil Engineer (RPEQ) confirming design intent and
                                       conformance with applicable standards and specifications, along with the
                                       relevant descriptions of assets, services and structures and;
                              ii.      Licensed Surveyor in regard to the cadastral and locational information, levels
                                       and applicable survey datum.
                      d.      The data must be in accordance with Council’s “Planning Scheme Policy 6 –
                              Engineering Design Standards”, and fully detail the levels for all engineering works
                              including but not limited to the drainage network and structures, finished ground and
                              pavement surface levels.
                      On Maintenance
               45.    All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
                      Council’s relevant Planning Scheme Policy and the draft departmental guideline for the use
                      of polypropylene and high-density polyethylene pipe for stormwater prior to commencement
                      of the use. To achieve ‘On Maintenance’, the supervising RPEQ must submit to Council:
                      a.      Certification that all works have been undertaken and completed in accordance with
                              the requirements of this Permit;
                      b.      As Constructed details in accordance with Council’s Planning Scheme Policy;
                      c.      Maintenance and operational manuals for all proprietary or site specific devices.
                      d.      A 12-month minimum maintenance period for civil works that would not be impacted
                              by a failure of the alternate poly pipe types.



                                                                                                       Page 15 of 20
Document Set ID: 22627357
Version: 3, Version Date: 19/10/2023

Used in these records

About this file

File size
222 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Minor Change - MCU21 0027 02 & OPW21 0047 02 [As Published].pdf · 222 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.