Decision Notice - Minor Change - MCU21 0027 02 & OPW21 0047 02 [As Published] · MCU21/0027.02
b. Stormwater runoff from the site is not currently, and is not likely to result in visible
evidence of sedimentation or erosion, or lead to water contamination.
If at the time of request for the On-Maintenance inspection, the method of short-term
stabilisation has not achieved a level of stability that Council's Officers believe will have
a high probability of achieving long term stability (i.e. until house construction has
occurred on all lots), Council Officers may take the following matters into consideration
in determining whether the site is capable of achieving medium to long-term stability:
• evidence that the site has been effectively stabilised in the short term;
• evidence that soil has been adequately ameliorated;
• evidence that seed of annual and perennial grass species has been applied at
an adequate rate; and
• that grass seed has germinated at a density that is likely to achieve an effective
grass cover.
ENVIRONMENTAL HEALTH
Building Works
15. Noise from residential building works shall comply with the following:
a. Limited to between 6:30am to 6:30pm Monday to Saturday.
b. All reasonable measures are taken to minimise noise emissions
c. Not permitted on Sunday or public holidays.
Measurement of Noise
16. Measurement of sound pressure levels (adjusted for tonality and impulse) must be in
accordance with either:
a. Australian Standard AS1055.1 “Acoustics–Description and measurement of
environmental noise – General procedures”, or
b. The relevant “Noise Measurement Manual” as provided by the Department of
Environment and Heritage Protection.
17. A qualified person is considered to be either:
a. a Registered Professional Engineer of Queensland, or;
b. an environmental consultant with a minimum of 3 years current experience in the field
of acoustics.
Acoustic Advice & Design
18. It is highly recommended that the developer seek the advice and design input of a qualified
acoustic consultant at the plan development stage to ensure the development does not cause
a noise nuisance under the Environmental Protection Act 1994. Attention should be given
to the following (but not limited to):
a. building design and construction
b. design, selection and installation of fixed plant and equipment
c. he location of air conditioning and heating units, refrigeration plant, pumps, mechanical
exhausts and plant rooms etc
d. the use of acoustic enclosures/screens around noisy plant and equipment.
e. operating times.
Page 18 of 20
Document Set ID: 22627357
Version: 3, Version Date: 19/10/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Minor Change - MCU21 0027 02 & OPW21 0047 02 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 222 KB (small file)
- File type
No other editions are linked here.