Original source · versioned page text
Minor Change Request report tewantin netball
Deciding the Request
In accordance with S81 of The Planning Act 2016, Council must only consider the information
provided and any other matter considered relevant, including — all matters Council would or may
assess against or have regard to if the change application were a development application.
Council must only consider the statutory instrument, or other document, as in effect when the
development application for the development approval was properly made. However, may give
weight they consider appropriate, in the circumstances, to—
(a) the statutory instrument or other document as in effect when the change application was
made (Superseded Planning Scheme); or
(b) if the statutory instrument or other document is amended or replaced after the change
application is made but before it is decided—the amended or replacement instrument or
document; or
(c) another statutory instrument—
(i) that comes into effect after the change application is made but before it is decided; and
(ii) that the responsible entity would have been required to consider if the instrument had
been in effect when the development application for the development approval was properly
made.
In accordance with the above the proposal is assessed against the conditions of approval, the
Superseded Planning Scheme and the Noosa Plan 2020. The proposal complies with all these
instruments and approval and is discussed below.
Assessment
The key development parameters from the existing approval are outlined below and an
assessment of the differences is provided thereafter.
Noting that where the proposal varies from the approval, this indicates that assessment must be
provided against the relevant Probable Solution of the superseded scheme or Performance
Outcome of the current scheme.
Criteria SPS Noosa Plan 2020 Proposal Compliance
Use Definition Indoor Club Minor Change Y
Entertainment
Building height
storeys 2 storeys 2 storeys 1 storey Y
metres 8 metres 8 metres 7.8 metres Y
Site cover - 10% < 10% overall Y
GFA - 800m2 210m2 Y
Wall Length - 15m 32m PO
Front setbacks - 20m 6.7m PO
Roof Pitch - 5 degrees >5 degrees Y