Approved Decision Notice - DBW24 0114 [As Published] · DBW24/0114
Approved Plans
2. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table.
Plan No. Rev. Plan/Document Name Date
DA1000 DA-F ENTRY LEVEL – PREPARED BY LIGHTBODY 25.02.2025
ARCHITECTS
DA1001 DA-D MAIN LEVEL – PREPARED BY LIGHTBODY 25.02.2025
ARCHITECTS
DA1002 DA-F LOWER LEVEL – PREPARED BY LIGHTBODY 25.02.2025
ARCHITECTS
DA1006 DA-d ROOF LEVEL – PREPARED BY LIGHTBODY 25.02.2025
ARCHITECTS
DA 2000 DA-E BUILDING ELEVATIONS DA - WEST 25.02.2025
ELEVATION – STREET – PREPARED BY
LIGHTBODY ARCHITECTS
Annotated by Council
DA 2001 DA-D BUILDING ELEVATIONS DA – NORTH 25.02.2025
ELEVATION – STREET – PREPARED BY
LIGHTBODY ARCHITECTS
DA 2002 DA-F BUILDING ELEVATIONS DA – EAST 25.02.2025
ELEVATION – STREET – PREPARED BY
LIGHTBODY ARCHITECTS
DA 2003 DA-F BUILDING ELEVATIONS DA – SOUTH 25.02.2025
ELEVATION – STREET – PREPARED BY
LIGHTBODY ARCHITECTS
DA 2100 DA-E BUILDING SECTIONS PREPARED BY 25.02.2025
LIGHTBODY ARCHITECTS
DA 2101 DA-E BUILDING SECTIONS PREPARED BY 25.02.2025
LIGHTBODY ARCHITECTS
DA 2102 DA-C BUILDING SECTIONS PREPARED BY 25.02.2025
LIGHTBODY ARCHITECTS
DA 2103 DA-D BUILDING SECTIONS PREPARED BY 25.02.2025
LIGHTBODY ARCHITECTS
Currency Period
3. This development approval lapses if the works have not substantially started by 20 March
2027, unless an application to extend the currency period is approved by Council.
Page 2 of 7
Document Set ID: 23649833
Version: 3, Version Date: 25/03/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Approved Decision Notice - DBW24 0114 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 175 KB (small file)
- File type
No other editions are linked here.