EGX_PROD_n6914339_4-8_&_16_Lower_Mill_Road,_Cooroy_L5_SP213104;_L7_SP173771
Attached to the e-mail Energex Referra Agency Response - MCU20/0012.
4
Access to the easement and access along the easement must be available to Energex
personnel and heavy equipment at all times. Energex will require the Developer / owner to
supply and install gates where fencing prohibits access to and along the easement area.
To enable travel along the easement at anytime the gates must be series locked with an
Energex padlock. Both the padlock and a design drawing of an acceptable gate will be
provided by Energex.
Any costs or damages incurred by Energex as a result of the works on the easement are to
be met by the property Developer / owner.
Landscaping on the easement is generally not permitted.
Reference: HBD 6914339
Have you seen our fact sheets?
See the ‘considerations when developing around electricity infrastructure’ section of our website
www.energex.com.au/referralagency
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.