EGX_PROD_n6914339_4-8_&_16_Lower_Mill_Road,_Cooroy_L5_SP213104;_L7_SP173771

Attached to the e-mail Energex Referra Agency Response - MCU20/0012.

of 4
                                                   4




   Access to the easement and access along the easement must be available to Energex
    personnel and heavy equipment at all times. Energex will require the Developer / owner to
    supply and install gates where fencing prohibits access to and along the easement area.
    To enable travel along the easement at anytime the gates must be series locked with an
    Energex padlock. Both the padlock and a design drawing of an acceptable gate will be
    provided by Energex.

   Any costs or damages incurred by Energex as a result of the works on the easement are to
    be met by the property Developer / owner.

   Landscaping on the easement is generally not permitted.




Reference: HBD 6914339

                                  Have you seen our fact sheets?
    See the ‘considerations when developing around electricity infrastructure’ section of our website
                                www.energex.com.au/referralagency

Log in to download the original (EGX_PROD_n6914339_4-8_&_16_Lower_Mill_Road,_Cooroy_L5_SP213104;_L7_SP173771.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.