FINAL Ecological Management Plan Stage 1_Grasstree Court 5 February 2021

Attached to the e-mail Cover letter - Ecological Management Plan - Grasstree Ct Sunrise Beach.

Attached to the e-mail Cover letter - Ecological Management Plan - OPW18/0343.02 - Grasstree Court Sunrise Beach.

Attached to the e-mail OPW18 0343 - Sunrise Beach RAC - Grasstree Court Intersection.msg.

of 39

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (10.2 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Ecological Management Plan – Grasstree Court – Lot 6



     4. FAUNA MANAGEMENT

     4.1 Pre-clearing
A qualified fauna-spotter (holding an appropriate State-approved rehabilitation permit) is to be appointed
before commencement of clearing. Pre-clearing fauna management measures are to include the following,
as a minimum:

     •    Inspection of habitat on site within areas to be cleared.
     •    Identification of habitat trees (i.e. trees that have the potential to harbour fauna).
     •    Protective fencing installed to identify protected and clearing areas.
     •    Tree protection fencing must provide for the evacuation of fauna to retained habitat. Any gaps
          between fencing panels must not exceed 1m.
     •    Fauna spotter to be cognisant of koalas in the landscape and koala management measures in
          accordance with State guidelines.
     •    Fauna-spotter to attend pre-start meeting.
     •    Signage warning of fauna presence and speed limits (30km/hr) to be installed.

DERM customer service centre is to be notified (phone or email) at least five business days prior to
commencement of any clearing of koala habitat trees on the subject site of the date clearing is to
commence and the koala spotter to be used.


     4.2 Clearing & Construction
The fauna-spotter is to be on site during clearing of all vegetation. Fauna management measures during
clearing are to include the following, as a minimum:

     •    Directional clearing is to occur, i.e. clear from development area towards “conservation” areas (i.e.
          to the north and west for Lot 6) (refer Section 5).
     •    Habitat features to be checked for fauna prior to clearing.
     •    Habitat features such as hollow-bearing branches/logs are to be salvaged and re-located within the
          buffer area.
     •    Ongoing liaison with Civil Contractor and clearing contractors regarding fauna and vegetation
          clearing methods.
     •    Throughout clearing, the fauna-spotter is to capture, and release fauna as required.
     •    In the event of an injury to fauna, the fauna-spotter is to deal with the animal appropriately and/or
          have treated at local veterinary surgery or registered wildlife carer, as necessary (note below
          details).
     •    No domestic pets (including dogs, cats) allowed on the site during construction.

The Eumundi Wildlife Centre is the nearest wildlife rehabilitation facility (1411 Eumundi-Noosa Road,
Eumundi – tel. 5442 8057) and the nearest vet is the Sunshine Beach Vet (46 Duke Street, Sunshine Beach
– tel. 5447 4569).



     4.3 Habitat Creation
While not a condition of approval, following discussions with Council, it is proposed to install a permanent
water feature within the landscaping area/s of the Lot 6 development. This may take the form of
birdbaths/ponds or similar structures that are incorporated into the landscaping features creating a
permanent source of water.



                                                                                                            15
Log in to download the original file

FINAL Ecological Management Plan Stage 1_Grasstree Court 5 February 2021.pdf · 10.2 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.