Decision Notice - Minor Change - RAL22 0016 01 [As Published]
The bond will be refunded less any costs incurred by Council in ensuring compliance with
these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
9. Bonds must:
a. meet the requirements of council’s relevant Planning Scheme Policy for performance
and uncompleted works.
b. be calculated using a schedule of works and relevant bond equation
c. include GST.
d. have approval of the bond calculations and amount from Council prior to lodgement.
e. be lodged with Council and accompanied by the Bond Administration Fee/s.
f. be requested for release by writing to Council, when relevant approval requirements
have been met.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
10. All necessary approvals from external service providers (e.g. Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.
11. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting.
12. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
13. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
b. Other relevant parties
14. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction
ii. Maintenance of safe vehicle and pedestrian access across the frontage of the
site both during daily construction and after daily construction has ceased
iii. Proposed fencing to the site during the construction phase of the development
iv. Adequate parking arrangements for construction workers
b. Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures
15. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
16. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
Page 4 of 13
Document Set ID: 22409110
Version: 4, Version Date: 05/05/2023