Compiled Plans & Documents OPW18-0342 02
Retirement Living & Aged Care Facility
Grasstree Court, Sunrise Beach
8 Interim Construction Land Management
The approved development is to be constructed over three stages, including:
Stage 1: RAC, central facilities and co-located apartments and 50 per cent of the
independent living villas
Stage 2: Balance 50 per cent of independent living villas
Stage 3: Apartment buildings.
Both Lot 6 and Lot 9 are intended to be cleared for civil earthworks at the same time, thus the
construction of the first two stages of development will not be subject to potential interim hazard by
retained vegetation internal to the site.
Notwithstanding this, the development site must be maintained in a low-fuel condition throughout
construction and into the maintenance phases, to avoid potential inadvertent of on-site vegetation
re-establishment during construction.
Status: Final March 2019
Project No.: 18-030 Page 39
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Compiled Plans & Documents OPW18-0342 02.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.