Original PDF page 24, section 1. The text section number identifies this passage in the reader.
scoured away or is of such an isolated volume so as to not be significant and acid sulfate treatment will not be
required.”
Acid sulfate management of the Noosa River is to be undertaken in accordance with Pacific Geotech
recommendations as follows: “Considering the proposed dredging methodology (ie. use of a cyclone separator)
and the natural buffering capacity of the sands, treatment for the acid sulfate neutralisation is not likely to be
required. This should be confirmed with validation testing at the time of the dredging operation. Validation testing
should be undertaken at a rate of 1 test per 250m3 of disturbed material. … If the validation testing indicates the
material is providing results above 18molH+/tonne (ie. above the action criteria) the material should be neutralised
at the time of dredging”.
Objective: To minimise the impacts of disturbance of soils on the surrounding environment.
Issues: Adverse impacts associated with unexpected sediment types (that may be acidic or contaminated).
Performance Criteria: Compliance with Queensland Acid Sulfate Soils Technical Manual and NAGD (2009).
Control Measures:
Responsible
Control Measures
Party
1. Dredge to be fitted with a cyclone when working in areas that don’t have adequate buffering capacity Contractor
2. Nourishment to consist of suitable sandy sediments ONLY. Dredged sediment to be monitored. In the Contractor
event that sediment types that are unsuitable for nourishment or are indicative of acid sulfates or
contaminated sediment, dredging is to cease or move to an adjacent area.
3. Acid sulfate validation testing to be undertaken at a rate of 1 test per 250m3 of disturbed material. Contractor
In the event that the validation testing indicates the material is providing results above 18molH+/tonne (i.e.
above the action criteria) a geotechnical expert is to be consulted and material is to be neutralised at the
time of dredging”
Monitoring: Monitoring is to be undertaken in accordance with Table 4.
CULTURAL HERITAGE
The dredge and nourishment area has historically been dredged and used for re-nourishment. Given the level of
previous disturbance, it is considered unlikely that items of indigenous cultural heritage significance are present.
Noosa River Caravan Park, Heritage Impact Statement (HIS)
The Noosa River Caravan Park at Munna Point is listed on the Queensland Heritage Register. This site already
has existing approvals for dredging and beach re-nourishment that were obtained during Munna Point Groyne
works.
The closest nourishment works are 2m seaward of an existing building and 3m seaward of camp sites (Figure
12); however, an existing geotextile container retaining wall separates the nourishment area and caravan park at
this location.
22
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.