Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118
9. Electrical
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Planning Unlicenced electrical work EXTREME 5 Only suitably licenced electrical contractors to undertake electrical work. Site Management
Electrical Contractor
Electrical licences to be checked at induction and copies of electrical licences retained Procore.
9.1 Temporary Power
Planning Inadequate planning HIGH 5 A plan/register of distribution board location and supply requirements are to be retained in the project site office and Site Management
with the electrical contractor. Electrical Contractor
Inability to identify the board HIGH 5 Where there is more than one switch board on site, marking shall be provided, by means of numbers, letters, or both, Electrical Contractor
for isolation purposes to identify each individual switchboard.
Inability to isolate the board EXTREME 5 Every switchboard or part of a switchboard that is supplied form a separate source of supply is to be clearly marked to Site Management
identify the source form which the supply originates. Electrical Contractor
Suitable access to power HIGH 5 Switchboards will have at least 1m clearance provided in front of the switchboard. Site Management
boards Electrical Contractor
Incorrect use of electrical EXTREME 4 In multi-level buildings distribution boards will be positioned in a manner which eliminates the need for electrical leads Site Management
equipment to be run between levels or in accordance with Table 1 in section 2.6.7 AS/NZS 3012 - Electrical Installations - Contract Partner
Construction
Damage to electrical EXTREME 4 Wiring and electricals circuits (including overhead installations) will be positioned to avoid crossing roadways or access Site Management
installations resulting in power ways where cranes, high loads or heavy machinery may travel. Electrical Contractor
loss or injury.
Damage to electrical EXTREME 5 Risk assessment should be undertaken prior to the installation of cables or whenever a change occurs, as to the Site Management
installations resulting in power likelihood of the cables being exposed to mechanical damage – as per AS 3012 – 2.5.2 protection against mechanical Electrical Contractor
loss or injury. damage
Inadequate planning EXTREME 5 Power points installed inside relocatable premises will only be used to supply power to electrical equipment and Site Management
lighting within that relocatable premise.
Workers electrocuted / EXTREME 4 All generators connected as site supply to the main switchboard of a construction site are to be installed in accordance Site Management
shocked with AS 3010 and the manufacturers requirements with Records of all testing to be retained on site and provided to Electrical Contract
Woollam. Partner
Workers electrocuted / EXTREME 4 Portable generators supplying electrical equipment by plug and socket outlet on the generator set is not required to Site Management
shocked have an earth electrode connected as per AS/NZS 3012 Contract Partner
Non-compliant installation EXTREME 5 A contract partner supplied Temporary Electrical Board Checklist to be completed prior to handover and submitted to Site Management
Woollam. Records of all testing to be retained on site and provided to Woollam. Contract Partner
Project Hazard/Risk Assessment / Page 56 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 836 KB (small file)
- File type
No other editions are linked here.