Original source · versioned page text
Delegated Report - Code - Planning MCU22 0087 [As Published]
Very large file (11.9 MB): the original may take a few minutes to open or download. The page text below is quick to read.
DEVELOPMENT ASSESSMENT DELEGATED REPORT
62. All street surfacing must consist of a minimum depth of 30mm of an approved hot mixed
asphaltic concrete, unless other pavement types are approved as feature areas in
intersection thresholds, speed control devices, turning areas, indented parking etc.
63. Root barriers are required to be installed behind the back of kerb for all new kerbs within 5m
of a trunk of a tree.
Pavement Design and Construction
64. Pavement design for privately owned works must be undertaken in accordance with the
relevant standards. Structural integrity of the driveway and car park areas will remain the
responsibility of the property owner/developer and must be certified by an RPEQ.
Works within Road Reserve/Reinstatement
65. Safe vehicle and pedestrian access on all streets in the vicinity of the development must be
maintained at all times. Should footpath/road closures be necessary to carry out construction
works, Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
66. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles.
67. Electrical conduits or other services proposed to be installed within existing and proposed
road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
driveways or significant vegetation must be installed by boring. Trenching is not permitted,
unless specifically approved by Council.
Site Access and Driveways
68. Driveway crossovers must be constructed in accordance with council’s Standard Drawings
RS-049, RS-050 and any associated addendum.
69. Any existing unnecessary or redundant property accesses must be removed, and the kerb,
footpath and verge area reinstated to match the existing footpath and/or verge treatments.
Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
or turf, and must be maintained by the developer until established.
70. The following must be complied with during the construction of the required
crossover/driveway:
a. The driveway surfacing must consist of either an approved hot mixed asphaltic
concrete or patterned/plain concrete.
b. The driveway must be constructed so as not to concentrate stormwater runoff onto
neighbouring properties.
c. Underground service conduits for water supply, electricity and any other services must
be provided as part of the access driveway
d. Where there is an existing pedestrian path, a matching crossfall must be provided for
the driveway on the alignment of the path, for the full width of the path.
e. The property access must be located a minimum of 1m clear of existing power poles,
streetlights or other signage. The developer is responsible for any necessary relocation
of existing services to provide this clearance and must contact the relevant service
authorities and comply with their requirements in relation to these works.
Earthworks and Retaining Walls
71. All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
on Earthworks for Commercial and Residential Development, with any required geotechnical
testing undertaken in accordance with the Standard. A certificate must be provided by a
RPEQ and submitted to Council prior to the commencement of the use.
Page 33 of 42
Document Set ID: 22374890
Version: 10, Version Date: 06/08/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.