5.0 - CONCLUSION
This SWMP outlines how stormwater runoff from the site will be managed in order to not adversely
impact the receiving environment.
The proposed lawful point of discharge for the proposed development shall be the Crank Street drainage
pit via the construction of a new stormwater connection.
Stormwater detention shall be provided through the provision of a 13000 lt detention tank to the new
lot. Refer attached drawings for the proposed tank details.
Stormwater treatment is not considered necessary for the site. The QLD ESC Design spreadsheet
demonstrates that a sediment basin is not required for this development.
By implementing the proposed stormwater management system, and providing adequate maintenance,
the downstream environment and neighbouring properties will not experience any adverse deterioration
of water quality as a result of the proposed development.
Off. 2C/82 Parker St, Maroochydore 4558
7
OFFICE: (07) 54 792 118 MOBILE: 0412 313 645 FAX: (07) 54 510 118
E-MAIL: [email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.