CONSTRUCTION MANAGEMENT PLAN CONSTRUCTION MANAGEMENT PLAN
Performance
Indicators
Item Performance Indicator
CONSTRUCTION MANAGEMENT PLAN DIARY Objective To comply with all statutory regulations and relevant policies, and minimise the impact on the environment whilst carrying
out construction activities in a safe and sustainable manner.
Construction
Management
11. Implement the erosion and sedimentation control measures and associated management plan contained in
the approved plans.
Tasks and Actions
Required 12. All earthwork stockpiles are to be kept moist, covered with tarpaulins or otherwise treated to minimise
1. Vegetation No disturbance of soil below retained vegetation due to construction activities. Weekly Visual Inspection or After Rainfall Event dust emissions and stored in locations which minimise the possibility of the soil entering the stormwater
system.
Project:- Operational Works - PROPOSED SUBDIVISION To minimise the environmental and amenity impact of construction activities through onsite proactive approach to
Management 13. A construction shakedown area is to be installed at the entrance to the site to reduce unwanted soil
2. Hours of Work No work conducted outside specified hours without satisfactory evidence of measures Principal:- EAGLE SURVEYS Strategy construction processes and consequences (cause and effect). Successful integration of activities will achieve ecological from leaving the site via vehicle tyres.
taken to suppress noise and other emissions / dust. Contractor:- sustainability which is recognised as a balance that integrates the protection of ecological processes and natural systems, 14. All site staff and sub contractors shall be directed to use the nominated shakedown entry / exit
Location:- NO.33 CRANK STREET, TEWANTIN economic development, and maintenance of cultural, economic, physical and social wellbeing of people in communities. point.
3. Lighting No resident's complaints regarding construction security lighting. Job Ref. No:- 250314 Council File Ref. No. 15. Roads abutting the site and affected by the works shall be swept at regular intervals as required, or
LINDSAY CONSULTING PTY
whenever inspection shows signs of soil / pavement construction material on an abutting road or at
LINDSAY CONSULTING PTY LTD
Date:- Regular Monitoring (Weekly) the nominated site entrance.
4. Existing Roads
No abutting public roads contain soil, gravel, clay or other such materials originating Construction The following schedule of management strategies, tasks and actions for construction works forms the basis of sustainable LTD
Approx Time:- am/pm Special Event Monitoring (briefly describe event) Management 16. A high level of site “housekeeping” shall be maintained to ensure that vermin are not
from onsite construction activities. management of site construction issues. Irrespective of whether or not an item is included in the following schedule
Tasks and Actions attracted to poorly disposed of materials. Any waste or materials that have been
Required however, the Contractor shall employ best practice measures to achieve sustainable outcomes at all times.
No observed or reported incidents due to inadequacy or absence of signage or other Condition C orrective Action
Corrective Action Taken illegally dumped on site shall be removed.
5. Signage Date Control
control measures. Item Monitored
Measure Installed
Acceptable Required (Describe)
Management Strategy / Action 17. The Contractor shall provide bins for staff and sub contractors at locations where RPEQ 4928
ü food is consumed and shall ensure that such bins are used and emptied at
û 1. Ensure that all staff and sub contractors working on the site are aware of potential environmental impacts and OFF. 2C/82 PARKER STREET, MAROOCHYDORE PH 54 792 118
6. Waste Control No complaints from local residents and site is kept tidy at all time regular intervals.
required minimum environmental control measures and responsibilities before commencement of any site works.
Retained Vegetation
2. Disturbance of soils below the canopy of any retained vegetation is to be excluded or otherwise minimised in accordance
18. All materials, be they construction materials or used containers, shall either be
recycled onsite or alternatively transported to a Council approved recycling station
THIS DRAWING REMAINS THE PROPERTY OF
No occurrence of illegal dumping onsite and all materials where possible have been
7. Waste Minimisation
appropriately recycled. Air Emissions
with the approved plans. or disposal point. LINDSAY CONSULTING PTY LTD AND IS FOR
19. Any distillate or other petroleum products or dangerous goods stored onsite are
3. No dust emissions shall extend beyond the boundary of the site.
to be in bunded areas, located well clear of any watercourse. Appropriate spill THE SOLE USE OF THE CLIENT. NO PART
8. Dangerous Goods No spillage or seepage of dangerous goods stored onsite.
Noise
4. No odour emissions are detectable beyond the boundary of the site. control kits for any chemicals or stored fuels shall also be provided onsite.
20. Best practice management techniques shall be employed to control erosion and
MAY BE USED IN PART OR WHOLE WITHOUT
9. Erosion & Sedimentation No visible signs of sediment laden waters leaving the site. Security Lighting
5. Work, including plant and equipment maintenance and servicing, shall only be carried out between the hours of 6:30am
and 6:30pm Monday to Saturday inclusive. Written agreement must be provided by neighbouring residents if any work minimise sediment transport onsite, including those details contained in the PRIOR EXPRESS WRITTEN CONSENT OF
activity with the potential to emit excessive noise is to be undertaken outside the above mentioned hours, and even with
such consent, such activities are to be minimised.
approved plans and the Erosion and Sedimentation Management Plan.
21. The Contractor shall prepare and implement an approved Traffic Management Plan
LINDSAY CONSULTING PTY LTD
No works are carried out without implementation of the approved Traffic Management
10. Traffic Management for site construction activities. The Traffic Management Plan shall be provided to
Plan.
CLIENT AND PROJECT DESCRIPTION
Vibrations
6. All equipment shall be acoustically treated with manufacturer supplied muffler systems with ensure that equipment does the Council inspector and the Supervising Engineer at the prestart meeting.
not create environmental harm or excessive noise.
Existing Utilities, Roads & Drainage Infrastructure 22. Comply with any conditions of Council's operational works approval applicable to
11. Existing Infrastructure No unplanned damage to existing utilities and infrastructure.
7. Temporary security lighting for the site must be designed and located to ensure that its effects are not obtrusive and the works.
All non conformances have been reported and rectified Construction Traffic & Parking
direct light spill does not alter the amenity of adjacent properties. 23. All public complaints received by the Contractor must be recorded in writing,
including any investigations undertaken, conclusions reached and actions taken as a
EAGLE SURVEYS
12. Non Conformances 8. All existing utilities (roads, drainage, electrical and communication) on or adjacent the site are to be protected and
result of same. This complaints record is to be made available to the
maintained at all times, with the cost of any damage to such infrastructure to be met by the Contractor.
Waste Minimisation & Recycling
administering authority on request.
PROPOSED SUBDIVISION
The site foreman is to monitor the performance of all construction activities and any departure from the Construction 9. Any areas of high risk / danger on the site are to be adequately signposted. 24. All site personnel are to report any significant non-conformances to the site
Monitoring Management Plan control measures is to be immediately rectified. 10. Vibration beyond the site boundary from construction activities is to be minimised and where there is a likelihood of manager as soon as practical and within 1 hour of the occurrence of, or
Erosion & Sedimentation Control (Environmental Diary) observance of same.
The site foreman is to be responsible for all inspections and maintenance of the Construction Management Plan.
such vibration extending beyond the boundaries to an adjoining property owner, the property owner shall be advised
accordingly. 25. The contractor shall prepare an informative letter to be dropped to
residents/businesses adjacent to the development. The letter is to advise contact
33 CRANK STREET,
Responsible Person
TEWANTIN
Other
details for communications for the site manager, working hours, projected timing of
works and any other information the contractor sees relevant.
The site foreman is to complete the Construction Management Plan Diary (including Environmental Diary for sediment Item Monitored
control) on a weekly basis as a minimum, but also after every significant rainfall event (which causes site runoff) or
other special event affecting the site or any watercourses traversing the site. The Construction Management Plan Diary
Reporting (in conjunction with the Environmental Diary) shall be completed and delivered to the Superintendent for record and audit Any Special Comments:-
purposes with each progress claim for the construction works.
DRAWING TITLE
The site foreman is to arrange all corrective actions, controls and rectification activities, and report on all measures Signed:- CONSTRUCTION
MANAGEMENT PLAN DETAILS
Corrective Actionstaken in the Construction Management Plan Diary.
EROSION AND SEDIMENTATION MANAGEMENT PLAN ENVIRONMENTAL DIARY
Sediment Control Weekly Visual Inspection or After Rainfall Event
Project:- Operational Works - PROPOSED SUBDIVISION
SCALES
Principal:- EAGLE SURVEYS
Contractor:-
Objective Comply with all statutory regulations and maintain erosion and sedimentation
Location:- NO.33 CRANK STREET, TEWANTIN
controls throughout the duration of construction. Comply with the intent of
Job Ref. 250314
the sedimentation management plan shown on sheet 29 of the drawings
No:-
prepared by Noel Covey & Associates, and other measures as deemed Date:- Regular Monitoring (Weekly)
necessary to control erosion and minimise sediment transport. Approx Time:- am/pm Special Event Monitoring (briefly describe event)
Management Strategy Site Foreman to identify direction of stormwater land flows and flows resulting
from construction, and provide sediment fences, rock filter dams, turf strips, Date Condition Corrective
Item Control Acceptable Action Corrective Action Taken
stormwater pit entry filters, and other measures as shown on the plan or as Monitored Measure Required (Describe)
Installed ü û
deemed necessary to prevent uncontrolled stormwater flows over unprotected
areas, and avoid sediment transport to waterways and stormwater pits.
Tasks and Actions Erect sediment barriers as shown on sheet 29 of the drawings, and at other Sediment
Fences
Required locations as deemed necessary by visual inspection. Temporary rock filter
dams are to be placed at all concentrated stormwater flow outlet locations
and maintained with fresh filter screenings throughout the duration of Rock
construction. All earthworks areas to be topsoiled and seeded or Filter
Dams
hydromulched upon completion of profiling. All footpath areas to be
provided with a minimum 4m wide turf strip behind kerb and channel
Stormwater
SURVEY DATUM
immediately after footpath area construction and topsoil profiling is
completed. Outlets
Performance Indicators Site ForemanStrategically
to - place filters around all stormwater pits.
100 PVC
check for erosion and sediment flows at base of all
·
embankments and other
.
Catchpit overflow
exposed areas after rain; Areas
pipe
· check that rock filter dams are working during rain periods; Inlet Pipes
· check that all sediment fences and other erosion control
mechanisms are Pavement
Areas
IL 5.00
ASSOCIATED CONSULTANTS
working during rain periods; and
Monitoring · clean and
Site Foreman maintainperformance
to monitor filter fabric of
covers to pits after
all sediment rain on
controls periods.
a
regular weekly basis and after every rainfall event. Any damaged Bottom
of
sediment control item is to be rectified, and trapped silt removed and Embankment 10000 lt MIN
deposited in an area not prone to erosion.
Responsible Person Site Foreman to be responsible for all inspections and maintenance of sediment Humeceptors/ detention tank
Gross
control measures. Pollutant
Traps
Reporting Site Foreman is to complete the Environmental Diary for sediment control on a NOM TANK IL 2.00
weekly basis as a minimum, but also after every significant rainfall event or
other special event affecting the sediment control measures. The Detention
Basin
Environmental Diary shall be completed and delivered to the Superintendent for
25 PVC restricted
WATER DETENTION TANK DETAIL
record and audit purposes with each progress claim for the construction works.
Corrective Actions The Site Foreman to arrange for installation of additional sediment Other flow pipe
controls and/or improve maintenance controls and replacement of
screenings to filter dams as required, and report on measures taken Any Special Comments:-
in the Environmental Diary. Signed:-
REVISION LIST
A ORIGINAL ISSUE 21/5/25
Computer File
250314OPW.DWG
DRAWING NUMBER SHEET REV.
25-0314-C6 6 A
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.