Original source · versioned page text
Att 8 - SWMP
Attached to the e-mail Shopping complex - Traffic Report & Stormwater Management Plan (Email 3 of 3 MCU17/0054.
1. Introduction
1.1 Scope
This Stormwater Management Plan (SWMP) has been prepared to support a development
application for Material Change of Use for a proposed commercial development at 11-19
Hilton Terrace Tewantin. A proposal plan is provided as Appendix A.
This SWMP has been written to address stormwater quantity and quality generally in
accordance with Noosa Plan requirements and the Queensland Urban Drainage Manual
(QUDM, 2013).
1.2 Site Description
The existing site is almost completely impervious, comprising a number of buildings and
hardstand areas. Figure 1.1 shows existing site conditions and surface coverage.
The site is low-lying, having surface elevations generally between 1.0m and 2.0mAHD. As
such, the site will need to be filled in order to achieve adequate flood immunity and will
therefore be raised above the existing verge level.
A small stormwater catchment associated with Ernest Street flows into the site via an
existing pipe on the Eastern Site Boundary and is shown in the site survey provided in
Appendix B. This external catchment will need to be accommodated in the stormwater
design for the site.
Figure 1.1 – Existing Site Conditions
SWMP – 11-19 Hilton Tce Tewantin 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.