SUPERSEDED - Approved Decision Notice - RAL21 0026 & OPW21 0303

of 17

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               21.    All necessary approvals from external service providers (e.g. Unitywater) and external parties
                      on which the development works are proposed have been obtained and a copy supplied to
                      Council.
               22.    Copy of approved plan 21/8698-3: “Proposed Driveway to Lot.31”, duly signed by the
                      consultant Registered Professional Engineer of Queensland (RPEQ) must be provided to
                      Council’s Engineering Officer Construction prior to the “prestart” meeting
               23.    A condition report including photographs of the frontage of the site must be completed and
                      submitted to council prior to the prestart meeting.
               24.    Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               25.    Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6245. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Erosion and sediment control works;
                      c.      Other relevant parties
               26.    A Construction Management Plan must be submitted to Council prior to the pre-start meeting
                      and must specifically address the following:
                      a.      appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
                              Devices (MUTCD).
                      b.      provision for safe pedestrian access across the frontage of the site both during daily
                              construction and after daily construction has ceased.
               27.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               28.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering
               29.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               30.    All works must be constructed, and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice;
                      b.      The relevant conditions of the higher order Reconfiguration of Lot approval viz.
                              RAL21/0026 to which this approval relates;
                      c.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines;
                      d.      The latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site.




                                                                                                      Page 4 of 17
Document Set ID: 21939337
Version: 4, Version Date: 26/05/2022
Log in to download the original file

SUPERSEDED - Approved Decision Notice - RAL21 0026 & OPW21 0303.pdf · 418 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.