Skip to the record
Trusted by locals. Built for Noosa.

Original source · versioned page text

Response to Information Request 20220004 -Tunba Court

Attached to the e-mail Response to Information Request OPW21/0355 - 36 Tunba Court, Cooroy Mountain.

of 12

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

            4th March 2022

            Ref:    OPW21/0355

            Noosa Council
            PO Box 141
            TEWANTIN QLD 4565


            Attention:                        Mark Lewis

            Dear Sir,

                        Re:                   Information Request
                        At:                   36 Tunba Court, Cooroy Mountain, QLD 4563


            With reference to the abovementioned information request for the development
            application (ref: OPW21/0355), we have been engaged to prepare additional information
            and design plans to respond to your queries as follows:


                    2. Provide additional detail to demonstrate how the existing and proposed
                    works achieve compliance with:

                        2.1. The Earthworks Code – Performance Outcomes PO2, PO9 and PO11

                    PO2
                    Change to the levels on site do not have an adverse impact on the flooding and
                    drainage characteristics off-site.

            The earthworks proposed as part of this operational works approval will not increase the
            impervious surface area of the site, and run-off increases from any future development are
            able to be catered for through the provision of rainwater reuse and attenuation tanks
            sized based on the development’s characteristics.

            Stormwater run-off from the earthworks pad are captured and conveyed by a concrete
            spoon drain to a point of discharge at the north of the development area, where the
            stormwater will be dispersed and energy dissipated through a rock energy dissipator
            sized in accordance with QUDM for the peak 1% storm flow event to minimise impacts of
            changes to the existing flow characteristics on the downstream environment. The point of
            discharge is in line with the existing overland surface flows, therefore the changes to
            earthworks levels are not considered to significantly alter the drainage characteristics or
            flooding off-site.




P +61 7 5211 1003         A 37 Mary St, Noosaville Qld 4566     E [email protected]    recorconsulting.com
Log in to download the original file

Response to Information Request 20220004 -Tunba Court.pdf · 1.1 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 11 pages

Page 2

                    PO9
                    On sloping sites development follows the natural landform wherever practical and
                    excavation or filling is minimal.

            The development has sought to create a level pad surface area on steeply sloping hillside,
            where following the natural landform would be impractical for this purpose. The
            earthworks which have been initially constructed are proposed to be modified in
            accordance with the Geotechnical Investigation Global Stability Assessment dated
            November 21 by Morrison Geotechnic reducing fill batter slopes and providing benched
            terraces between the cut slopes to ensure stability of the resulting earthworks.

                    PO11
                    Earthworks minimise any adverse impact upon groundwater, watercourses,
                    drainage lines, wetlands, and native vegetation.


            The earthworks have been carried out clear of watercourses, drainage lines, wetlands and
            native vegetation and are not expected to impact upon the vegetated area in proximity to
            the lower fill batter.

            The stormwater drainage system proposed for the earthworks has been designed in order
            to maintain the pre-development characteristics in so far as is practicable. Stormwater run-
            off that would have previously flowed overland into the vegetated area and gully to the
            north of the earthworks continues to discharge towards the gully. An energy dissipator
            provided at the outlet of the drainage system will minimise impacts of scour or erosion
            and encourage dispersion of concentrated flows at the outlet so that impacts of the run-
            off are reduced.


                           2.2. The Water Quality and Drainage Code – Performance Outcomes
                           PO1, PO2, PO5, PO6, PO10 and PO13.


                    PO1
                    The development and its stormwater management system is planned and designed
                    having regard to:

                       1. the natural features of the site;
                       2. the need to avoid impacts and potential risks to ecologically important
                          areas;
                       3. the likely effectiveness of erosion and sediment control and stormwater
                          drainage measures during rainfall events during and post construction; and
                       4. the need to protect environmental values and water quality of receiving
                          waters both during and post construction.

            The stormwater drainage for the development has been designed to minimise the
            impacts of the development upon the downstream receiving waters and maintain the flow
            characteristics of the downstream receiving environment as much as possible.




P +61 7 5211 1003        A 37 Mary St, Noosaville Qld 4566   E [email protected]       recorconsulting.com

Page 3

            The proposed concrete spoon drain channels at the top of batters will convey stormwater
            run-off from the upstream catchments and from the earthworks pad to the drainage gully
            to the north of the development area which maintains consistency with the flow paths of
            the pre-development site so that impacts to downstream environments and neighbouring
            properties are minimised.

            A rock energy dissipator has been sized in accordance with QUDM Section 8.7.2 to
            ensure that the outlet of the drainage system is sufficiently protected such that the risks of
            erosion or scour in the receiving waters are mitigated.

            An erosion and sediment control plan has been prepared by Aussie Environmental to
            manage the water quality of receiving waters during construction. Construction is to be
            carried out in accordance with this plan to reduce impacts of the construction phase.

            At the post construction phase, any disturbed or exposed areas of the development are to
            be stabilised using grass seeding as soon as practicable to prevent sediment being lost
            from the development site and stabilise the earthworks surface.

                    PO2
                    Stormwater drainage infrastructure is planned, designed and constructed to:

                       1. incorporate allowance for increased flood risk and tidal inundation through
                          pipework as a result of cilmate change and sea level rise;
                       2. ensure the development is adequately drained; and
                       3. ensure stormwater is managed and lawfully discharged without altering
                          stormwater drainage characteristics external to the site.

            The concrete spoon drains proposed as the drainage infrastructure for the development,
            will provide the batter slope protection required by the geotechnical slope stability
            assessment to ensure water does not infiltrate into the batters. The spoon drains have
            been sized based on the 1% AEP storm event, allowing a climate change increase of 20%
            to the BoM IFD rainfall intensities for the site with the details of these calculations
            attached. An assumed 20% impervious area has been taken into account in sizing the
            lower earthworks pad to allow for any future development of this area

            Finished surfaces are to be graded locally towards the drainage lines so that run-off from
            the development will be collected in the drainage infrastructure. Minimum slopes of 1%
            are proposed for the drains to ensure the site will be free draining, and also achieving the
            required capacity for the major storm event.

            The proposed point of discharge within the subject site is through a rock energy
            dissipator falling towards of an existing drainage gully. The drainage gully is the eventual
            point of capture of pre-development flows, so discharging to this location is considered to
            maintain the existing flow paths from the site. The energy dissipator is located
            approximately 30m from the adjacent property boundary and has been sized to prevent
            erosion or scour of the gully and disperse concentrated flows so that when run-off crosses
            the property boundary it will be sufficiently similar to pre-existing conditions that any
            impacts to drainage characteristics external to the site are expected to be minimal.




P +61 7 5211 1003        A 37 Mary St, Noosaville Qld 4566     E [email protected]        recorconsulting.com

Page 4

                    PO5
                    Stormwater drainage infrastructure is aligned to avoid crossing waterways,
                    wetlands, drainage lines and ecological important areas, or where it is
                    demonstrated this is unavoidable, disturbed areas are reinstated and revegetated
                    upon completion of works.

                    PO6
                    Development is located, designed, constructed and operated to protect and
                    enhance environmental values and water quality of waterways, wetlands, lakes,
                    ground waters and drainage systems.

            The drainage infrastructure proposed for the development does not cross waters ways,
            wetlands, drainage lines and ecologically important areas. Drainage characteristics
            downstream of the proposed development will be sufficiently similar to pre-development
            conditions as described above, with the proposed outlet for the development into a gully
            to which existing flows currently are collected. Additionally, disturbed areas arising from
            the earthworks are to be stabilised with grass seeding after construction to minimise
            sediment losses from the proposed development and maintain the water quality of the
            downstream receiving water.

            The environmental values and water quality of the receiving waters will be maintained
            through the provision of erosion and sediment controls during construction in accordance
            with the Erosion and Sediment Control Plan submitted with the application. Post
            construction, stabilising of disturbed areas to minimise any risk of ongoing water quality
            impacts from the earthworks.


                    PO10
                    Development prevents increased bed and bank erosion and sedimentation in
                    receiving waterways by avoiding changes in low rate, peak flow run-off and flow
                    duration.

            An assessment of the estimated peak flows from the pre-development area and from the
            earthworks pad was carried out to determine the impacts arising to peak flows for
            different storm events using the rational method to provide an indication of the scale of
            the change. A summary of the comparison is provided below – refer to the attached
            calculations for further detail.

              Qy (m3/s) - Pre-developed    Qy (m3/s) - Earthworks       Change (L/s)     % Change
                                    0.0331                       0.0346           1.5889      0.0481
                                    0.0399                       0.0416           1.7136      0.0430
                                    0.0602                       0.0628           2.5536      0.0424
                                    0.0740                       0.0777           3.6587      0.0494
                                    0.0891                       0.0929           3.8416      0.0431
                                    0.1129                       0.1176           4.7227      0.0418
                                    0.1301                       0.1353           5.1968      0.0399




P +61 7 5211 1003        A 37 Mary St, Noosaville Qld 4566   E [email protected]       recorconsulting.com

Page 5

            It was found that run-off stormwater peak and low rate storm flows resulting from the
            earthworks are altered by less than 5%, which is considered an insignificant increase in
            potential to increase bed or bank erosion or sedimentation in receiving waterways. The
            provision of energy dissipating outlets to reduce flow velocity and disperse concentrated
            flows will further reduce the potential of this increase having negative impacts to the
            downstream waterways.
                    PO13
                    Development is designed and constructed to maintain surface and ground water
                    balances that sustain the environmental values of water dependent ecosystems,
                    including downstream aquatic, riparian, wetland and terrestrial ecosystems.


            No attenuation or capture surface run-off is proposed, with all run-off from upstream
            catchments and the proposed development areas discharge into the drainage gully to
            which they would fall in the absence of the development. A geotechnical investigation
            carried out by Morrison Geotechnics of the proposed development area did not identify
            evidence of groundwater within boreholes taken from the development area, so it is not
            considered likely that the proposed development will impact upon the surface and
            ground water balances in a way that would negatively impact environmental values of
            downstream ecosystems.


                    4. If the survey plan indicates that the works extend beyond the property
                       boundary provide plans for the works to be undertaken to relocate the
                       earthworks to be within the subject site.

            A note on the design plan has been added indicating that earthworks extending across
            the boundary are to be removed and reinstated to pre-development conditions. The run-
            off that was being channelled to this area requiring a table drain at the base of the batter
            slope is now conveyed to the north to ensure it is discharged clear of the boundary so
            there are no issues with the removal of this small section of earthworks.


                        5. Provide comment on which is the preferred construction alternative and
                        provide amended plans prepared by a suitably qualified person which clearly
                        indicate the full extent of works required.

            The batters for the development will be altered in line with the geotechnical
            recommendations consisting of:

                    •   Benching the cut batter where batter height exceeds 4m with maximum slope of
                        38º
                    •   Flattening the fill batter to a maximum of 2.5H:1V

            Please refer to the attached plan which provides the updated earthwork extents required
            to comply with these design constraints.




P +61 7 5211 1003            A 37 Mary St, Noosaville Qld 4566   E [email protected]    recorconsulting.com

Page 6

            We believe the revised design as per the attached plans and as described in this letter
            addresses the requirements of the RFI, however should further information be required
            please contact this office.

            Yours faithfully,
            RECOR Pty Ltd


            Authored By                                        Reviewed By
            SIGNATURE                                          SIGNATURE




            Benjamin Parry                                     Nathan Wagstaff
            Civil Engineer                                     Manager
            BEng (Hons) MIEAust                                BEng (Hons) MIEAust CPEng NER (Civil, Structural) RPEQ




P +61 7 5211 1003          A 37 Mary St, Noosaville Qld 4566       E [email protected]                recorconsulting.com

Page 7

            Attachment A
            Design Plan




P +61 7 5211 1003   A 37 Mary St, Noosaville Qld 4566   E [email protected]   recorconsulting.com

Page 8

                                                                                                                                                                                                                                                                                                                                                         OP WORKS
                                                                                                                                                                                                                                                                                                                                                      NOT FOR CONSTRUCTION

                                                                                                                                                                                                                                 UPSTREAM SPOON DRAIN (600mm WIDE)




                                                                          134
                                                                                                                                                                                                                                 2H:1V MAX BATTER                                                                                                                            VANTAGE VSPOON DRAIN
                                                                                                                                                                                                                       2m MIN                                                                                                                                                OR EQUIVALENT




                                                                                                                                                                                                                     38
                                                                                                                                                                                                                                        2M WIDE BENCH




                                                                                                                                                                                                                       °M
                                                                                                                                                                                                                                                                                                                                                                             PIPED STORMWATER
  ANGULAR ROCK ENERGY DISSIPATOR AT OUTLET




                                                                                                                                                                                                                         AX
                                                                                                                                                                                                                                                                                                                                                                             CROSSING
                 MEAN DIAMETER (D50) 200mm                                                                 9m 450mm PIPED CROSSING




                                                                                                                                                                                                                              38
                     1.8m L x 1.2m W x 0.32m D                                                             WITH CONCRETE HEADWALL                                                                                                                       1m                      UPSTREAM SPOON DRAIN (450mm WIDE)




                                                                                                                                                                                                                                °M
                                                                                                           AND ENDWALL AT 2% SLOPE




                                                                                                                                                                                                                                  AX
                                                                                                                                                                                                                                                             22                                                                                                              ROCK ENERGY DISSIPATOR
                                                                                                                                                                                                                                                               °M
                                                                                                                                                                                                                                                                 AX




                                                             132

                                                                   134




                                                                                                136
                                                                                                                                                                                     DATUM RL 127.000
                                                                    134                                                                                                                                                                                                                                                                                                      AS CON BATTER EXTENTS
 67m Ø450mm VANTAGE CONCRETE
  VSPOON DRAIN (OR EQUIVALENT)
                   AT 1% SLOPE
                                                                                                                                                                                                                                                                                                                                                                             DESIGN BATTER EXTENTS




                                                              34 1
                                                                                                                                                                                                                                                                                                                                                                             DRAINAGE DIRECTION




                                                                                                                                                                                                                       138.084
                                                                                                                                                                                                                       138.077
                                                                                                                                                                                                                       138.063
                                                                                                                                                                                                                       134.086
                                                                                                                                                                                                                       134.541
                                                                                                                                                                                                                       134.528



                                                                                                                                                                                                                                            134.459


                                                                                                                                                                                                                                                      134.412
                                                                                                                                                                                                                                                      134.746
                                                                                                                                                                                                                                                      133.698



                                                                                                                                                                                                                                                                      130.000
                                                                                                                                                                                     DESIGN
                         0




                A
                       13




                                                                                                                                                                                                           143.531




                                                                                                                                                                                                                       139.584
                                                                                                                                                                                                                       139.095
                                                                                                                                                                                                                       138.075
                                                                                                                                                                                                                       134.086
                                                                                                                                                                                                                       134.541
                                                                                                                                                                                                                       134.538



                                                                                                                                                                                                                                            134.463


                                                                                                                                                                                                                                                      134.412
                                                                                                                                                                                                                                                      134.407
                                                                                                                                                                                                                                                      134.387



                                                                                                                                                                                                                                                                      130.000
                                                                                                                                                                                                                                                                      129.868
                                                                                                                                                                                                                                                                      129.695
                                                                                                                                                                                     SURVEY (AS CON)
                        13
                           0




                                                                                                                                                                                     CHAINAGE




                                                                                                                                                                                                                       11.409
                                                                                                                                                                                                                       16.709
                                                                                                                                                                                                                       18.027




                                                                                                                                                                                                                                                      36.676
                                                                                                                                                                                                                                                      37.401




                                                                                                                                                                                                                                                                      49.173

                                                                                                                                                                                                                                                                      51.363
                                                                                                                                                                                                                       9.325
                                                                                                                                                                                                                       10




                                                                                                                                                                                                                       20



                                                                                                                                                                                                                                            30




                                                                                                                                                                                                                                                      40




                                                                                                                                                                                                                                                                      50
                                                                                                                                                                                                           0
                                                                                                                                                                                                           A-A - LONGITUDINAL SECTION
                                                                                136 136
                                                                                                                                                                                                                          A1 HORZ SCALE 1:500
                                                                                  135.0
                                                                                                                                                                                                                          A1 VERT SCALE 1:250
 128




                                                                                          138                                                       PAD STORMWATER CATCHMENT                                                                                               UPSTREAM STORMWATER CATCHMENT
                                                                                                                                                    AREA:              0.16Ha                                                                                              AREA:             0.65Ha
                                                                                                                                                    Fi (Assumed):      20.0%                                                                                               Fi:               0.0%
                                                                                                                                                    tc (Mannings eqn): 6 Min                                                                                               tc (Friends eqn): 16 Min
                                                                                                                                                    Itc (1 IN 100):    302mm/hr                                                                                            Itc (1 IN 100):   205mm/hr

                                                                                                                                                    RATIONAL METHOD                                                                                                        RATIONAL METHOD
                                                                                                140.0

                                                                                                                                                    1hrI10:            70.2mm/hr                                                                                           1hrI10:            70.2mm/hr
                                                                                                                                                    C10:               0.74                                                                                                C10:               0.70
13




                                                                                                                                                    Fy:                1.2                                                                                                 Fy:                1.2
   0




                                                                                                                                                    Climate factor:    1.2                                                                                                 Climate factor:    1.2
    130




                                                                                                                                                    Qy = 1/360 * 0.16 * (1.2*0.74) * 302*1.2                                                                               Qy = 1/360 * 0.65 * (1.2*0.70) * 205 *1.2
                                                                                                  14




                                                                                                                                                        = 0.143m³/s                                                                                                            = 0.373m³/s
                                                                 4




                                                                                                 2
                                                              13




                                                                                                                                                    SPOON DRAIN CAPACITY (CIRCULAR)- Mannings                                                                              SPOON DRAIN CAPACITY (CIRCULAR)- Mannings
                                                                                                                                                    VANTAGE VSPOON OR EQUIVALENT                                                                                           VANTAGE VSPOON OR EQUIVALENT
                                                                                                                                                    Ø:            0.45m                                                                                                    Ø:            0.6m
          132

                                                                                                        A
                                                                                                                                                    r:            0.225m                                                                                                   r:            0.3m
                                                                                                    14                                              n:            0.013                                                                                                    n:            0.013
                                                                                                      4                                             Sf :          0.01                                                                                                     Sf :          0.015                                                         DO NOT SCALE, IF IN DOUBT ASK!
                                                                                                                                                    Area of flow: 0.08m²                                                                                                   Area of flow: 0.141m²
                             134                                                                                                                    P:            0.707m                                                                                                   P:            0.942m
                                                                                                                                                    R:            0.113m
                                                       134




                                                                                                                                                                                                                                                                           R:            0.15m
                          5.0             13                                                                                                        Qmax:              V*A                                                                                                 Qmax:               V*A
                                                                                                                                                    V:                 (1/n)*R^2/3*S^1/2                                                                                   V:                  (1/n)*R^2/3*S^1/2




                                                                                                                                                                                                                                                                                                                       MAX FLOW DEPTH
                                                                                                                                                    V:                 1.79m/s                                                                                             V:                  2.66m/s
                                       136                                                                14                                        Qmax:              0.143m³/s                                                                                           Qmax:               0.376m³/s
                                                                                                            6                                       Qmax >= Qy :       TRUE                                                                                                Qmax >= Qy :        TRUE
                                                                                                                  TREE IMPACTED BY BATTER TO
                                                                                                                  BE REMOVED OR RELOCATED                                                      STORMWATER CATCHMENT ASSESSMENT - SPOON DRAIN SIZING                                                                                       A      04/02/22 ISSUE FOR OP WORKS                                   BP
                                                 138                                                              CLEAR OF EARTHWORKS                                                                                                                                                              DIAMETER                             Rev Date Description                                        By Chk
                                  13                                                                                                                                                           BASED ON SEMI-CIRCULAR CONCRETE PIPE SPOON DRAIN
                                 8                                                                                                                                                             NOMINALLY VANTAGE VSPOONDRAIN OR APPROVED EQUIVALENT
                                                 140                                                                           EARTHWORK NOTES
                                                             14




                                                                                                                                1.    CONTRACTOR IS TO LOCATE ANY UNDERGROUND SERVICES WITHIN THE VICINITY AND NOTIFY RECOR OF ANY CONFLICTS.
                                                                                                                                2.    ALL EARTHWORKS ARE TO BE IN ACCORDANCE WITH THE REQUIREMENTS OF "GEOTECHNICAL INVESTIGATION GLOBAL STABILITY
                                                               2




                                         14
                                        0                                                                                             ASSESSMENT" DATED NOVEMBER 2021 BY MORRISON GEOTECHNIC.                                                                                                                                              [email protected]
                                                                                                                                3.    UPSTREAM CUT BATTER TO BE MAXIMUM 38° SLOPE TO A MAXIMUM 4m HEIGHT WITH 2M BENCH AND UPPER BATTER AT 38° MAXIMUM SLOPE                                                                               37 MARY ST NOOSAVILLE, QLD
            REMOVE EARTHWORKS AND                                                          77m Ø600mm VANTAGE CONCRETE                TO MAXIMUM HEIGHT OF 3.5M.                                                                                                                                                                           07 5211 1003
            REINSTATE TO EXISTING WHERE                                                    VSPOON DRAIN (OR EQUIVALENT)         4.    DOWNSTREAM FILL BATTER TO BE MAXIMUM 2.5H:1V SLOPE                                                                                                                                                Client
                                                  14




            EARTHWORKS HAVE EXTENEDED                                                      MIN 1.5% SLOPE                       5.    FOLLOWING STRIPPING AND EXCAVATION OF PAD TO DESIGN LEVELS, PROOF ROLL TO IDENTIFY ANY SOFT SPOTS. SOFT SPOTS TO BE                                                                               GEOFF HUSSIN
                                                 2




            BEYOND PROPERTY BOUNDARY
                                                                                                                                      EXCAVATED AND REPLACED WITH SELECT FILL.                                                                                                                                                          Project Name

                                                                                                                                6.    ALL FILL TO BE COMPACTED AT +1-2% OPTIMUM MOISTURE CONTENT FOR STANDARD COMPACTION, AND FILL PLACED IN LAYERS MAXIMUM                                                                             36 TUNBA COURT
                                                                                                                                                                                                                                                                                                                                        COOROY MOUNTAIN
                                                                                                                                      150mm TO 200mm THICK (LOOSER THICKNESS) AND COMPACTED TO ACHIEVE DRY DENSITY RATIO OF MINIMUM 95% MAX DRY DENSITY
                                                                                                                                7.    TEMPORARY OPEN SWALES AND DIVERSION DRAINS TO BE PLACED UPSTREAM OF EARTHWORKS DURING CONSTRUCTION TO PROTECT
                                                       14




                                                                                                                                      EXCAVATION FROM SURFACE RUN-OFF.
                                                       4




                                                                                                                                                                                                                                                                                                                                         Title
                                                                                                                                8.    GRADE FINISHED SURFACES LOCALLY TOWARDS THE DRAINAGE LINE TO ENSURE FINISHED SURFACE IS FREE DRAINING AND WITHOUT                                                                                 BULK EARTHWORKS PLAN
                                                                                                                                      AREAS SUBJECT TO PONDING.
                                                                                                                                9.    VANTAGE VSPOON DRAINS (OR APPROVED EQUIVALENT) ARE TO BE INSTALLED IN ACCORDANCE WITH MANUFACTURERS REQUIREMENTS
                                                                                                                                      AND SPECIFICATIONS.
                                                             14




                                                                                                                                10.   CONCRETE HEADWALLS AND PIPES ARE TO BE INSTALLED IN ACCORDANCE WITH MANUFACTURERS REQUIREMENTS AND SPECIFICATIONS.
                                                             6




                                                                                                                                11.   STORMWATER TO DISCHARGE THROUGH ROCKY ENERGY DISSIPATOR COMPRISED OF 320mm THICKNESS OF ANGULAR ROCK, WITH MEAN                                                                                   Project No.            Discipline             Status
                                                                                                                                      DIAMETER OF 200mm TO PREVENT EROSION AND SCOUR AT OUTLETS.                                                                                                                                                  20220004                  CIVIL             PRELIMINARY
                                                                                                                                12.   EROSION AND SEDIMENT CONTROLS ARE TO BE IMPLEMENTED IN ACCORDANCE WITH THE EROSION AND SEDIMENT CONTROL PLAN                                                                                      Designed By            Drawn By               Scale
                                                                                                                                                                                                                                                                                                                                                                                                 1:400
                                                                                                                                      PREPARED BY AUSSIE ENVIRONMENTAL.                                                                                                                                                                                BRP                  BRP                            (at A3)

                                                                                                                                13.   ALL EXPOSED SURFACES ARE TO BE STABILISED WITH GRASS SEEDING OR TURFING AS SOON AS PRACTICABLE FOLLOWING COMPLETION OF                                                                             Drawing No.                                                Revision

                                                                                                                                      EARTHWORKS.                                                                                                                                                                                                C30                                                       A

Page 9

            Attachment B
            Stormwater Assessment




P +61 7 5211 1003   A 37 Mary St, Noosaville Qld 4566   E [email protected]   recorconsulting.com

Page 10

Rational Method Calculations
Project number:                                    20220004                                                                                                        Calculations:                                       B. Parry
Street Address:                                    36 Tunba Ct
Locality:                                          Cooroy Mountain, Noosa Shire Council                                                                            Date:                                               8/02/2022




                                                                                                                          Pre-post earthworks run-off conditions

Pre-development Earthworks Pad
                                                                                      2
Impervious Surface                                                              0 m
                                                                                   2
Permeable Area                                                               1600 m

Total Site Area:                                                             1600 m2


Time of Concentration
                                                                                                                                                                   Time of Concentration
Sheet flow (Friends Eqn.)
                                        Length                                  47 m                                                                                                            Standard Inlet time                   5 mins
                                   Horton's n                                 0.04 Densely grassed
                            Fall over distance                                14.5 m                                                                               Pipe Flow
                                         Slope                                30.9 %                                                                                                                  Flow distance                66.00 m
                                          Time                                 7.8 mins                                                                                                                       Slope                    1 %
                                                                                                                                                                                                      Pipe Diameter                 0.45 m
                                              Tc                               8.0 mins                                                                                               Flow velocity (Mannings eqn.)                 1.79 m/s
                                                                                                                                                                                                               Time                 0.61 mins

                                                                                                                                                                                                              Time                   6.0 mins


Rational Method Calculations
                                   Area (Ha.)                                0.160 Ha.                                                                                                                   Area (Ha.)                0.160 Ha.
                                           fi                                0.000                                                                                                                               fi                0.000
                                          1                                                                                                                                                                    1
                                           I10                                70.2 mm/hr                                                                                                                         I10                70.2 mm/hr
                                          C10                                 0.70                                                                                                                              C10                 0.70

AEP                                                Fy                                Cy                       Iy (2100)                     Qy (m3/s)              AEP                                                 Fy                  Cy            Iy (2100)       Qy (m3/s)
                                   63.2% AEP                                   0.8                    0.560                        132.82               0.0331                                          63.2% AEP                    0.8         0.560            139.20         0.0346
                                    50% AEP                                   0.85                    0.595                        150.72               0.0399                                           50% AEP                    0.85         0.595            157.20         0.0416
                                    20% AEP                                   0.95                    0.665                        203.76               0.0602                                           20% AEP                    0.95         0.665            212.40         0.0628
                                    10% AEP                                      1                    0.700                        237.84               0.0740                                           10% AEP                       1         0.700            249.60         0.0777
                                      5% AEP                                  1.05                    0.735                        272.64               0.0891                                             5% AEP                   1.05         0.735            284.40         0.0929
                                      2% AEP                                  1.15                    0.805                        315.60               0.1129                                             2% AEP                   1.15         0.805            328.80         0.1176
                                      1% AEP                                   1.2                    0.840                        348.48               0.1301                                             1% AEP                    1.2         0.840            362.40         0.1353


Comparison Earthworks Vs Pre-development

Qy (m3/s) - Pre-developed                          Qy (m3/s) - Earthworks            Change (L/s)             % Change
                                       0.0331                               0.0346                   1.5889                          4.81
                                       0.0399                               0.0416                   1.7136                          4.30
                                       0.0602                               0.0628                   2.5536                          4.24
                                       0.0740                               0.0777                   3.6587                          4.94
                                       0.0891                               0.0929                   3.8416                          4.31
                                       0.1129                               0.1176                   4.7227                          4.18
                                       0.1301                               0.1353                   5.1968                          3.99

Page 11

Rational Method Calculations
Project number:                                     20220004                                                                                                           Calculations:                                        B. Parry
Street Address:                                     36 Tunba Ct
Locality:                                           Cooroy Mountain, Noosa Shire Council                                                                               Date:                                                8/02/2022



                                                                                                                      Catchments Assessment for Spoon drain sizing

Upstream Catchment                                                                                                                                                     Earthworks area (assuming future development)
                                                                                   2                                                                                                                                                             2
Impervious surface                                                            0 m                                                                                      Impervious Surface (Rural - fi = 20%)                             320 m
                                                                                 2                                                                                                                                                            2
Permeable Area                                                             6500 m                                                                                      Permeable Area                                                   1280 m

Total Site Area:                                                           6500 m2                                                                                     Total Site Area:                                                 1600 m2


Time of Concentration                                                                                                                                                  Time of Concentration
Existing Site                                                                                                                                                          Existing Site
                         Standard Inlet time                                  0 mins                                                                                                                 Standard Inlet time                   5 mins

Sheet flow (Friends Eqn.)                                                                                                                                              Pipe Flow
                                        Length                              133 m                                                                                                                          Flow distance                66.00 m
                                   Horton's n                              0.06 Densely grassed                                                                                                                    Slope                    1 %
                            Fall over distance                               49 m                                                                                                                          Pipe Diameter                 0.45 m
                                         Slope                             36.8 %                                                                                                          Flow velocity (Mannings eqn.)                 1.79 m/s
                                          Time                             15.9 mins                                                                                                                                Time                 0.61 mins

                                               Tc                          16.0 mins                                                                                                                               Time                   6.0 mins


Rational Method - Peak Flow Calculation
Upstream Catchment                                                                                                                                                     Earthworks Pad (assuming future development)
                                Area (Ha.)                                0.650 Ha.                                                                                                                           Area (Ha.)                0.160 Ha.
                                        fi                                0.000                                                                                                                                       fi                0.200
                                           1                                                                                                                                                                         1
                                            I10                            70.2 mm/hr                                                                                                                                 I10                70.2 mm/hr
                                           C10                             0.70                                                                                                                                      C10                 0.74

AEP                                                 Fy                            Cy                      Iy (2100)                        Qy (m3/s)                   AEP                                                  Fy                  Cy            Iy (2100)       Qy (m3/s)
                                   63.2% AEP                                0.8                   0.560                            97.87                      0.0990                                          63.2% AEP                   0.8         0.592            139.20         0.0366
                                    50% AEP                                0.85                   0.595                           110.40                      0.1186                                           50% AEP                   0.85         0.629            157.20         0.0439
                                    20% AEP                                0.95                   0.665                           148.56                      0.1784                                           20% AEP                   0.95         0.703            212.40         0.0664
                                    10% AEP                                   1                   0.700                           173.04                      0.2187                                           10% AEP                      1         0.740            249.60         0.0821
                                      5% AEP                               1.05                   0.735                           196.56                      0.2609                                             5% AEP                  1.05         0.777            284.40         0.0982
                                      2% AEP                               1.15                   0.805                           225.84                      0.3283                                             2% AEP                  1.15         0.851            328.80         0.1244
                                      1% AEP                                1.2                   0.840                           246.96                      0.3746                                             1% AEP                   1.2         0.888            362.40         0.1430


Channel Sizing
Using Manning's Eqn - V = R 2/3. Sf1/2/n

                                            D                                0.6 m                                                                                                                                    D                  0.45 m
                                              r                              0.3 m                                                                                                                                      r               0.225 m
                                             n                            0.013                                                                                                                                        n                0.013
                                      Sf (min)                            0.015 m/m                                                                                                                             Sf (min)                0.010 m/m
                                             A                            0.141 m²                                                                                                                                     A                0.080 m²
                                             P                            0.942 m                                                                                                                                      P                0.707 m
                                             R                            0.150 m                                                                                                                                      R                0.113 m
                                             V                            2.660 m/s                                                                                                                                    V                1.793 m/s
                                      QCapacity                           0.376 >=                                                  0.37               TRUE                                                     QCapacity               0.143 >=                       0.143      TRUE

Page 12

IFDs Frequent and Infrequent Storm Events
Project number:     20220004
Street Address:     36 Tunba Ct
Locality:           Cooroy Mountain, Noosa Shire Council

Source :           http://www.bom.gov.au/water/designRainfalls/revised-ifd/

Location:          Latitude:
                     -26.4248 [Nearest grid cell: 26.4125 (S)]
                   Longitude:
                   152.966 [Nearest grid cell: 152.9625 (E)]

Date obtained:          3/02/2022

                       Annual
                     Exceedance
                                                                                                                              Climate factor (1.2)
                     Probability
                        (AEP)
Duration               63.20%            50%#              20%*          10%           5%           2%           1%                 63.20%           50%#            20%*            10%            5%            2%            1%
1 min                          167              189               254           298          339          392          431                   200.4           226.8           304.8          357.6         406.8         470.4         517.2
2 min                          142              161               220           261          301          356          399                   170.4           193.2             264          313.2         361.2         427.2         478.8
3 min                          134              151               206           244          281          330          368                   160.8           181.2           247.2          292.8         337.2           396         441.6
4 min                          127              144               195           230          264          308          342                   152.4           172.8             234            276         316.8         369.6         410.4
5 min                          121              137               186           218          250          290          321                   145.2           164.4           223.2          261.6           300           348         385.2
6 min                          116              131               177           208          237          274          302                   139.2           157.2           212.4          249.6         284.4         328.8         362.4
8 min                      110.68              125.6             169.8         198.2        227.2         263         290.4                132.816          150.72          203.76         237.84        272.64         315.6        348.48
10 min                        98.8              112               150           175          199          229          251                  118.56           134.4             180            210         238.8         274.8         301.2
15 min                        83.7              94.4              127           148          168          193          211                  100.44          113.28           152.4          177.6         201.6         231.6         253.2
16 min                       81.56                92             123.8         144.2        163.8        188.2        205.8                 97.872           110.4          148.56         173.04        196.56        225.84        246.96
20 min                           73             82.4              111           129          147          169          185                    87.6           98.88           133.2          154.8         176.4         202.8           222
25 min                        65.1              73.4              98.8          115          131          152          167                   78.12           88.08          118.56            138         157.2         182.4         200.4
30 min                           59             66.5              89.7          105          120          138          152                    70.8            79.8          107.64            126           144         165.6         182.4
45 min                        46.7              52.8              71.6          84.2         96.4         112          125                   56.04           63.36           85.92         101.04        115.68         134.4           150
1 hour                        39.3              44.5              60.7          71.7         82.4         96.7         108                   47.16            53.4           72.84          86.04         98.88        116.04         129.6
1.5 hour                      30.7              34.8                48            57           66           78         87.3                  36.84           41.76            57.6           68.4          79.2          93.6        104.76
2 hour                        25.7              29.3              40.6          48.5         56.4           67         75.2                  30.84           35.16           48.72           58.2         67.68          80.4         90.24
3 hour                           20             22.9              32.2          38.7         45.3         54.1         61.1                     24           27.48           38.64          46.44         54.36         64.92         73.32
4.5 hour                      15.7                18              25.7          31.1         36.5         43.9         49.7                  18.84            21.6           30.84          37.32          43.8         52.68         59.64
6 hour                        13.2              15.2              21.9          26.6         31.4         37.8           43                  15.84           18.24           26.28          31.92         37.68         45.36          51.6
9 hour                        10.3                12              17.5          21.4         25.3         30.7           35                  12.36            14.4              21          25.68         30.36         36.84            42
12 hour                       8.69              10.1              14.9          18.3         21.8         26.5         30.2                 10.428           12.12           17.88          21.96         26.16          31.8         36.24
18 hour                       6.77              7.95              11.8          14.6         17.5         21.3         24.4                  8.124            9.54           14.16          17.52            21         25.56         29.28
24 hour                       5.64              6.64              9.94          12.3         14.8         18.2         20.9                  6.768           7.968          11.928          14.76         17.76         21.84         25.08
30 hour                       4.87              5.74              8.64          10.8           13           16         18.5                  5.844           6.888          10.368          12.96          15.6          19.2          22.2
36 hour                       4.31              5.08              7.68           9.6         11.6         14.4         16.6                  5.172           6.096           9.216          11.52         13.92         17.28         19.92
48 hour                       3.52              4.16              6.32          7.93         9.64           12         13.9                  4.224           4.992           7.584          9.516        11.568          14.4         16.68
72 hour                       2.62              3.09              4.71          5.94         7.26         9.13         10.7                  3.144           3.708           5.652          7.128         8.712        10.956         12.84
96 hour                        2.1              2.48              3.77          4.77         5.86         7.38         8.66                   2.52           2.976           4.524          5.724         7.032         8.856        10.392
120 hour                      1.77              2.08              3.16             4         4.91          6.2         7.28                  2.124           2.496           3.792            4.8         5.892          7.44         8.736
144 hour                      1.54               1.8              2.73          3.45         4.23         5.33         6.25                  1.848            2.16           3.276           4.14         5.076         6.396           7.5
168 hour                      1.37               1.6              2.42          3.04         3.72         4.67         5.46                  1.644            1.92           2.904          3.648         4.464         5.604         6.552


[OCR of page images]
 

iebs Frequent and infrequent Storm Events we
Projet number" 20220008 ae
street Address: 36 Tunba ct As

 

 

Locality Cooroy Mountain, Noosa Shire Council
Source Tittpi//www.bom.gov.au/water/designRainfalls/revised 1d),
Location: Latitude:
-26.4248 [Nearest grid cell: 26.4125 (S)]
Longitude

152.966 [Nearest grid cell: 152.9625 (E)]
Date obtained: 3/02/2022
Annual

Exceedance
Probability

Climate factor (1.2)

63.20% 63.20%

[10 min
115 min
[16 min
[20 min
[25 min
[30 min
[45 min

[1 hour
1.5 hour
2 hour

[3 hour
4.5 hour
[6 hour

[9 hour
112 hour
[18 hour
[24 hour
'30 hour
[36 hour
[48 hour
[72 hour
[96 hour
1120 hour
[144 hour
[168 hour

  

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.