Response to Information Request 20220004 -Tunba Court
Attached to the e-mail Response to Information Request OPW21/0355 - 36 Tunba Court, Cooroy Mountain.
It was found that run-off stormwater peak and low rate storm flows resulting from the
earthworks are altered by less than 5%, which is considered an insignificant increase in
potential to increase bed or bank erosion or sedimentation in receiving waterways. The
provision of energy dissipating outlets to reduce flow velocity and disperse concentrated
flows will further reduce the potential of this increase having negative impacts to the
downstream waterways.
PO13
Development is designed and constructed to maintain surface and ground water
balances that sustain the environmental values of water dependent ecosystems,
including downstream aquatic, riparian, wetland and terrestrial ecosystems.
No attenuation or capture surface run-off is proposed, with all run-off from upstream
catchments and the proposed development areas discharge into the drainage gully to
which they would fall in the absence of the development. A geotechnical investigation
carried out by Morrison Geotechnics of the proposed development area did not identify
evidence of groundwater within boreholes taken from the development area, so it is not
considered likely that the proposed development will impact upon the surface and
ground water balances in a way that would negatively impact environmental values of
downstream ecosystems.
4. If the survey plan indicates that the works extend beyond the property
boundary provide plans for the works to be undertaken to relocate the
earthworks to be within the subject site.
A note on the design plan has been added indicating that earthworks extending across
the boundary are to be removed and reinstated to pre-development conditions. The run-
off that was being channelled to this area requiring a table drain at the base of the batter
slope is now conveyed to the north to ensure it is discharged clear of the boundary so
there are no issues with the removal of this small section of earthworks.
5. Provide comment on which is the preferred construction alternative and
provide amended plans prepared by a suitably qualified person which clearly
indicate the full extent of works required.
The batters for the development will be altered in line with the geotechnical
recommendations consisting of:
• Benching the cut batter where batter height exceeds 4m with maximum slope of
38º
• Flattening the fill batter to a maximum of 2.5H:1V
Please refer to the attached plan which provides the updated earthwork extents required
to comply with these design constraints.
P +61 7 5211 1003 A 37 Mary St, Noosaville Qld 4566 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.