                                                                                  23098 - SBSMP/2
                                                                                          Page 11




                                     Table 5-5 - Comparison of Peak Flows
                             XPSTORM          XPSTORM                 XPSTORM            XPSTORM
         XPSTORM Total
                          Post-development Post-development        Post-development       Total Post-
  ARI    Pre-development
                          Flows into Tanks Bypass Flows (Un -      Flows from Tanks   development Flows
(years) Flows (Catchment)
                3          (Un -Mitigated)     Mitigated)             (Mitigated)         (Mitigated)
              (m /s)
                                (m3/s)           (m3/s)                  (m3/s)             (m3/s)
   1            0.040               0.038                  0.021        0.019               0.040

   2            0.047               0.043                  0.024        0.021               0.046

   5            0.069               0.057                  0.036        0.026               0.062

  10            0.083               0.064                  0.043        0.029               0.072

  20            0.095               0.073                  0.050        0.039               0.089

  50            0.117               0.084                  0.070        0.039               0.109

 100            0.132               0.092                  0.086        0.039               0.125


As can be seen, the XPSTORM pre-development results are comparable to Rational Method for all
storm events, as they are generally within 10% to the Rational Method results. Therefore, the results
show that a reasonable validation in peak flows has been achieved from the XPSTORM model when
compared to Rational Method and is considered acceptable in assessing for mitigation of post
development flows.

Subsequently, the XPSTORM hydraulic modelling results have demonstrated that the proposed
mitigation implemented will maintain pre-development flows (or less) for all design storms at the
LPD located northeast of the subject site.

Refer to Appendix H for the pre-development XPSTORM results, Appendix I for the post-
development XPSTORM results and Appendix J for the XPSTORM post-development mitigated
results.




Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy
Log in to download the original file

Appendix B- SWMP.pdf · 4.8 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.