Appendix B- SWMP
23098 - SBSMP/2
Page 13
All new stormwater pits are to be protected from sediment infiltration by wrapping new pits and
grates in geofabric or covering appropriately with timber board. Silt fences are to remain in place
during the maintenance period until the site is established (80% ground cover).
Potential sources of contaminants identified for the construction phase of the development are
outlined in Table 6-2 together with proposed stormwater quality improvement devices,
management and maintenance procedures.
Table 6-2 - Potential Contaminants and Proposed Treatments
Proposed Treatment
Management /
Pollutant Potential Source Device and Maintenance
Maintenance Procedures
Procedure
Sediment & Excavated material, fill Provision of sediment and Sand filled filter socks.
Eroded material, exposed silt barriers to the site Removal of excess
material ground, stockpiles of drainage entry and exit sand/silt build-up at
material. points. regular intervals and
after every storm.
Dust Stockpiles of material, Covering the material or Coverage of material
exposed ground. wetting it down at with plastic, geotextile,
regular intervals. surface binding agents or
regular watering.
Litter Refuse generated by Construction waste is to Industrial bin is to be
staff. be cleaned off the site provided within the
area and disposed of into construction area - to be
an industrial bin then emptied on at least a
removed by a refuse weekly basis.
collection contractor.
Concrete Washing of concrete Provision of a closed area Liquids to be removed by
trucks/tools to remove onsite for washing off of a waste collection
wet/unused concrete. concrete slurries. contractor. Solids to be
placed into a refuse bin.
Surfactants Washing down operations No cleaning of vehicles Monitoring & prevention
(detergents) on hardstand area using will be permitted on site.
detergents.
Chemical Typically this may occur Where spills occur, the A temporary containment
(Paints, due to spillage of containment area is to area. This is to be
thinners etc.) product. stop escape. The impermeable and of a
material is to be treated size to permit
(as required) and mixing/transfer, and
removed and cleaned by with a storage volume of
a licensed contractor. twice the largest
Minor spillage outside container used.
this area shall be cleaned Treatment of spills is to
up with cloths and occur on site. No
disposed of to waste via discharge of treated
the industrial bin. water to the stormwater
system is to occur
without council approval.
Incidents are to be
reported to the EPA.
Wastewater Spillage from the A licensed contractor No leakage is to be
relocation of the existing shall remove any residue permitted to enter the
sewerage reticulation. sewage from unused groundwater or discharge
pipes and contaminated to the stormwater
soils are to be disposed system.
of via the industrial bin.
Site Based Stormwater Management Plan
Proposed Townhouse Development at 5 Pearl Street, Cooroy
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.