Delegated Report - Code - Planning MCU22 0145 [As Published] · MCU22/0145

of 28

Text shows just the words. Original shows the document exactly as it was published.

                           ED 22266 OPW - 05         D      Plant List & Specification Plan by 30/06/2023
                                                            Element Design


                      Currency Period
               2.     This development approval lapses if the use has not happened by 15 August 2025, unless
                      an application to extend the currency period is approved by Council.


               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               3.     Tree protection fencing must be installed under the supervision of the Project Arborist. (Refer
                      to Retention of Existing Trees Conditions).
               4.     All necessary approvals from external service providers (e.g., Unitywater) and external
                      parties on which the development works are proposed have been obtained and a copy
                      supplied to Council.
               5.     A condition report including photographs of the frontage of the site must be completed and
                      submitted to Council at the prestart meeting / prior to any works commencing.
               6.     Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               7.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Landscape works;
                      c.      Erosion and sediment control works;
                      d.      Other relevant parties
               8.     A Construction Management Plan must be submitted to Council at least 5 business days
                      prior to the pre-start meeting and must specifically address the following:
                      a.      Traffic Management during all aspects of the construct phase including:
                              i.       A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures prior to construction.
                              ii.      Maintenance of safe vehicle and pedestrian access across the frontage of the
                                       site both during daily construction and after daily construction has ceased
                              iii.     Proposed fencing to the site during the construction phase of the development
                              iv.      Adequate parking arrangements for construction workers
                              v.       No queuing of trucks is permitted on residential streets, especially prior to
                                       7.00am. Further parked trucks must have engines turned off
                      b.      Maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures
                      c.      Works programme identifying key components of the works and their respective
                              durations



                                                                                                       Page 19 of 28

Document Set ID: 22322758
Version: 7, Version Date: 22/08/2023

Used in these records

About this file

File size
6.1 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning MCU22 0145 [As Published].pdf · 6.1 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.