1211 - Engineering Report Complete C · 132002.220527.1
Attached to the e-mail 132002.220527.1 Change to Existing Approval Engineering & Geo tech reports (1of 6 emails).
p: 07 5453 4494 e: [email protected] a: PO Box 432, Buderim Q 4556 w: www.barlowshelley.com.au ENGINEERING REPORT For Building Alterations at 17 WEBB ROAD, SUNSHINE BEACH For M & M CHARLTON Ref: 1211 ENG-01_Version 1.0 APRIL 2015
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 12 pages
Page 2
DOCUMENT INFORMATION Document Title: Engineering Report Document Reference No. ENG_1211 Commissioned By: M &M Charlton Prepared By: Barlow Shelley Consulting Engineers Pty Ltd Author: Peter Barlow Reviewed & Authorised By: Peter Barlow DOCUMENT CONTROL Version Date Author Reviewer 1.0 April 2015 P. Barlow C. Landreth “©2015 Barlow Shelley Consulting Engineers Pty Ltd All Rights Reserved. Copyright in the whole and every part of this document belongs to Barlow Shelley Consulting Engineers Pty Ltd and may not be used, sold, transferred, copied or reproduced in whole or in part in any manner or form or in or on any media to any person without the prior written of Barlow Shelley Consulting Engineers Pty Ltd”
Page 3
CONTENTS 1.0 GEOTECHNICAL OVERVIEW .......cccscccsssesceceecneecnsscnsscesssesssessensneesssnssnssansansarseanseanseaneee T 2.0 STORMWATER MANAGEMENT PLAN ............00008 2.1 Existing Stormwater Runoff from Webb Road 2.2 Exisitng Drainage System.... 2.3 Proposed Drainage System.... ww NY RD 2.4 Stormwater Discharge .......0scceseeccsenerceeeeeeeeeeseeeeeseaeseanaesseneesceeeeseeeseseaeseseaessananssanenseene 3.0 STRUCTURAL ENGINEERING FOR RENOVATIONG.........00ccccssscssses seers seers sseneesseneeseen APPENDICES APPENDIXA - ENGINEERING DRAWINGS
Page 4
1.0 GEOTECHNICAL OVERVIEW Prior to undertaking any building alterations, one of the most important investigations for this site is the Geotechnical Investigation. Please refer to the accompanying Geotechnical Investigation Report No.14169-001-RevO by Tectonic Geotechnical & Environmental Engineers. The geotechnical results show that the site has a Low Risk of global slope instability, and that footings for the new house alterations can be adequately founded on site without any erosion problems. Additionally this geotechnical report provided permeability results to aid the stormwater management of the site. Generally the site is stable and well suited for the residential alterations proposed. Engineering Report Page 1 of 11 1211-ENG-01_Version 1.0 (April 2015)
Page 5
2.0 STORMWATER MANAGEMENT PLAN 2.1 Existing Stormwater Runoff from Webb Road One of the main reasons that the existing residence is often inundated with stormwater runoff, is because stormwater from Webb Road spills over the kerb and channel and runs down the private driveway to the house. As detailed on our Stormwater Management Plan No. 1211/P02 and on our driveway longsection Plan No. 1211/P03, this existing runoff from Webb Road will be redirected to the Council Stormwater pit in the kerb and channel as legally intended. This will be achieved by increasing the flood freeboard in the footpath by lifting the vertical curve crest in the new driveway, thus providing a bund against stormwater runoff from the road. 2.2 Existing Drainage System The ground floor level of the existing residence is RL15.85m. The driveway to the residence drops from RL20.9 at Webb Road to RL15.81m adjacent to the existing house. Attached Drawing No. 1211/P01 shows the layout of the existing driveway and residence. Due to the steep drop along the sealed driveway and the sealed forecourt in front of the house, stormwater runoff velocity is very significant by the time the stormwater reaches the existing house. Presently two grated drains, as shown on the attached Drawing No.1211/P01, have been installed to intercept stormwater runoff from the driveway and forecourt, upstream of the existing house. There is also a third open concrete drain on the north west boundary which intercepts stormwater from the adjacent property. Unfortunately the two grated drains in the driveway and the forecourt are often overtopped by Stormwater Runoff from storms greater than a 2 year ARI storm. As can be seen the floor level of the house at RL15.85m, is only 4cm higher than the grated drain which catches stormwater runoff immediately upstream of the house. The reason for this inundation is that the drains have not been designed for a 100 year ARI storm, they are often clogged by debris, and the drain level is only 4cm below the floor level of the house. As a consequence the existing residence is often inundated by stormwater runoff during short heavy storms (over a 2 year ARI storm). This is one of the main reasons the alterations are proposed for this residence. The only safe drainage system is to have an Engineering Report Page 2 of 11 1211-ENG-01_Version 1.0 (April 2015)
Page 6
overflow drainage path that can never be blocked, and surface levels that grade away from the ground floor level of the house. 2.3 Proposed Drainage System Please refer to our attached Drawing No. 1211/P02 which shows the proposed new drainage system to the altered residence. There are several features to note: Firstly, all runoff from the driveway will be directed into a side entry gully pit (Council standard) which cannot be blocked (i.e the overflow from the grate is still intercepted in the side letterbox opening which is lower than the paved driveway). Secondly, the underground drainage system will be designed for a 10 year ARI storm event, which is much greater capacity than current system. Thirdly, the finished surface level of the driveway and forecourt will be lowered and graded away from the ground floor level of the house alterations. Finally and most importantly, an overflow flow path is diverted around the house. Therefore even if all the underground pipes become blocked, the surface levels will direct a 100 year ARI storm runoff away from the house and around the southern part of the house alteration. Therefore there will be no storm events that can inundate the altered house floor levels. 2.4 Stormwater Discharge Please refer to attached Geotechnical Report No.14169-001-RevO by Tectonic Geotechnical & Environmental Engineers. They were tasked with identifying a safe and secure method of discharging stormwater from the site, which did not cause erosion or instability to the site. To ensure stormwater runoff quality, every stormwater collection pit will be fitted with an approved filter basket to remove gross pollutants. Permeability results from the site show that a lined infiltration bore 5 metres downstream of the house provides the best solution for stormwater discharge. Please refer to our Drawing No. 1211/P02 which shows the infiltration bore proposed. The proposed Engineering Report Page 3 of 11 1211-ENG-01_Version 1.0 (April 2015)
Page 7
stormwater discharge shown on Drawing No.1211/P02, complies with recommendations from the Geotechnical Report for the site. 3.0 STRUCTURAL ENGINEERING FOR RENOVATIONS In order to solve the drainage inundation problem, the floor level of the altered house will be raised over the existing slab. Enclosed is our preliminary Drawing No. 1211/P05 which shows the waffle slab system on top of the existing house slab. Footings for altered load bearing walls will be taken through the existing slab to acceptable bearing material as specified in attached Geotechnical Report No.14169-001- Rev0 by Tectonic Geotechnical & Environmental Engineers. The structural section of the house enclosed, shows the proposed new retaining wall external to the house. It has been designed to help resolve the current stormwater inundation problem. 4.0 CONCLUSION This report and the accompanying engineering drawings were undertaken at preliminary building stage to ensure that the proposed house alterations are compatible with the existing site, and that all engineering issues can be satisfactorily addressed at Building Application stage. It is our engineering opinion that the alterations to this house will overcome the current drainage inundation problems, and that the alterations will be structurally suitable for this site. (alow PETER BARLOW -— DIRECTOR (RPEQ 1330) BEng, MIEAust, CPEng, RPEQ For and on behalf of: BARLOW SHELLEY CONSULTING ENGINEERS PTY LTD Engineering Report Page 4 of 11 1211-ENG-01_Version 1.0 (April 2015)
Page 8
ENGINEERING DRAWINGS Drawing Nos 1211/P01 to 1211/P05 Prepared by Barlow Shelley Consulting Engineers
Page 9
WEBB RD
= LEGEND
Gg
EXISTING DRIVEWAY
AS ——— base rorsonosnes
VS ExistING
FFL 16.01
EXISTING LEVELS
EXISTING TREE
EXISTING BULDINGS
EXISTING CONCRETE
—=>- EXISTING STORMIATER FLOW
SV SW EXISTING STORMWATER PIPE
EXISTING LEVEL
x SL-1623
FORECOURT
EXISTING RESIDENCE
EXISTING <
FFL 16.06,
EXISTING DRAINAGE
INUNDATION
SL 15.80
/ EXISTING
FFL 15.85
=p [= Ppamescma] sone (| arrose PSroaan nesoenrns arena
V AT 17 WEBB RD, SUNSHINE BEACH
° 2 4 6 8 10 on 2 FOR MURRAY & MARGIE CHARLTON
Director: PETER BARLOW DRAWING TITLE:
SCALE 1:200 A3. (RPEQ 1330) EXISTING SITE LAYOUT
bsscsinjarinscnirnmescuhesininseminnion | DRAWING STATUS D 5 craic ase w evehenhbjoras STORMWATER DRAINAGE
pte Sato Cooning Engraae : 8 POBa432Suderm4S85 AGN 42135766613
Page 10
'WEBB RD /
ON ame TO BE LIFTED
‘200mm TO KEEP WEBB RD
DRAINAGE OUT.
LEGEND
PROPOSED DRIVEWAY
EXISTING LOT BOUNDARIES
EXISTINGLEVELS
ISTING TREE
EXISTING BUILDINGS
PROPOSED HOUSE
PROPOSE
EXISTING LEVEL.
PROPOSED GRADE
EXISTING GRADE
INFILTRATION AS PER GEOTECH
REPORT,
is ring at woe
‘SCALE 1200 43,
Director: PETER BARLOW
(RPEQ 1330)
DRAWING STATUS
NOT FOR CONSTRUCTION
OFFL 14.30
PROPOSED
RESIDENCE
@ offeeGhalowtndeycomau WW wwwbarbushally com ay
8 POBa432Suderm4S85 AGN 42135766613
PROWEGT
PROPOSED RESIDENTIAL ALTERATION
AT 17 WEBB RD, SUNSHINE BEACH
FOR MURRAY & MARGIE CHARLTON
PROPOSED STORMWATER FLOW
PROPOSED STORMWATER PIPES
AND PITS:
PROPOSED CENTRELINE.
Tos NOWEER
1211
DRAWING TITLE:
PROPOSED SITE LAYOUT
STORMWATER MANAGEMENT PLAN
Page 11
1P.6804, 21.126 JOIN SMOOTHLY TO EXISTING LP.2.694, 20.963 EXISTING SURFAC: 792, 16.500 PROPOSED DRAINAGE PATH P.55.908, 15.100 12.8% 2.5% ~1.008% -7.140% 1.1444 GRADE DATUM R.L.13.0 CUT(-)/FILL(+) DESIGN SURFACE LEVELS NATURAL SURFACE LEVELS CHAINAGE DRIVEWAY LONGITUDINAL SECTION ‘Seale - Vert. 1:100 Scale - Horiz, 1:500 ROE B a rlovw PROPOSED RESIDENTIAL ALTERATION AT 17 WEBB RD, SUNSHINE BEACH on She e FOR MURRAY & MARGIE CHARLTON Director: PETER BARLOW DRAWING TITLE: (RPEQ 1330) “— PROPOSED DRIVEWAY AND DRAINAGE LONGSECTIO! DRAWING STATUS NOT FOR CONSTRUCTION @ offeeGhalowtndeycomau WW wwwbarbushally com ay 8 POBa432Suderm4S85 AGN 42135766613
Page 12
PROPOSED HOUSE ¢ 2 OVERLAND DRAINAGE PATH GARAGE 3% wee RL14.00 Grade Level 15.100 CH 55.399 Ly SECTION A 7:200 (A3) PROWEGT PROPOSED RESIDENTIAL ALTERATION =RE== [+ -peecsns[ scr es 0 Barlow ~ AT 17 WEBB RD, SUNSHINE BEACH 5 Sp FOR MURRAY & MARGIE CHARLTON Ee Shelley Be PRELIMINARY CROSS SECTION SCALE 17200 A3 (APEQ 1330) 1p OT 549% DRAWING STATUS be cag wine . @ offeeGhalowtndeycomau WW wwwbarbushally com ay . iia 9 NOT FOR CONSTRUCTION 8 PO Baud Bude 5 ABN 4? 135768813.
Page 13
PROPOSED HOUSE STORMWATER RUNOFF EXISTING HOUSE SLAB | WAFFLE SLAB SYSTENON FETANNG WAL STING OV EXISTING EXISTING SLAB, ‘SLAB. (NOTE: BEARING NOT ISSUE) FOOTINGS FOR LOADING WALLS AS PER GEOTECHNICAL REPORT =p [= Papamescma] sone (| arrose PaSroaan nesoenrns aremaron A AT 17 WEBB RD, SUNSHINE BEACH FOR MURRAY & MARGIE CHARLTON ° 2 4 6 8 100 Director: PETER BARLOW DRAWING TITLE: ‘SCALE 1:20 A3 (RPEQ 1330) A PRELIMINARY SLAB AND RETAINING WALL SECTION cedure men gemissen tom — | DRG NOE ean . @ offeeGhalowtndeycomau WW wwwbarbushally com ay . : NoT FOR CONSTRUCTION 8 POBa432Suderm4S85 AGN 42135766613 is rain i ate cpi pte Sato Cooning Engraae
Used in these records
1211 - Engineering Report Complete C.pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.2 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.