PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 20 MAY 2014
Page 74 of 143
Document No: "[Click to insert document #]"
Revision No: 001
Effective date: 6 March 2014
Next Review Date: 30 May 2014
Unit VV 7 [ € 7}: - 2 S a s -
ae Interim Connections Policy — Schedule 2: Applications
Table 4 - Standard Connections Application and Approval Information
Step Interim Connections Policy Provision
Application (Request) How do | request a Standard Connection?
e Where the Connection complies with all of the Connection Criteria for the relevant Connection listed in Table 1 - Criteria
and Conditions for Standard Connections, the applicant must do all of the following:
co Complete the Unitywater approved application form (available on Unitywater's website at www.unitywater.com),
including supplying the plans and other information specified in the form;
o Pay the fee stated in Unitywater’s Fees and Charges Schedule;
o If the Applicant is not the owner of the land related to the Connection, provide the land owner's written consent to the
application.
Note: Payment of these charges (to the extent they apply to the Connection) when the request application is lodged will reduce the time required for
Unitywater to complete the Connection and provide services to the land.
Assessment What is the timeframe for deciding the request?
Up to 5 business days (or a longer period agreed to by the Applicant) after a complete application has been received (Act,
s.99BRAU).
What happens when request is granted?
Unitywater gives the Applicant a decision notice within 5 business days after the Standard Connection is granted.
The decision notice will include: (Act, s.99BRAU, s.99BRAV, s.99BRCJ)
o The Standard Conditions listed in Table 1 - Criteria and Conditions for Standard Connections;
o The following charges (to the extent applicable):
= Charges stated in Unitywater's Fees and Charges Schedule to the extent applicable for the Connection;
Copyright © Unitywater Page 21 of 28
Printed copies are uncontrolled 74 of 143See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.