08/0255 - MCU - Detached House [As Published] · 132008.255

of 63

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

    

 
  

 

., Checklist - Applications Involving Land
+ Development & Land Use Sections

IDAS APPLICATION

This checklist should be used for any IDAS application. Please check each of the following items before accepting an
application at ihe counter.

 

 

 

 

1.1.1 Ensure that the form is fully completed.
1.1.2 Inthe case of an MCU or Op Works below the high-water mark, owners consent is required.

 

1.1.2.1 If there are multipie owners, the consent of each owner is required. .
1.1.2.2 Ifthe owner of the land is a company, either ACN No. or Company Seal required.

4.2 Form! Part B-O Supporting Information

1.4.2 Ensure that for each box checked on Form A, the relevant additional Forms B-O are attached. [-T
1.1.2.1 Ensure that each of Forms B-O which are attached are fully completed. [7]

  

3 “MFENVIRONMENTALLY: RELEVANT ACTIVITIES,

3.1. Ensure that Part G is completed if EPA referral is required.

3.2 Where EPA is delegated to Council (see * in ERA checklist), ensure that the correct application
fee is paid and recorded on the application.

RM 27 REQUEST TOIEHANGE APBROVAL FREES -

Ensure that items 1-28 have been checked and/or completed including information regarding

applicant details and owners consent.

 

 

 

 

 

 

2 REE

1 aR

      
 

 

 

     

    

   

"E won

NS!

 

5.1 Ensure that at least 6 sets of the Plan of Development (5 for Reconfiguration and Operationat
Works) accompanies the application. In addition ensure that each set is complete.

5.2 Ensure that 1 of the copies of the Plan of Development is in an A3 or A4 format and is
unbound.

 

 

 

  
    
 

 

 

Ensure that at least 6 copies of any report accompanies the application (6 for Reconfiguration
and Operational Works). If the application is accompanied by a covering letter, ensure that it is

io
capable of reproduction. (4
and is unbound.

In the case of reports, ensure that 1 of the copies is in an A3 or A4 format
2 SEE By

 

       

 

 

accompanies the application or has been paid.
7.2. Ensure that the fee which has been paid is recorded on the application form.

 

 

 

 

v

f
| Receiving Officer Lo Ate LD cceeenee rete Date AL ASE veeeetenees

pplication, please deliver boti to the followin, iDAS Applicaticn Recelving

  
  

Having completed this form and accepted th

trays:- ,

« Ifthe application is for a Material Change of Use exclusively -AOP1’s desk in the Land Use Section.

« Ifthe application is for an Material Chance of Use & Reconfiguration - AOP1's desk in the Land Use Section.

* Ifthe application is for Operational Works (for parking, access, sewerege or drainage) exclusively - AOD2 in the
Land Development Section.

* — {nall other circumstances - AOP1’s desk in the Land Use Section.

Please DO NOT leave the application at the counter and DO NOT deliver the application to Records.

 

SEPI g:\antorms\upplication checklist.doc
Full text of the other 62 pages

Page 2

 

a DTS GROUP Qv-D PTY LTD
1ST FLOOR 6 HEUSSLER TCE
DTS MICtTON-Gitp—-4664——_—____—_
PO Box 361
wanes PAODINGTON QLD 4064

GROUP QLD
PHONE 31118 0600
FAX 3118 0699
[email protected]
DEVELOPMENT CONSULTANTS:

be TOWN PLANNING
Our Ref: A05255 Gurvermo & Daarrins WWW. DTSGROUPQLD.COM.AU
ENVIRONMENTAL MANAGEMENT ACN 010 000 843
5 February, 2008 Beene

Chief Executive Officer,
Noosa Council,

PO Box 141 Tewantin,
Queensland, Australia 4565

Attention: Development Assessment
Dear Sir / Madam,

\ @ RE: Code Assessable Development Application for Development Permit for
Material Change of Use (Establishing a new Detached House) and Preliminary
Approval for Building Work on land at 34 The Quarterdeck, Noosa Heads being
described as Lot 82 on RP88934

Client: Jovershire Pty Ltd

 

_. On. behalf of our client, we submit_the following in support of the above

application:
° Four (4) copies of the Development Assessment Report
. Four (4) copies of the Architectural Plans undertaken by Willis

Greenhalgh Architects
° Duly executed IDAS Forms (Parts A, D) and Referral Checklist.

A, cheque, for $650; 00" "being the application fee. Development Fee
Assessment Form attached.

 

We trust that this application will be given the utmost attention and
consideration

Should you require any further information, we would be pleased to assist.

Kind regards,

   

NICHOLA BAILEY
E [email protected]

 

DIRECTORS

JEFFREY M. BREWER CERT.INCART. MDIA, JP, MARK T. KIERPAL BBEUPP GOURP. MPIA.,
MaLcou J. THOMS Surv Assoc., ANTHONY J VALENTINE Lic Cad Surv MSSI,

Ltoyo J. LAING Lic Cad SURV FSSI., ANGUS WaRNICK SuRV. GRAD. MSSI. BSST (GIS).
Rooney 8S. JAMES Surv. Grav. MSSI.

ASSOCIATES

JANESH GUNARATNE SRTP., NICHOLAS Barley BRTP (HONS).MPIA, Paut SHELLARO SURV.ASSOC.

Page 3

INTEGRATED PLANNING ACT 1997

    
  

Common details

bp

Part A, Version 2.4, 29 May 2006

 

   

/ h

a a

P

 

The completion of all applicable questions on Part A is mandatory for all applications. Part A must be accompanied by the completed IDAS Assessment Checklist if
fequired, and by one (1) or more other completed parts of the Form as required. For more information on the parts of the Form refer to www.ipa.qid.gov.au,

Any information

luested in the form may be provided in an attachment to the application. For further information about completi

the following details, refer to Guide 1.

 

Description of land

All land the subject of the application, must be
identified. However, a description of the land is not
required in relation to a mobile or temporary
Environmentally Relevant Activity (ERA).

Advice for completing Q2 - Q2 applies if
development is proposed within a water body or
watecourse.

Advice for completing Q3 - Most land can be
identified by alot on plan description. These details

can be obtained from litle documents or through the~

local government.

However, if the land on which the development is

proposed does not have a lot on plan description

{i.e, the development is proposed in a water body or

watercourse) provide -

(i) the lot on plan description for the
adjoining/adjacent land; or

(ii) GPS coordinates where there is no
adjoining/adjacent land (eg. in Moreton Bay).

Advice for completing Q7 - Q7 does not applyif -

the development is within a water body or
watercourse,

mpletins - 08 applies if
development is within a local government area.
Note: Areas below high water mark are not within a
local government's area unless provided for under
the Local Government Act 1993.
Advice for completing Q9 - Q9 applies if
development is on strategic port land or a strategic
port tand tidal area. For more details refer to Guide
u

1. Street address: (ncludinghouse number, street name, suburb/ocality name & postcode) (if applicable)
34 The Quarterdeck, Noosa Heads

2. Name of water body or watercourse, within which the development is proposed: (if applicable)
NIA

3. _ Lot on plan description (eg. Lot 123 on RP 4567) / GPS coordinates:
Lot 82 on RP88934

4.. The above description is for: (tick applicable box)
EX] (i) the land on which the development is proposed; or
CO (ii) the land adjoining the water body or watercourse, within which the development is
proposed; or
LD (iii) the water body or watercourse,

5. Shop / tenancy number: 6. Storey / level: : 7. Total area of land: (m? or
NIA N/A ha):

8. Local government area in which the land is situated: (eg. Esk, Hervey Bay, Woocoo etc.) {if applicable)
Noosa Shire Council

9. Port authority for the strategic port land or strategic port land tidal area on which the
development is proposed: (eg. Port of Brisbane, Port of Townsville) (if applicable)
NIA

 

Proposal details

If there is insufficient room available, details may be
provided in an attachment to the application.

10. Existing use of the land: (eg. vacant, single house, shop etc.)
Detached Dwelling

11. Proposed use of the land: (eg. 6 unit apartment building, 30 lot residential subdivision, ERA for aquaculture in
ponds with a total area of 7 ha for which wastes are released into waters etc).

Remove and establish a new Detaced Dwelling

 

Other applicable parts of Form 1

Part A must aiways be accompanied by other
completed parts of Form 1. For information about
when a pari of Form 1 may apply refer to Guide 1.

12. Other parts of Form 1 completed as part of this application: (eg. Part D, Part /, etc)
Part D and Referral checklist

 

Applicant details

Clearly identify who is making the application, The
applicant need mot be the owner of the land.

When signing and lodging this application

The applicant is responsible for ensuring the
information provided is correct. The assessment
manager, any referrat agency & the Chief Executive
(where applicable) will rely on this information when
assessing and deciding the application.

Ifthe applicant Is a company - a contact person
must be shown,

 

13. Applicant's name:
Jovershire P/L C/- DTS Group QLD

15, Contact person:
Nicholas Bailey

14. Contact number:
3118 0600

16. Facsimile number/e-mail address:
3118 0699 / [email protected]

17. Postal address:
PO 361, PADDINGTON QLD 4064

Page 4

INTEGRATED PLANNING ACT 1997
Cand owner's consent (if appiicabiey — |

Section 3,2.1(3) of the IPA prescribes that an
application must contain, or be supported by, the
written consent of the land owner/s, if the
application involves:

(i) amaterial change of use;

(ii) reconfiguration of a lot;

(iii) work on land befow high-water mark & not
within 8 canal as defined under the Coastal
Protection and Management Act 1995;or

(iv) work on rail corridor land defined under the
Transport Infrastructure Act 1994,

Section 3.8. 1(2}(a) of the IPA provides that

landowner’s consent is not required for a mobile or

temporary ERA.

For more information refer to Guide 1

 

Part A, Version 2.4, 29 May 2006
| 20-—t and owner’s-consent-to-the-making-of this-application:

Name
Signature
Date

22.(.2008

h
(i) Joversire PIL as trustee

(il

 

(ii

(iv)

(v)

 

e@ Resource entitlement (if applicable}

Section 3.2.1(5) of the IPA requires evidence of
resource entitlement be given for applications that
involve a prescribed State resource.

Section 3.2.1(10}{a)(ii) of the IPA prescribes that an
application cannot be taken to be properly made.
without evidence of the resource entitlement.
Advice for completing Q21 & 22

Refer to schedule 10 of the integrated Planning
Regulation 1998 that prescribas the nature of
evidence required by the State in support of the
lodging of this development application,

 

21. Does this application invoive a State resource prescribed under a regulation (other than involving
quarry materia! on State coastal land under the Coastal Protection and Management Act 1995)?

BI NO - go to 24 (2 YES - go to q22

22. This application is accompanied by evidence: (tick applicable box)
C1 (i) of the allocation of, or entitlement to, the resource - attach evidence and go to Q23(vi)

C (ii) the chief executive of the department administering the resource is satisfied the

development is consistent with an allocation of, or entitlement to, the resource - go
to Q23

(7 (iii) the chief executive of the department administering the resource is satisfied the
development application may proceed in the absence of an allocation of, or

 

entitlement to, the resource - go to Q23

Page 5

INTEGRATED PLANNING ACT 1997 Part A, Version 2.4, 29 May 2006
Advice for completing Q23 __23._Evidence.of the.resource. entitlement:

 

eee gts nsec“ evdonce (i) Resource entitlement / authority details (vii) Official stamp of the department _

The official stamp of the Department of Natural administering the resource (if
Resources, Mines and Water is mandatory where applicable}

the application involves any water or riverina quarry a
material under the Water Act 2000, (ii) Name of delegated officer
Section 3.2.1(5A) allows the resource manager to
limit the time the evidence may be used. Q23 (vi)
must be completed if the evidence is time limited.

{iii) Position of delegated officer
(iv) Signature of delegated officer
(v) Date

(vi) Expiry date of evidence (if applicable)

 

 

Assessment triggers 24. Is the IDAS Assessment Checklist completed and attached to this application?

This checklist does not apply if the application . oo
requires the completion of Parts A pas of the {Yes (NO - the assessment manager may refuse to accept this application on the
Form only. It must be completed for all other grounds that the application has not been properly made
applications.

Plans / drawings / reports 25. Plans/drawings/reports accompanying this application:

An application should be accompanied by details to .

support the proposal & enable the assessment Plan/ Drawing ! Report Number

manager, referral agencies and any person viewing Tith

the application during public scrutiny or public e

nolification to understand the scope of the proposal Dat

and any potential impact. jate

oo vo {i)- Town Planning Assessment Report - DTS Group QLD.

(ii) Archtectural Plans - Willis Greenhalgh Architects

(ii

(iv)

 

 

PLEASE NOTE: The assessment manager may refuse to accept an application that, at the time of lodgement, fails to provide all applicable information required by
Part A and any other relevant part of Form 1

OFFICE USE ONLY (applicable to assessment manager's)

 

 

 

 

 

 

 

 

 

 

REFERENC
FEE DATE RECEIVING
5 6 SO recened > 2>-(0& | orricers NAMES P> wer NUMBERS ovfouss
Notification of Engagement of Private Certifier (Optional format) (/
To, Council. ! have been engaged as the private certifier for the building work referred {o in this application.
Date ofengagement| / / Accreditation Number. _— Name’, Signature:

 

 

 

Page 6

INTEGRATED PLANNING ACT 1997

Part D, Version 2.0, 4 October 2004

Form 1 Development Application

 

Material change of use

assessable against a local government’s planning scheme

_—
a
|

L

j.
ed

 

Completion of all applicable questions on Part D is mandatory for all applications involving assessment of a
material change of use (MCU) assessable against a local governments planning scheme.

 

Nature of the application

A development permit authorises
development to occur, while a preliminary
approval is a step in the approval process
and does not authorise development to
occur.

1. This application is for: (tick 1 or both if applicable)

C Preliminary approval for a material change of use of premises including conceptual

design for any associated works that require approval under the planning scheme (ie.
consideration of the proposal concept)

AND/OR

EX] Development permit for a material change of use of premises including conceptual
design for any associated works that require approval under the planning scheme.

 

The subject land

For the definition of "gross floor area” go to
the planning scheme against which the
application will be assessed.

Material change of use details

2. How the subject land is identified in the planning scheme (name the zone, precinct etc.)
Noosa Heads Locality - Detached House Zone

3. Existing gross floor area: (i'applicebie) "2

4. Are there any existing easements on the land?

KINO

~_ [1 YES~- attach plans of tha location and details of the purpose of the easement

5. Details of the change to the use of the land: (eg. vacant land to shopping centre, house to apartment
building, vacant land to industry (tyre manufacturing) etc.)

Removal of Existing Dwelling and replacement with new detached house

 

6. Numberofemployees: 4
7. Operating days and hours: na
Associated building works details (if i 40%
applicable) 8. Site cover:
For the definition of “site cover’, "gross floor
area” and “storey” go to the planning 9. Gross floor refer to plans

scheme against which the application will
be assessed,

area:

 

40. Number of on-site car parking spaces:
14. Number of storeys / maximum height above natural 2 and 3
ground:
12. Number of employees a
13. Hours and days the use will operate na
Associated operational works 14. Details of associated operational works (eg. landscaping, cut and fill, drainage, road works etc.)
details (if applicable) nla

 

 

PLEASE NOTE

This application cannot be accepted unless accompanied by Part A of Form 1.
The assessment manager may refuse to accept an application that, at the time of lodgement, fails to provide all applicable information

requested by Part A and any other relevant part of Form 1.

 

OFFICE USE ONLY (applicable to assessment manager}

Page 7

INTEGRATED PLANNING ACT 1997 . IDAS Assessment Checklist, Version 20, 2 April 2007

Form 1 Development Application

IDAS Assessment
Checklist

(Formerly the “Referrals Checklist”)

      

IMPORTANT NOTE FOR ALL APPLICANTS:

1. This checklist was formerty referred to as the "Referrals Checklist’, Some of the ‘Guides’ to using the IDAS Application Forms continue to refer to this document as the
“Referrals Checklist’, The name of this checklist was changed from 25 July 2005 to more accurately describe its function.

2, Under the !PA and {DAS framework, an application may require assessment by the local Council and/or certain Queenstand State entities (e.g. Environmental
Protection Agency, Dept. of Natural Resources and Water, Queensland Heritage Council etc.).

3. This checklist is provided to assist applicants to determine when an application requires assessment by a Queensland State entity and may also assist the applicant to
determine the assessment manager’ for the application.

4, Therefore, the completion of all questions in section 1 of this checklist is mandatory for all applications (other than those requiring the completion of Parts A & B
only).

5. _ Itis the responsibility of the applicant to accurately complete this checklist.
@ Section 2 is mandatory only if the proposed development is located in any part of a wild river area declared under the Wild Rivers Act 2005.
Depending on the nature of the application, an applicable State entity may be either the assessment manager or an IDAS referral agency for the application.

8, The assessment manager for the application will rely on the information provided in this checklist (as well as any material lodged in support of the application) to
identify any applicable referral agencies for the application in the Acknowledgement Notice. The assessment manager will also rely on this information when identifying
if the application triggers referral coordination?,

9.  Toassist you in answering the following questions a series of guides are available free from the IPA website www.ipa.qid.gov.au. Guide 25 explains the role of the
IDAS Assessment Checklist in the IDAS application process, and its relationship to the Form 1 development application.

10, Any other parts of Form 1 that this checklist requires to be completed are available from the Council or the applicable State entity, or can be downloaded free from
www ipa.qid.gov.au,

11.- Section 3 provides advice about the referrals that can be required for applications for building work assessable against thie Building Regulation 2006.

 

eS .SECTION.1 - STATE ASSESSMENT (completion, mandatory) +”

  

 

 

 

 

Note:. The following state assessment triggers apply 0 development other than for building work assessable against the Building Regulation 2006,

Environmentally relevant activity 1. The application involves: (tick applicable box/es)

For more information refer to Guide 4. (1 (i) an environmentally relevant activity (ERA) for which a code for environmental

Untess you answered "none of the above” to compliance has not been made - complete Part G of Form 1

Q1, the application requires assessment by _ . — . . .

the administering authority’. C1 (ii) a mobile or temporary ERA for which a code of environmental compliance has not
@ Ifan entity, other than the administering been made - complete Part G of Form 1

authority, is the assessment manager for the
apptication, the administering authority is a
concurrence agency for the application in
relation to this matter.

| (iii) none of the above

Note: An application involving ERA 19 andor
20 will also require completion of Part Kr of
Form 1 for approval where an allocation under
the Water Act 2000 is required.

 

Continued overeat

 

PLEASE NOTE: The assessment manager may refuse to accept an application, which, at the time of lodgement, fails to provide the
completed IDAS Assessment Checklist (if applicable),

OFFICE USE ONLY (applicable fo assessment manager)
DATE RECEIVED REFERENCE NUMBER/S

 

1 The assessment manager is responsible for assessing and deciding an IDAS application. The assessment manager for an application is prescribed in schedule 8A of the IPA.
2. For additional information refer to Guide 6 ‘Does my application trigger the referral coordination process?”

3° The ‘administering authority’ may de either the Environmental Protectian Agency, the relevant local government (for a devolved ERA) or the Queensland Department of Primary Industries and
Fisheries (for a delegated ERA).

Page 1

Page 8

INTEGRATED PLANNING ACT 1997

State-controlled road_matters.
For more information refer to Guide 3.
Unless you answered “none of the above” to
Q2, the application triggers referral to the
Department of Main Roads (DMR) as a
referral agency.

In certain circumstances DMR will be an
advice agency, while in other circumstances
DMR will be a concurrence agency.

Schedule 2 of the IP Requtation will assist you
to determine where DMR is an advice or
concurrence agency for the application.

 

IDAS Assessment Checklist, Version 20, 2 April 2007
.2.__The. application. involves: (tick applicable.bowes).

 

(1) (i) development on land contiguous to a State controlled road and for -
CC (a) materia! change of use assessable against the planning scheme;
([) (b) reconfiguring a fot unless -
« the total number of lots is not increased; and
e the total number of lots abutting the State-controlled road is not increased;
C1 (¢) operational work (not associated with a material change of use assessable against
the planning scheme or reconfiguring a lot mentioned in (b) above)
« associated with access to a State-controlled road; or
¢ for filling or excavation; or

« involving the redirection or intensification of site stormwater from the land, through
a pipe with a cross-sectional area greater than 625 cm? that directs stormwater to
a State-controlled road.

LJ (ii) development on land not contiguous to a State-controlled road and -

O(a) material change of use —
* assessable against the local government's planning scheme; and
« mentioned in schedule 5 of the IP Regulation and exceeding the thresholds set by
that schedule;
CO (b) reconfiguring a lot for a purpose mentioned in schedule 5 of the IP regulation
and exceeding the thresholds set by that schedule;
(1c) operational work (not associated with a material change of use assessable against
the planning scheme or reconfiguring a lot mentioned in (b) above)
« assessable against the local government's planning scheme; and
« mentioned in schedule 5 of the IP Regulation and exceeding the thresholds set by
that schedule.

Bd] (ii) none of the above

 

Clearing vegetation
For more information refer to Guide 12. -

Unless you answered “none of the above” to
Q3, the application requires assessment by
the Department of Natural Resources and
Water (NRW).

If an agency other than NRW is the
assessment manager for the application, NRW
ts a concurrence agency for the application in
felation to this matter.

If you ticked Q3(i) or (ii), your application
requires referral to NRW for assessment
tegardless of whether vegetation clearing is
proposed or nat.

3. The application involves: (tick applicable box/es}
(i) material change of use -
(a) assessable against the planning scheme;

(b) on a lot containing ~
« acategory 1, 2 or 3 area shown on a property map of assessable vegetation; or

« if there is no property map of assessable vegetation for the lot - remnant
vegetation;

(c) where the existing use of the land is a rural or environmental use; and
(d) where the size of the land is 2 hectares or larger - complete Part J of Form 4
reconfiguring a lot -

(a) ona lot containing a category 1, 2 or 3 area shown on a property map of

assessable vegetation or, if there is no property map of assessable vegetation for
the lot, remnant vegetation;

where the size of the lot before the reconfiguration is 2 hectares or larger;

(c) where 2 or more lots are created; and

(d) where the size of any lot created is 25 hectares or smaller - complete Part J of Form 1
CI (iii) operational work -

(a) for the clearing of native vegetation where the vegetation clearing is made
assessable under Schedule 8 of the IPA; and

(b} not associated with a material change of use assessable against the planning
scheme mentioned in (i) or reconfiguring a lot mentioned in (ii) - complete Part J of
Form 1

Ed (iv) none of the above.

Diii)

(b)

 

 

4 Land contiguous to a State-controlled road is dafined in schedule 14 of the IP Regutation to mean land - if part of the land is within 100m of the State-controlled road; or that is part of a future State-

controlled road.

Page 2

Page 9

INTEGRATED PLANNING ACT 1997
Strategic port land
For more information refer to Guide 11.

\fyou ticked (i) - the relevant Port Authority is
the assessment manager for the application.

if you ticked (ii) Queensland Transport is a
concurrence agency for the application.

4___ The. applicationinvoives:

IDAS Assessment Checklist, Version 20, 2 April 2007

(J (i) development on strategic port land as defined in the Transport Infrastructure Act 1994
(TI Act) - complete Part I of Form 1

C1 (ii) a material change of use that is inconsistent with the land use plan approved under
the TI Act for the strategic port land - complete Part ! of Form 1

Ex] (iii) none of the above

 

Acid sulfate soils
For more information refer to Guide 10,

Unless you answered “none of the above" to
Q5, the application requires assessment by
Department of Natural Resources and Water
(NRW).

(fan agency other than NRW is the
assessment manager for the application, NRW
is an advice agency for the application in
felation to this matter.

 

5.

The application involves development on land situated in an identified local government area
and where the surface of the land is: (tick applicable box)

C1 (i) below 20m AHD® and the development will involve the excavation of 1000m3or more of
soil or sediment at or below 5m AHD, or

1 (ii) at or below 5m AHD and the development will involve filling the site with 1000m? or
more of material

XX (iii) none of the above

 

Major hazard facilities or possible
major hazard facilities
For more information refer to Guide 17.

Ifyou answered "YES” to Q6, the application
requires assessment by the Department of
Emergency Services (DES).

If an agency other than DES is the
assessment manager for the application, DES
is a concurrence agency for the application in
telation to this matter.

Water related development under
the Water Act 2000

For more information about items (a) - (,
refer to Guide 15. For more information about
item (g), sefer to Guide 14 Does my
application involve assessment of a referable
dam?
Untess you answered “none of the above" to
--Q7, the application requires assessment by
the Department of Natural Resources and
Water (NRW).
If an agency other than NRW is the
assessment manager for the application, NRW
is a concurrence agency for the application in
relation to this matter.

 

Removal of quarry material from a
watercourse
For more information refer to Guide 16.

If you answered "YES" to Q8, the application
requires assessment by the Department of
Natural Resources and Water (NRW).

If an agency other than NRW is the
assessment manager for the application, NRW
is a concurrence agency for the application in
relation to this matter,

Note: Part G of Form 1 is required to be
completed as the activity of removing quarry
material from a watercourse is also an
Environmentally Relevant Activity (ERA).

7.

 

Does the application involve a material change of use for a major hazard facility or possible
major hazard facility as defined under the Dangerous Goods Safety Management Act 2001?

EX] NO

(C1 YES - complete Part L of Form 1

The application involves:

(1 (i) operational work, for taking or interfering with water under the Water Act 2000, that is:
(tick applicable box/es)

CJ (a) in a watercourse, lake or spring, (eg. a pump, gravity diversion, stream re-direction, weir or
dam) - complete Part Ka, Ks, Ks, Ke, or Ky of Form 1 whichever is applicable;

CO (b) for an artesian bore anywhere in the State, no matter what the use - complete Part
Ks of Form 1; sos . 7

LJ (c) for a subartesian bore, in declared subartesian area’, or in a certain area
covered by a water resource plan, for use for purposes other than stock and/or
domestic use - complete Part K; of Form 1;

( (¢) for a subartesian bore, in certain declared subartesian areas, for use for stock
and/or domestic purposes - complete Part Ki of Form 1;

CD (e) for taking overtand flow water in certain areas covered by a water resource
plan - complete Part Ks of Form 1;

(2 (f) for interfering with overland flow water in a drainage and embankment area -
complete Part Kioof Form 1

(1) g) for constructing a referable dam? or works that will increase the storage
capacity of a referable dam by more than 10% - complete Part Ks of Form 1; of

[X] (ii) none of the above.

Does the application involve development for the removal of quarry material from a
watercourse? requiring an allocation notice under the Water Act 2000?

NO
LI YES - complete Parts Kr and G of Form 1

5. The identified local government areas are: Aurukun, Bowen, Brisbane, 8readsound, Sundaberg, Burdekin, Burke, Burnett, Caboolture, Caims, Calliope, Caloundra, Cardwell, Carpentaria, Cook,
Coatoola, Dounglas, Fitzroy, Gladstone, Gold Coast, Hervey Bay, Hinchinbrooke, Isis, Johnstone, Livingstone, Logan, Mackay, Maroochy, Maryborough, Mirium Vale, Mornington, Noosa, Pine Rivers,
Redcliffe, Redland, Rockhampton, Sarina, Thuringowa, Tiaro, Torres, Townsville, Whitsunday.

6 Australian Height Datum (AHD).

7 The declared ground water areas are listed in Guide 13 Development in a declared catchment area.

8 Referable dam is defined under the Water Act 2000.

9 Watercourse fs defined in sch 10 of the IPA.

Page 3

Page 10

INTEGRATED PLANNING ACT 1997
Operational work that is tidal work
or work in coastal management
district
For more information refer to Guide 18. For
more information about prescribed tidal work
in local government tidal areas refer to Guide
24.

Unless you answered "none of the above” to
QS, the application requires assessment by
the Environmental Protection Agency (EPA).
If an agency other than EPA is the
assessment manager for the application, EPA
is a concurrence agency for the application in
elation to this matter.

Local gavernment is the assessment manager
for all prescribed tidal work.

IDAS Assessment Checklist, Version 20, 2 April 2007
9,__The_application involves. operational work that is: (.tick. the applicable box/es).

(1 (i) _ tidal work"? as defined under the Coastal Protection and Management Act 1995 (the
Coastal Act) that is not prescribed tidal work - complete Part M of Form 1; oF

C1 (ii) tidal work that is prescribed tidal work" other than in a canal’? -complete Part P of Form 1:
or

D1 (ii) carried out within a coastal management district under the Coastal Act and for -
complete Part M of Form 1 if any box/es (a) to (i) below are ticked.

(a) constructing or installing works in a watercourse between MHWS and HAT (ie.
other than those works in tidal water) where the development has been determined
Not fo be assessable against the Water Act 2000 ;

{J (b) constructing a canal12 intended to be connected to tidal waters;

(C1 (c)_ constructing an artificial waterway;

(0 (d)_ reclaiming land under tidal water;

Le) disposing of dredge spoil or other solid waste material in tidal water;

CO (interfering with quarry material on State coastal land above high-water mark;

(1 (g) draining or allowing drainage or flow of water or other matter across State
coastal land above high-water mark;

[1 (h)_ removing or interfering with coastal dunes on land, other than State coastal
land, that is in an erosion prone area and above high-water mark;

(i) constructing a bank or bund wall to establish a ponded pasture on land, other
than State coastal land, above high-water mark; or

& (iv) none of the above.

 

 

Operational work below high water
mark

For more information refer to Guide 18. For
more information about prescribed tidal work
in local goverment tidal areas refer to Guide
24,

Unless you answered “none of the above” to
Q10, the application triggers referral to
Queensland Transport ‘Maritime Safe!
Qld} as a concurrence agency.

Local government is the assessment manager
for all prescribed tidal work.

10. The application involves operational work that is: ( tick the applicable box/es)

[1 (i) tidal work’ as defined under the Coastal Protection and Management Act 1995 (the
Coastal Act) that is not prescribed tidal work — complete Part M of Form 1; or

0 (ii) tidal work that is prescribed tidal work’ - complete Part P of Form 1; of
OD (ii) carried out within a coastal management district’ under the Coastal Act and for -

(a) disposing of dredge spoil or other solid waste material in tidal water - complete
Part M of Form 1;

[J (b) reclaiming land under tidal water - complete Part M of Form 1; oF

CJ (6) constructing a canal12, if the canal is associated with reconfiguring a lot -
complete Part M of Form 1;

XI (iv) none of the above.

 

Coastal management
For more information refer to Guide 18.

Unless you answered “none of the above” to
Q11, the application requires assessment by
the Environmental Protection Agency (EPA).
if an agency other than EPA is the
assessment manager for the application, EPA
is a concurrence agency for the application in
relation to this matter.

 

11. The application involves: (tick the applicable box/es)

CI (i) a material change of use assessable under a planning scheme involving
operational work carried out completely or partly in a coastal management district's

Di (i) a material change of use assessable under a planning scheme involving building
work, carried out completely or partly in a coastal management district that is -
« the construction of a new premises with a GFA" of at least 1000m?
« the enlargement of the GFA of existing premises by more than 1000m2

C1 (ii) recenfiguring a lot assessable under schedule 8 of the IPA where the land is
situated completely or partly in a coastal management district

(i) recenfiguring a lot"? assessable under schedule 8 of the IPA and in connection with
the construction of a canal12 - complete Part M of Form 1

Kl (v)__ none of the above

 

10 Tidal work is defined in sch 10 of the IPA.

11 Prescribed tidal work is defined in the Coastaf Protection and Management Regulation 2003 and includes certain tidal works comptetely or partly within a local government tidal area.
12 Canal means canal as defined under the Coastal Protection and Management Act 1995

43 Tidal work is defined in sch 10 of the IPA.

144 Prescribed tidal work is defined in the Coastal Protection and Management Regulation 2003 and inctudes certain tidal works completely or partly within a local government tidal area,

15 Coastal management district is defined in sch 10 of the IPA and means a coastal management district under the Coastal Protection and Management Act 1995, other than an area declared as a
coastal management district under section 47(2) of that Act.

16 GFA is defined in sch 14 of the IPA to mean the gross floor area. For 2 definition of how to calculated GFA, go to the planning scheme against which the application is being assessed.

17 Under 3117 of the Coasta! Protection and Management Act 1995, an application for reconfiguration, where the reconfiguration is associated with the construction of an artificial waterway, must be
accompanied by the application for the operational works to construct the artificial waterway.

Page 4

Page 11

_
____————For more information refer to Guide 18. For

advice agency.

INTEGRATED PLANNING ACT 1997
Development within the limits of a
port

 

information about prescribed tda! work refer to

Guide 24.

\f you answered “YES” to Q12, the application

Uiggers referral to the Port Authority.

The Port Authority is a concurrence agency if

the development is ~

* within 200m of a shipping channel or an
entry and exit shipping corridor for the port

© within 1000m of a swing basin, a
commercial shipping wharf, a mooring,
anchorage or spoil grounds;

¢ within 1000m of a planned port facility
identified in a land use plan approved
under the Transport infrastructure Act
1994.

In all other situation the Port Authority is an

Marinas

For more information refer to Guide 18. For
information about whether a marina is
prescribed tidal work refer te Guide 24. The
local government is the assessment manager
for alt prescribed tidal work.

If you answered "YES" to Q13, the appilcation

triggers referral to Queensland Fire and
Rescue Service as an advice agency.

 

IDAS Assessment Checklist, Version 20, 2 April 2007___——

142. Does the application involve development below. high-water-mark’® and within the limits of a
|____ port under-the-Transport Infrastructure Act 1994?

ENO

(71 YES - complete Part M of Form 1, or Part P of Form 1 if the work is prescribed tidal work

13. Does the application involve operational work that is tidal work for a marina’? with more than 6
vessel berths?

INO

(7 YES - complete Part M of Form 1, or Part P of Form 1 if the tidal work is prescribed tidal work

 

 

Tidal works in strategic port land
tidal areas
For more information refer to Guide 18.
Unless you answered “NO" to Q14, the
relevant Port Authority is the assessment
manager for the application and the
Environmentat Protection Agency (EPA) and
Queensland Transport (QT) are concurrence
agencies for the application.
Heritage

* Foy furthér information refer to Guide 19.
Ifyou answered “YES" to Q15, the application

triggers referral to the Queenstand Heritage
Council as concurrence agency for the
application,

Unless you answered “none of the above” to
Q15(b), the application involves referral to the

Environmental Protection Agency as an advice
agency for the application

OW

Oi
iii

14. Does the application involve tidal works within a strategic port land tidal area2°?
NO
(YES - complete Part M of Form 1

15. Does the application involve development in a heritage registered place as defined under the
Queensland Heritage Act 1992?

JNO

(11 YES - complete Part C of Form 1

15(b)The application involves: {tick applicable boxes)

a material change of use assessable against the planning scheme and the lot shares
acommon boundary with a protected area or registered place under the Queensland
Heritage Act 1992;

reconfiguring a lot if the lot shares a common boundary with a protected area or
registered place under the Queensland Heritage Act 1992;

none of the above.

 

 

Declared catchment areas

For more information, including a list of the
declared catchment areas within Queenstand,
fefer to Guide 13.

Unless you answered “none of the above” to
Q16, the application requires assessment by
the Department of Natural Resources and
Water (NRW).

if an agency other than NRW is the
assessment manager for the application, NRW
is a concurrence agency for the application in
felation to this matter.

Ot
OW

 

 

16. The application is in an area declared to be a catchment area under the Water Act 2000 and
involves: (tick the applicable box/es)

reconfiguring a lot if any lot resulting from the reconfiguration is less than 16
hectares;

development assessable against the planning scheme involving the establishment or
expansion of a waste water disposal system, other than a disposal system for carrying
out an environmentally relevant activity under the Environmental Protection Act 1994,

(iii) none of the above

18 High water mark is defined in the Coastal Protection and Management Act 1995 and means the ordinary high water mark at spring tide.
19 Marina is defined in the Transport Operations (Maritime Pollution) Regulation 1995.
20 Strategic port land tida! areas are the areas generally 50 metres seaward of high water mark adjacent to strategic port land,

Page 5

Page 12

INTEGRATED PLANNING ACT 1997
Contaminated land.

Appiications involving matesial change of use
and/ or reconfiguring a tot may trigger this
referral.

For more information refer to Guide 5.

Unless you answered “none of the above” to
Q17, the application requires assessment by
the Environmental Protection Agency (EPA). If
an agency other than EPA is the assessment
manager for the application, EPA will be a
concurrence agency for the application in
relation to this matter.

 

Electricity infrastructure

For more information refer to schedule 2of the
IP Requlation.

Unless you answered “none of the above” to
Q18, the application triggers referral to the
agency to which the easement is granted in

@ favour of as advice agency.

18,

IDAS Assessment Checklist, Version.20,.2 April. 2002

47-—The-applicationrinvolves: (tick the applicable boxes)

Oi) reconfiguring a fot for which all of part of the premises are -
(a) premises mentioned in the IPA, schedule 8, part 1, table 2—
« item 5, including the exemption otherwise provided for by paragraph (d);
« item 6, including the exemption otherwise provided for by paragraph (e); or
« item 7, including the exemption otherwise provided for a mining activity or petroleum
activity; or
(b) in an area for which an area management advice has been given for unexploded
ordnance - complete Part N of Form 1
C1 (ii) a material change of use ~
(a) made assessable under the IPA, schedule 8, part 1, table 2, items 5 to 7; or
(b) assessable against the planning scheme and if all or part of the premises is in an area
for which an area management advice has been given for unexploded ordnance -
complete Part N of Form 1
EX] (ii) none of the above
The application involves: (tick the applicable box/es)

Ci) reconfiguring a lot where any part of the lot is -

subject to an easement in favour of a distribution entity or transmission entity under the
Electricity Act 1994 and the easement is for a transmission grid or supply network under
that Act; or

« situated within 100m of a substation site;

a material change of use, assessable against a planning scheme and not associated

with reconfiguring a lot if -

« any part of the premises is subject to an easement in favour of a distribution entity or
transmission entity under the Electricity Act 1994 and the easement is for a transmission
grid or supply network under that Act; and

any structure or work that is the natural and ordinary consequence of the use is, or will
be, located wholly or partly i in the easement;

CO (ili) a material change of use, assessable against a planning scheme and not associated
with reconfiguring a lot if any part of the premises is situated within 100m of a
substation site;

C1 (iv) operational work that is filling or excavation assessable against the planning scheme,
not associated with reconfiguring a lot, if -

any part of the premises is subject to an easement in favour of a distribution entity or
transmission entity under the Electricity Act 1994 and the work is located wholly or partly
in the easement;

the work is located wholly or partly within 10m of a substation site;
X] (v)_ none of the above.

Oi

 

 

@ Land designated for community

infrastructure

Applications involving development on land
designated for community infrastructure may
trigger this referral.

For more information refer to schedule 2 of the
IP Regulation,

lf you answered "YES" to Q19, the application
fequires assessment by the chief executive of
the department administering the Act
authorising the development for the
designated purpose.

tf an agency other than the designator Is the
assessment manager for the application, the
designating agency will be a concurrence
agency for the application in relation to this
matter.

 

19,

Does the application involve development assessable against the planning scheme and on land
designated for community infrastructure?

(i) intended to be supplied by a public sector entity; and
(ii) on land not owned by or on behalf of the State; and
{iii), other than development -

(a) for the designated purpose; or

{b) carried out by, or on behalf of, the designator.
&) No
LJ YES

Page 6

Page 13

INTEGRATED PLANNING ACT 1997
SEQ Regional.Plan.
For more information refer to schedute 2 of the
IP Regulation.

Refer to Chapter 2, part 5A and schedute 10

of the Integrated Planning Act 1997, and
schedule 2 of the Regulatory Provisions for
relevant definitions.

Unless you answered “none of the above” to
Q20, the application requires assessment by
the Office of Urban Management (OUM).

 

IDAS Assessment Checklist, Version 20,.2 April.2007
|-20-—Fhe-application involves (tick applicable boxes) -
CO s(i) amaterial change of use of premises ~

(a) in a Major Development Area in the Urban Footprint for -

CO (i) anurban activity -

C1 sinan area included in a structure plan where the IPA, section 3.1.6
applies;
Cs inan area not included in a structure plan where -

« the IPA, section 3.1.6 applies to the application for the material
change of use; or

« the premises exceeds 10,000m2; or
« the gross floor area (GFA) on the premises will exceed 10,000m2; or
« impact assessment is required under the relevant planning scheme

CJ (i) intensive animal husbandry, or
CO (il) residential development involving a rural residential purpose

{b) in the Regional Landscape and Rural Production Area for -
C1 (i) an urban activity and not specified in section 2.4(2); or
( (ii) residential development involving a rural residential purpose and not
specified in section 2.6(2)

(c) in the Rural Living Area for an urban activity and not specified in section
2.8(2);
(d) in the Investigation Area for -
CD (i) an urban activity and not specified in section 2.10(2);

C1 (ii) residential development involving a rural residential purpose and not
specified in section 2.12(2); or

C ii), intensive animal husbandry. - “ : -
C1 (ii) reconfiguring a lot-
On land in a Major Development Area in the Urban Footprint that is:
(a) not included in a structure plan; and
(b} not specified in section 3.1(2).

EX __{iii) none of the above

 

Fisheries matters

For more information refer to schedule 2of the
IP Regulation.
Unless you answered “none of the above" to
Q21, the application requires assessment by
the Department of Primary Industries and
Fisheries (DPI&F).
If an agency other than DPI&F is the
assessment manager for the application,
DPI&F is a concurrence agency for the
application in relation to items (i) - (Iv) and an
advice agency in relation to item (v).

21. The application involves: (tick the applicable boxes)
LC (i) an assessable material change of use for aquaculture - complete Part Or of Form 1;

UD (ii) assessable operational work that is the construction or raising of a waterway barrier -
complete Part O3 of Form 1,

Oi (il) assessable operational work completely or partly within a declared fish habitat area-
complete Part O2 of Form 1;

(J (iv) assessable operational work that is the removal, destruction or damage of a marine
plant - complete Part Oz of Form 1;

LJ (v) development assessable under the IPA, schedule 8, part 1, on land that adjoins a
declared fish habitat area;

 

Bd (vi) none of the above.

Page?

Page 14

INTEGRATED PLANNING ACT 1997
{Integration of Jand_use.and.public_—.
transport
For more information refer to Guide 23,
schedule 8A of the IPA, & schedule 2 of the IP.
Requtation.

Unless you answered “none of the abave”, the
application triggers referral to QT asa
concurrence agency.

IDAS Assessment Checklist, Version 20, 2 April 2007.
-22.—Fhe-application-involves:-(tick te applicable box/es)—

LO (i) a material change of use assessable against the planning scheme for a purpose
mentioned in schedule 13C of the IP Regulation and exceeding the thresholds set by

that schedule.
C1 (i) reconfiguring a lot—

(1 (2) _ on land that is completely or partly within a public transport corridor, and the
total number of lots increases;

LJ (b) _ on land that is completely or partly within a future public transport corridor or
an airport's public safety area;

C1 (c) _ on land that is within 400m of a public passenger transport facility or a future
public passenger transport facility, and the total site area is 5000m2 or
greater;

LJ (d) for a residential purpose within the 25 ANEF contour for an airport;

LJ (e) for a residential purpose resulting in 100 or more allotments.

LD (ii) operational work assessable against the planning scheme, but not associated with a
material change of use mentioned in (i) above or reconfiguring a lot mentioned in (ii)
above, on land that—

La) _ is completely or partly within a public transport corridor or a future public
transport corridor;
[1 (b) _ will result in work that encroaches into an airport's operational airspace.

Dd (iv) none of the above.

 

 

Railway safety and efficiency

For more information refer to Guide 23,
schedule 8A of the IPA & schedule 2 of the IP
Requiation.

Unless you answered ‘none of the above’, the
application triggers referral to QT as a
concurrence agency.

 

Moonie to Brisbane pipeline

For more information refer to schedule 2of the
IP Regulation.

Unless you answered “none of the above", the
application triggers referral to the holder of
pipeline licence No 1 issued under the
Petroleum Act 1923, currently Santos QNT Pty
Ltd, for advice.

23. The application involves: (tick the applicable box/es)—

CJ (i) a material change of use assessable against the planning scheme for a purpose
mentioned in schedule 13D of the IP Regulation and exceeding the thresholds set by
that schedule.

C1 (ii) reconfiguring a lot—

(1 (a) ontand that is completely or partly within a future public transport corridor,
future railway land or a railway tunnel easement;

(J (b) on land that is within 400m of a Citytrain passenger railway station or a
future Citytrain passenger railway station, and the total site area is 5000m?2
or greater;

CJ (c) _ on land that abuts rail corridor land, commercial corridor tand or future
railway land, and the total number of lots increases;

C1 (4) _ on land that abuts rail corridor land, commercial corridor tand or future
railway land and an easement abutting the corridor or future railway land is
created;

[J (e) on tand that is completely or partly within 100m of, and abutting an approach
to, a railway level crossing, and the total number of lots increases;

CJ (f) for a residential purpose resulting in 100 or more allotments.

( (ii) operational work assessable against the planning scheme, but not associated with a
material change of use mentioned in (i) above or reconfiguring a lot mentioned in (ii)
above, involving extracting, excavating or filling greater than 50m, on land that—

(1 (a) _ is completely or partly within rail corridor land or commercial corridor land,
and the work is not for rail transport infrastructure or other rail infrastructure;

(1 (b) _ is completely or partly within future railway land, or a railway tunnel
easement;

(1 (c) — abuts rail corridor tand, commercial corridor land or future railway land, and

the work is within 25m of the railway boundary.

LX] (iv) none of the above.

The application involves the easement for the construction or operation of the Moonie to

Brisbane strategic pipeline, and involves: (tick the applicable box/es)—

C (i) a material change of use assessable against the planning scheme and not associated
with reconfiguring a lot, and any structure or work will be located wholly or partly in the
easement.

Cl (ii) reconfiguring a lot

CO (iii) operational work assessable against the planning scheme, that is filling, excavation,
compaction, drilling, boring or piling not associated with a reconfiguring a lot, and the
work is located wholly or partly in the easement.

(iv) none of the above.

24.

 

 

Page 8

Page 15

INTEGRATED PLANNING ACT 1997
Koala habitat.area
For more information, refer to Guide 26 and
schedule 2 of the IP Requiation.

Unless you answered “none of the above”, the
application requires referral to the

Environmental Protection Agency as a
concurrence agency.

 

IDAS Assessment Checklist, Version 20,.2 April 2007.
|-25:—The application involves~ (tick the applicable bowes)—

C1 (i) a material change of use of premises in a koala conservation area or koala
sustainability area made assessable under a planning scheme, thatis not for a
domestic activity and will result in -
an Height DatumQAHD).

(J (b) anew building and any reasonably associated structure with a total footprint
greater than 1000m?;

(J (©) anextension to an existing building and any reasonably associated structure if
the extension has a total footprint greater than 1000m2;

(1d) extracting gravel, rock or sand from an area greater than 5000m?;

Ce) excavating or filling an area greater than 5000m?;

(1 (f) additional traffic in a koala conservation area or koala sustainability area,
between 6p.m. on a day and 6a.m. on the following day.

C1 (ii) reconfiguring a fot in a koala conservation area or koala sustainability area that will
result in -

(1 {a)_ an increased number of lots;
( (b) clearing of native vegetation over an area greater than 2500m?,

O (iii) operational work in a koala conservation area or koala sustainability area made
assessable under Schedule 8, Part 1, Table 4, items 1A to 1G (not associated with
reconfiguring a lot mentioned in (ii) above) that will result in the clearing of native
vegetation over an area greater than 2500m2.

C1 (iv) operational work in a koala conservation area or koala sustainability area made
assessable under a planning scheme {not associated with a material change of use
mentioned in (i) or reconfiguring a lot mentioned in (ii) above) that is not for a domestic
activity and will result in -

(1 (a) clearing of native vegetation over an area greater than 2500m?;
(1 (b) extracting gravel, rock or sand from an area greater than 5000m2;
C1 (c) excavating or filling an area greater than 5000m2.

 

 

OX] (v) none of the above.
Wild river area 26. Does the application involve development in a wild river area declared under the Wild Rivers
For more information, refer to Guide 27 Act 2005?
Ifyou answered YES to Q26, you must also ® NO
complete section 2 of this checklist. This will
enable you to determine if your application can Oyes

proceed in a wild river area and which referral
agency will assess your application against
the Wild Rivers Code, or if the proposed
development is “prohibited” in a wild river
area.

Note: Development can be ‘prohibited’ in a
wild river area because the application cannot
be accepted by the assessment manager.

 

Pretiminary Approval
If you answered YES to Q27, the application
triggers referral to the Department of Local

Goverment, Planning, Sport and Recreation
as an advice agency.

27. Does the application involve a development for which preliminary approval is sought under
Section 3.1.6 of the Integrated Planning Act 1997?

No
Yes

 

Wetlands

Domestic activity means the construction or
use of a single residence on a lot and any
reasonably associated building or structure.
Examples of a building or structure that could
be reasonably associated with a single
residence inctude: caretaker's residence,
granny flat, building or structure used for a
home business,

Note: Welland is defined in the Integrated
Planning Regulation 1998.

Unless you answered “none of the above" to
Q28, the application involves referral to the

Environmental Protection Agency as an advice
agency for the application.

28. -The application involves: (tick the applicable boxes) -

C1(i) — amaterial change of use, other than for a domestic activity, assessable against the
planning scheme that is in or within 100m of a wetland;
C1 (ii) reconfiguring a lot -

In or within 100m of a wetland that will result in
(1 (a) more than 10 lots being created; or
CJ (6) lots less than 5 hectares;

KX (ii) none of the above

 

Page 9

 

Page 16

INTEGRATED PLANNING ACT 1997
Conservation-_Estate

Urban purposes is defined in the Integrated
Planning Act 1997 as “purposes for which land
is used in cities or towns, including residential,
industrial, sporting, recreation and commerciat
purposes, but not including environmental,
conservation, rural, natural or wildemess area
purposes”.

Untess you answered “none of the above” to
Q29, the application involves referral to the

Environmental Protection Agency as an advice
agency for the application.

IDAS Assessment Checklist, Version, 20,.2 April.2007-
29-—-Fhe-application involves: (lick the applicable box/es)—
CO (i) a material change of use for urban purposes that is in or within 100m of any of the
following -
C1 (a) aprotected area, forest reserve, critical habitat or area of major interest under
the Nature Conservation Act 1992;;

LJ (b) a State forest or timber reserve under the Forestry Act 1959;
LJ (6) amarine park under the Marine Parks Act 2004;
(1d) a recreation area under the Recreation Area Management Act 1988;
(1 (e) a world heritage area listed under the World Heritage Convention;
(1() Brisbane forest park under the Brisbane Forest Park Act 1977.
C1 (ii) reconfiguring a lot if -
C1 (a) any part of the lot is situated in, or within 100m of, any of the following —

Li (i) aprotected area, forest reserve, critical habitat or area of major
interest under the Nature Conservation Act 1992;

Li) a State forest or timber reserve under the Forestry Act 1959;

Di) amarine park under the Marine Parks Act 2004;

Ci (iv)  arecreation area under the Recreation Area Management Act 1988;

(1) aworld heritage area listed under the World Heritage Convention;
Brisbane forest park under the Brisbane Forest Park Act 1977; and

(J) (b) the reconfiguration involves more than 10 lots being created, or any lot
resulting from the reconfiguring is tess than Sha;

 

£X] (iii) none of the above.

 

Page 10

Page 17

INTEGRATED PLANNING ACT 1997

 

 

 

IDAS Assessment Checklist, Version 20, 2 April.2007.

“SECTION 2= ASSESSMENT IN A WILD RIVER AREA

‘(completion mandatory if the proposed development is located in a wild river area) *

 

 

Wild River Area

[t the responsibility of the applicant to
determine if the development is proposed
in a wild river area.

taformation about wild river areas including the
geographical location and position of
management areas in relation to properties,
can be accessed by contacting the
Department of Natural Resources and Water
{NRW), accessing the department's website
www.nrw.qid.gov.au or contacting the
department by email on:

wild [email protected]

Note on Referrals

Referrals for development in a wild river area
(other than for agricultural activities and
animal husbandry activities) are not changed
from the existing referral arrangements.
Notes on development assessable
against the Wild Rivers Code

For information regarding development in a
wild river area, see the relevant wild river
declaration and Guide 27. The relevant wild
river declaration will provide information
regarding which types of development must be
assessed against the Wild Rivers Code, and in
some cases which types of development are
exempt from wild river requirements.

The notes on development assessable against
the Wild Rivers Code in this section of the
checklist provide some guidance however this
May vary between wild river areas, The
relevant declaration will provide the
information applying to each wild river area.

 

-Applications for some new developments will °°

Not be accepted if the proposed development
is in a high preservation area (HPA). Most
apptications for development activities which
may be made including thase in a preservation
area (PA), must be assessed against and
Must comply with the Wild Rivers Code where
indicated in a relevant wild river declaration.

1.

 

Which wild river area is the development proposed in?

The proposed development is to be located in: (tick the applicable box/es)
(1 i) a high preservation area (HPA);

(J ii) a preservation area (PA) ;

(CJ it) a wild river foodplain management area (FMA);

oO iv) a wild river nominated waterway,

(1 v) a designated urban area (DUA).

 

Environmentally relevant activities
(ERAs) in a designated urban area

\fyou answered YES, your application for an
ERA is exempt from any wild river
Tequirements and provided there are no other

aspects of this development that require
@ assessment against wild rivers, you do not
need to complete the remaining questions in
Section 2,

If you answered NO to Q2, please complete
the semaining questions in Section 2.

Clearing native vegetation

If YES, there are a limited number of purposes
for which an application to clear native
vegetation may be accepted in a HPA. See
Guide 27 for a list of relevant purposes for
which an application may be made ina
HPA,

IFYES and you ticked 04 box |} the application
May be made and is assessable against the
Wild Rivers Code. If YES and you ticked Q4
box ji) the application will not be accepted.

Note: If clearing native vegetation is in a PA,
there are no wild river requirements and
provided there are no other aspects of this
development where wild river requirements
apply, do not complete the remaining
questions in Section 2.

 

2.

Does the proposed development only involve any of the following environmentally relevant
activities (ERAs) in a designated urban area (as mapped in the relevant wild river
declaration)?

i) An ERA 28 or ERA 14; or
ii) A level 2 ERA except ERA 1, 2, 3, 4, 20, 22 or 59.
Oo NO oO YES (ensure you have completed Part G of Form 1)

Is the application operational work for clearing native vegetation in a HPA?
Oo NO [1 YES (ensure you have completed Part J of Form 1)

If YES, is the clearing?

{1 i) clearing regrowth (as defined in the Vegetation Management Act 1999) in a registered
area of agriculture in a HPA (see Guide 27); or

(_] ii) in a HPA outside a registered area of agriculture?

Page 11

Page 18

INTEGRATED PLANNING ACT 1997
Works in tidal areas, coastal
management districts and fish
habitat areas

Ityou answered YES to Q5, and ticked any
boxes in Q6), your application is required to be
assessed against and must comply with the
Wild Rivers Code.

If you answered YES to Q5 and ticked box i} in
Q6, your application is required to be referred
tothe EPA.

Note: if specified works are proposed in a
local government area, it is prescribed tidal
work — the relevant local govemment will be
the assessment manager with the EPA as a
concurrence agency

If you answered YES to QS, and ticked box ii)
or iii) in Q6, your application requires referral
to DPIF,

Ifyou answered NO to Q6 and ticked box i) in
Q6, the application will not be accepted.

Ityou answered NO to QS, ticked box ii} in Q6
and the development is necessary to install
authorised works or infrastructure where a
development permit is not required, or if a
required permit is held, the application must
be assessed against and must comply with the
Wild Rivers Code. Applications for purposes
other than specified works or as described
above will not be accepted.

If you answered NO at Q5 and ticked box iii) in
Q6, the application may be made if the works
are ina PA. These applications must be
assessed against and must comply with the
Wild Rivers Code. The application will not be
accepted if the developments proposed to be
located in a HPA.

For more information about specified works

fefer to Guide 27

IDAS Assessment Checklist, Version 20, 2 April 2007, ===

| 5_-|s-the-development for specified works? (See definition in the Wild Rivers Act 2005 and Guide

27- Development in a wild river area)
mie Olyes
The application is for one or more of the following:

O i) Operational works that is tidal works or works in a coastal management district (ensure you
have completed Part M and/or Part P of Form 1); oF

O ii) Operational works for the removal, destruction or damage of marine plants (ensure you have
completed Part O2 of Form 1); OF

oO iii) Building or operational works in a fish habitat area (ensure you have completed Part O2 of Form
1).

 

Residential, commercial or
industrial development

ff you answered YES to Q7, your application is
Not subject to wild river requirements.
Provided there are no other aspects of this
development that require assessment against
the relevant wild river declaration or Wild
Rivers Code, you do not need to complete the
femaining questions in Section 2.

If you answered NO to Q7 and ticked elther
box i) or ii) in Q8, the assessing agency is the
televant local government. The application
must be assessed against and must comply
with the Wild Rivers Code.

~ Is the application for residential, commercial or industrial development in a designated urban

area?
imine Olyes
If NO, does the application for residential, commercial or industrial development involve:

O i) a material change of use made assessable in a local government planning scheme
(ensure you have completed Part D of Form 1); or

C7 ii) operational works associated with reconfiguring a lot (ensure you have completed Part F
of Form 1).

 

Animal husbandry activities

lf you answered YES to Q9 your application
fequires assessment against and must comply
with the Wild Rivers Code.

The assessing agency is NRW.

Note: Applications for animal husbandry
activities will not be accepted if proposed in a
HPA. For more details and a definition of
animal husbandry activities see the Wild
Rivers Act 2005 and refer to Guide 27.
Agricultural activities,

if you answered YES to Q10, your application
tequires assessment against and must comply
with the Witd Rivers Code.

The assessing agency is NRW.

Note: Applications far agricultural activities will
not be accepted if proposed in a HPA. For
more details and a definition of agricultural
activities see the Wild Rivers Act 2005 and
refer to Guide 27.

The production of fodder in a PA, and pasture
improvement using low impact soit disturbance
techniques is not an agricultural activity as
defined under the Wild Rivers Act 2005. For
more information see Guide 27.

 

10.

11.

Does the application involve a material change of use for animal husbandry activities (as
defined under the Wild Rivers Act 2005) in a PA?

(No oO YES (ensure you have completed Part R of Form 1)

Does the application involve agricultural activities {as defined under the Wild Rivers Act 2005)
in a PA?

LIno

If YES is the application for:

oO YES (ensure you have completed Part Q of Form 1)

LJ i) a material change of use; or

LC ii) operational works.

Page 12

Page 19

 

INTEGRATED PLANNING ACT 1997
Works.that- take overland-flow water—

The relevant wild river dectaration will state
works that take overland flow water are either
self assessable or assessable, or are exempt
from wild river requirements.

If you ficked Q13 i), your application must be
assessed by NRW against the Wild Rivers
Code and must comply with the code.

If you ticked Q13 ii) an application is not
Tequired to be made however the works must
comply with the relevant self-assessable
section of the Wild Rivers Code, otherwise the
works become assessable development for
which an application is required and must be
assessed by NRW against the relevant part of
the Wild Rivers Code and must comply with
the code.

lf you ticked Q13 iii) your application is not
‘Subject to wild river requirements.

Applications for development that is other than
that stated to be assessable, self-assessable
or exempt will not be accepted.

Works that interfere with overland
flow water

The relevant wild river declaration will state
works that interfere with overland flow water
that are either self assessable, assessable or
exempt from wild river requirements,

Ifyou ticked Q15 |), your application must be
assessed by NRW against the Wild Rivers
Code and must comply with the code.
Ifyou ticked Q15 ii) an application is not
fequired to be made however the works must
comply with the relevant self-assessable
section of the Wild Rivers Code, otherwise the
works become assessable development for
which an application is required and must be
assessed by NRW against the relevant part of
.. the Wild Rivers Cade and must comply with:
the code,
if you ticked Q15 iii) your application is not
subject to wild river requirements.

Applications for development that is other than
that stated to be assessable, self-assessable
or exempt will not be accepted.

Waterway barrier works

Applications for building ar raising waterway
barrier works in a HPA will not be accepted,
if you answered YES to Q16, your application
must be assessed by DPIF against the Wild
Rivers Code and must comply with the code.

13.

14,

15,

16.

(DAS Assessment Checklist, Version, 20, 2. April. 2002 __—

L]No

If YES, is the application for works stated in the relevant wild river declaration to be?
(i) assessable works

oO YES (ensure you have completed Part Ks of Form 1)

(_] ii) self-assessable works

(J iii) exempt works

Does the application involve works that interfere with overland flow water in a FMA?
O NO DO YES (ensure you have completed Part Kio of Form 1)

If YES, is the application for works stated in the relevant wild rivers declaration to be?
(Ji) assessable works
(Ji) self-assessable works

(1 it) exempt works

Does the application involve building or raising waterway barrier works in a PA?
(no i) YES (ensure you have completed Part O3 of Form 1)

 

Aquaculture (non ERA)

Applications for aquaculture in a HPA will not
be accepted.

Ifyou answered YES to Q17, your application
must be assessed by DPIF against the Wild
Rivers Code and must comply with the code.

Works that interfere with water in a
watercourse

Note: If the development is proposed in a
HPA, applications for all works that interfere
with water in a watercourse (including dams or
weirs, stream realignment or stream diversion)
will not be accepted.

In a PA, applications for instream dams and
weirs may be accepted In nominated
waterways. If you ticked box ii) in Q19, your
application will not be accepted.

Note: Operational works outside a HPA or
nominated waterway are not subject to wild
river requirements.

More information and locations of nominated
waterways is available by contact NRW,
accessing the department's website
www.nrw.qid.qov.au or contacting the
department by email on:

wild [email protected],

18.

19.

 

Does the application involve aquaculture in a PA?
LINo (1 YES (ensure you have completed Part O; of Form 1)

Does the application involve operational works that interfere with water in a watercourse that is
in a nominated waterway in a PA?

oO NO O YES (ensure you have completed the relevant Part K of Form 1)

If YES,
CO i) The application is for an instream dam or weir, or

(_J ii) The application is for operational works that interfere with water in a watercourse, and is
for development other than a dam or weir.

Page 13

 

Page 20

INTEGRATED PLANNING ACT 1997
Environmentally relevant activities

Most applications for.an_ERA In.a. HPA will-nat-
be accepted. Applications which may be
made require referral to the EPA. The
assessment of some ERAs is assessed by
NRW, others have been devolved to OPIF,
NRW or delegated local goverment (see
EPA website for more information on devolved
ERAs)

tfyou answered NO to Q20 you do not need to
complete Qs 21-24.

lf you answered YES to Q20 and the
development is in a PA, your application must
be assessed by the administering authority??
against the Wild Rivers Code and must
comply with the code, unless the proposal is
for development where an application will not
be accepted, or is exempt from wild river
requirements (see Q2). You will be able to
determine if an application will not be
accepted for the development by answering
Q21 - Q24,

(fyou answered NO to Q21, you do not need
to complete Q22. If you answered YES to
Q21 you are required to complete 022.

if you answered NO to 022, the application
wilt not be accepted. If you answered YES to
Q22, the application must he assessed by
NRW against the Wild Rivers Code and must
comply with the code.

Ifyou answered NO to Q23 and the
development is proposed in the HPA the
application will not be accepted. If you
answered YES to Q23, the application must
be assessed by the EPA or NRW (as
prescribed in schedule 8A of the IPA) against
the Wild Rivers Code and must comply with
the code.

if you answered YES to Q24 the application
will not be accepted, {f you answered NO to
Q24, your application must be assessed by
NRW agaist tie Wild Rivers Code and must
comply with the cade.

Exempt ERAs in a designated urban
area

If the development is proposed in a
designated urban area there may be no wild
Fiver requirements. See Section 2 Q2.

Note: All apptications that can be accepted
must be assessed against and must comply
with the Wild Rivers Code (other than exempt
ERAs in a designated urban area).

 

20.

21,

22.

23.

24,

IDAS Assessment Checklist, Version 20, 2 April 2007
Does the application involve an ERA?

im NO ~T YES (ensure you have completed Part G of Form1)

Is the application for an ERA 20 instream?

CIno C] ves

Is a quarry allocation notice held for the proposed ERA 20 instream?

Lino Clyes

Does the application involve any of the following in a HPA?

i) alevel 2 ERA 11, (and is for specified works or a residential complex)

ii) an ERA 19 (dredging)

iii) Low impact ERA 20 (out of stream) for specified works or a residential complex (as defined
in the Wild Rivers Act 2005, and Environmental Protection Act 1994)

iv) an ERA 22 (out of stream)

(no Clyes

Is the proposed development for ERA 20 (out of stream) and;
~— inaFMA; and

— notlow impact; and
— not for a residential complex in the area, or for specified works.

[Jno Llyes

 

Documentation

if you answered NO to Q25, your application
may be subject to an information request and
processing of the application may be delayed.

 

25.

Has documentation been included with the application describing how the applicant proposes
to comply with the mandatory requirements, required outcomes, and/ or performance
requirements as set out in the relevant part/s of the Wild Rivers Code?

[No Cl yes

2 The administering authority may be either the EPA, or if devolved or delegated, the local goverment, OPIF or NRW.

Page 14

 

Page 21

INTEGRATED PLANNING ACT 1997

IDAS Assessment Checklist, Version 20, 2 April 2007

 

— ISECTION-3™ BUIEDING-REFERRALS, (completion not mandatory)

    

Below is a list of the referrals that can apply to an application for building work assessable against the Building Regulation 2006. This section of the IDAS
Assessment Checklist is provided for advice only. This section of the IDAS Assessment Checklist is not required to be completed and lodged with an
application for building work assessable against the Building Regulation 2006 only.

 

Special fire services - generally

For more information go to schedule 2 table 1 and
schedute 2A of the |P Regulation.

Assessment period 15 days. No response is a
deemed refusal.

1. An application may trigger referral to Qld Fire and Rescue Services as an advice agency if the building
work requires special fire services mentioned in schedule 2A part 1 of the integrated Planning Regulation
1998 (IP Regulation) or includes an alternative solution assessed against the performance requirements
of the Building Code of Australia.

 

Fire safety for budget accommodation
For more information go to schedule 2 of the IP
Regulation

2. — An application may trigger referral to Qld Fire and Rescue Services as an advice agency if the building
work the subject of the application requires the installation of a fire safety system for a budget
accommodation building. _

 

Spray painting
For mora information go to schedule 2 of the {P
Regulation

3. An application may trigger referral to the Department of Industrial Relations (DIR) as a concurrence
agency if the application involves a workplace incorporating spray painting.

 

Retail meat premises
For more information go to schedute 2 of the |P

Regulation

4. An application may trigger referral to Safe Food Qld as a concurrence agency if the application involves a
retail meat premises.

 

Private health facilities
Far more information go to schedule 2 of the
IP Requiation

5,  Anapplication may trigger referral to the Department of Health as a concurrence agency if the application
involves a private health facility.

 

Workplace area less than 2.3m?
For more information go to schedule 2 of the IP
Requiation

6. An application may trigger referral to the Department of Industrial Relations (DIR) as an advice agency if
the application involves a work place area less that 2.3m?.

 

oe Land contiguous to a State-
controlled road

For more information go to schedute 2 of the IP
Regulation

7. An application may trigger referral to the Department of Main Roads as a concurrence agency or advice
agency if the application involves land contiguous to a State-controlled road.

 

Pastoral workers accommodation
For more information go to schedule 2 of the IP
Regulation

8. An application may trigger referral to the Department of Industrial Relations (DIR) as a concurrence
agency if the application involves pastoral workers accommodation.

 

Child care centre
For more information go to schedule 2 of the IP

9. An application may trigger referral to the Department of Communities as a concurrence agency if the
application involves a childcare centre.

 

Coastal development
For more information go to schedule 2 of the IP
Regulation

10. An application may trigger referral to the Environmental Protection Agency (EPA) as a concurrence
agency if the application involves land completely or partly seaward of a coastal building line?2,

 

| Heritage 1. An application May trigger referral to the Heritage Council as a concurrence agency if the application
"| For more information go to schedute 2 of the IP involves a heritage registered place.
Regulation

 

Fisheries matters
For more information ga to schedule 2 of the IP
Regulation

12, An application may trigger referral to the Department of Primary Industries and Fisheries (DPI&F) as a
concurrence agency if the application involves assessable building work in a declared fish habitat area; or
as an advice agency if the application involves assessable building work on land that adjoins a declared
fish habitat area.

 

Integration of land use and public

transport

For more information go to schedule 2 of the IP
Regulation

13. An application may trigger referral to Queensland Transport as a concurrence agency if the application
involves existing or future public transport corridors, or airport operational airspace”.

 

 

Railway safety and efficiency
For more information go to schedule 2 of the IP
Regulation

 

14. An application may trigger referral to Queensland Transport as a concurrence agency if the application
involves future railway land.

 

 

NOTE: CONCURRENCE AGENCY ASSESSMENT PERIODS

The local government, as the concurrence agency, is required to assess and provide a response for the following building applications within a prescribed
time. For applications relating to design and siting (17, 18 & 19), and building work for removal or rebuilding (23), the assessment period is 5 days. For
all other applications the assessment period is 15 days. If no response is received from the local government for an application, it is taken to be a
deemed refusal. However for amenity and aesthetics impact of particular building work for a single detached class 1a or class 10 building or structure
(15), no response is taken to be a deemed approval.

 

Amenity and aesthetic impact of
particular building work for single
detached class 1 building or class
10 building or structure

For more information go to schedule 2 table 1 of
tha IP Regulation,

Assessment period 15 days. No response is a
deemed approval.

15. An application will trigger a referral to the local government if it is :
e fora single detached class 1 building or class 10 structure; and
© the local government has declared by resolution the following:
- the appearance of the building or structure will have an extremely adverse impact on the amenity
of the locality; and
— the appearance of the building or structure would be in extreme conflict with the character of the
locality.

 

Whether particular buildings may be
occupied for residential purposes
For more information go to schedule 2 table 1 of
the (P Regulation.

Assessment period 15 days. No responseis a
deemed refusal.

16. An application to use an existing building that is not class 1, 2, 3 or 4 for residential purposes may trigger
a referral to the local government as the concurrence agency.

 

Design and siting
For more information go to schedule 2 table 1 of

 

 

17. An application may trigger referral to the local government as the concurrence agency if the building work
does not comply with the performance criteria of parts 11 and 12 of the Queensland Development Code.

 

 

22 Coastal building {ines are prescribed under the Coastal Protection and Management Act 1995.
2 Operational airspace is as defined in State Planning Policy 1/02 “Development in the Vicinity of Certain Airports and Aviation Facilities".

Page 15

 

Page 22

x

’
INTEGRATED PLANNING ACT 1997

IDAS Assessment Checklist, Version 20, 2 April 2007

 

 

 

 

 

 

 

 

the IP Regulation. 18.__ An. application. may_trigger. referral-to-the-local-government-as-the-concurrence-agency-if-the building work—|

Assessment period 5 days, No response Is a does not comply with the qualitative statement for building clearance and site cover.

deemed refusal 19. An application may trigger referral to the local government as the concurrence agency if the building work
does not comply with the qualitative statement for performance criteria 4, 5, 7, 8 or 9 of the Queensland
Development Code, part 11 or 12.

Fire safety in particular budget 20. An application may trigger referral to the local government as the concurrence agency to determine the

accommodation buildings building will comply with the fire safety standard under the Building Act 1975 when the building work has

For more information go to schedule 2 table 1 of been completed.

the IP Regulation,

Assessment period 15 days. No response is a

deemed refusal.

Higher risk personal appearance 21. An application may trigger referral to the local government as the concurrence agency to determine if the

services building work

For more information go to schedule 2 table 1 of ¢ — complies with the performance criteria of the Queensland Development cade part 15; and

the IP Requlation and the QDC part 15. ¢ the work does not comply with an acceptable solution stated in the part.

Assessment period 15 days. No response is a

deemed refusall.

Building work for residential service | 22. An application for building work for premises in which residential care service under the Residentiat

For more information go to schedule 2 tabla 1 of Services (Accreditation) Act 2002, section 4, is conducted, or is proposed to be conducted, will trigger

the IP Regulation and the QDC part 20. referral to the local government as the concurrence agency.

Assessment period 15 days. No response is a

deemed refusal,

Building work for removal or 23. An application for the removal and/or rebuilding at another site of a building or other structure, will trigger

rebuilding referral to the local government as the concurrence agency.

For more information go to schedule 2 table 1 of

the IP Regulation,

Assessment period § days. No response is a

deemed refusal.

Building work for rainwater tank in 24. An application may trigger referral to the local government as the concurrence agency to determine if the

designated rainwater tank area
For more information go to schedule 2 tabte 1 of
the IP Regulation and the QDC part 25.

Assessment period 15 days. No response is a
deemed refusal

 

building work or structure complies with the relevant performance criteria if -

e Under the Building Regulation 2006, a rainwater tank is proposed to be installed as part of relevant
building work, in a designated rainwater tank area; and

« Under the Queensland Development Code, part 25, the rainwater tank does not include an
acceptable solution for a relevant performance criteria.

 

Page 16

 

Page 23

 

 

GROUP QLD

 

MATERIAL CHANGE OF USE

ASSESSMENT REPORT

In support of an application for a

DETACHED DWELLING

At

34 The Quarterdeck, Noosa Heads
Being described as Lot 82 on RP88934

Prepared by DTS GROUP QLD
Level 1, 6 Heussier Tce ©
PO Box 361Paddington, QLD 4064

On behalf of Jovershire Pty Ltd

February 2008

Local Authority: Noosa Shire Council

 

 

Page 24

February, 2008 DTS Group Qld - Assessment Report

 

 

34 The Quarterdeck, Noosa Heads
Being described as Lot 82 on RP88934

© 2007 - DTS Group Qld Pty Ltd
ABN 19329942119

1st Floor 6 Heussler Tce
Milton Qld
P.O Box 361 Paddington Qid 4064

 

Code Assessable Development Application Report-= = ~~"

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Document Status
Rev Author Reviewer Description Date
No. Name Signature
1 DTS Group Nicholas Bailey First Issue Draft 06.02.08
LIMITATIONS

This report was prepared for the use of Jovershire Pty Ltd in accordance with
generally accepted consulting practice. No other warranty, expressed or implied, is
made as to the professional advice included in this report. This report has not been
prepared for use by parties other than the client stated. It may not contain sufficient

e} information for the purposes of other parties or for other uses. It is recommended that
any works planned by others and relating specifically to the content of this report be
reviewed by DTS Group QLD to verify that the intent of our recommendations is
properly reflected in the final design. To the best of our knowledge, information
contained in this report is accurate at the date of issue.

 

‘A05255A.doc : , 1 2

Page 25

w

1 EXECUTIVE SUMMARY

2 INTRODUCTION

February, 2008 DTS Group Glid - Assessment Report

 

 

Planning Report Guide

 

 

3 SITE INFORMATION AND ANALYSIS...........c:ecsecsssssssesseessssecssssssensscassnssouseonesosscunessaecseses 8

 
 
 
 
 
  

3.1 PHYSICAL DESCRIPTION
3.1.1 Topography and vegetation..
3.1.2 Physical environment...
3.1.3. Area and site frontage.

3.2 EXISTING USES wooeeceeeeeeeseeeeees
3.2.1 Existing improvements..
3.2.2 Existing Infrastructure

3.3 PRE-APPLICATION / CONSULTATION AND HISTORY...

4 PROPOSAL... sssssessessesssesesssressssnsensnsesscrstsesessssceeansscscesecsssesecessesnenssssasesesscsesoseasoasenssonsooss 9

4.1 GENERAL DESCRIPTION..
4.2 PROPOSAL CONTEXT..
4.3 STAGING... ee eeeeeeeee
4.4 SUMMARY AND LIST OF SUPPORTING SPECIALIST REPORTS.
4.5 APPROVAL REQUIREMENTS...

5 ASSESSMENT FRAMEWORK..

5.1 STATE FRAMEWORK.....
5.1.1 Integrated Planning Act 1997 (IPA).....

... 9.1.2 State Planning Policies (identifying relevant Policies only) .. we

5.2 REGIONAL FRAMEWORK ou... csscssssessesseneesesesseseeussesusseeneereneneeneneeee wld
5.2.1 South East Queensland Regional Plan (SEQRP)..
5.2.2. Category and other specifically relevant provisions.
5.2.3 Urban Land Development Authority (ULDA)....

5.3 LOCAL FRAMEWORK
5.3.1 Desired Environmental Outcomes

 
 
 
 
  
 
 
 
   
 
   

 

& PLANNING SCHEME CODES

6.1 NOOSA HEADS LOCALITY CODE...
6.2 DETACHED HOUSE CODE...........-.
6.3 NATURAL HAZARDS OVERLAY CODE.

7 REFERRAL AGENCIEG..............sssssesscrsssssesssesssesssessnsssacsesesseseassssessssesessssesnserensoresnsecstacsies 29

 
 
 

8 KEY PLANNING ISSUES / RECOMMENDATIONS...

 

9 SITE PHOTOS ou... esssssssscsscrssncsncsecnecnscnsansseensassscesescsecenessacsecarensenssceacsuesnasssessneseeeesoesesoe 31

_ Figures

Locality Plan
Site Plan
Regional Plan Land Use Category Plan

Appendices
Architectural Plans

 

(A05255A.doc . Jj 3

Page 26

wn

th

February, 2008 DTS Group Qld - Assessment Report

 

 

  
    
   

 

— —~|—-Executive Summary

® Summary of Proposal

The proposed dwelling is non-compliant with the acceptable solutions of
the Detached Dwelling Code and as such triggers assessable work. The
proposed design will clearly present the same building scale, materials
and form to houses in the immediate locality. Key to this application is
that the proposal maintains a compatible building bulk and scale by
remaining below the specified maximum building height and complying
with required building setbacks. In this circumstance the building is
considered to provide an appropriate level of compliance with
performance criteria 9.10 of the Noosa Heads Locality Code and 14.66 of
the Detached Dwelling Code.

Below illustrates the location of the subject site.

 

   

Ri
a

  

Aen bien
Pont

    

i
Va

ianittldek Rosey:

&

 

 

<
Yu zi
soantons, fe

“NN

YN ees 6:2007,

ie PrIMATY SAHOO meee Hi.

 

 

Figure 1: Locality Plan

e Key Issues
Key issues involved in the assessment of the application are:
Building Scale - Compliance with Table 14 - 26
Consistent Building height on adjoining and surrounding land

 

‘A05255A doc j 4

Page 27

#

ay

February, 2008 DTS Group Qld - Assessment Report

 

 

 

Address of Site: 34 Quarterdeck, Noosa Heads

 

Name of Ward:

 

Real Property Description:' Lot 82 on RP88934

 

Area of Site: §06m?

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Regional Plan Land Use Category: Urban Footprint
Area Classification / Local Plan: Noosa Heads Locality
Name of Owner:! Jovershire Pty Ltd
Type of Application:? Pre-lodgement / Consultation:
Aspects of ieee Council: YIN | Date Contact Name / Ref
Development - DA Oy
PA | OP Ut ||- other or
McU O w (eg. Brisbane Water)
Rol. O O Referral Agencies: De
Bw O O Community: OM
ow QO O Local Councillor: oO
PA 3.1.6 (] yes 4] no Other: Om"
Brief Description! Purpose of Proposal:
“Detached Dwelling - non compliant with Colunm 2 of Table14.26
Staged Development: Not Applicable
| Referral Agencies:' :
Agency clas Referral Agency response received?
O-O | DyesO)no
OO | DyesCino
OO | OyesOno
OO | OyesC no
OO | OyesOno

 

 

 

 

 

Level of Assessment: K4code [1] code notifiable [1] impact

 

Public Notification: Kho Cl yes if Yes: (1 15 (] 30 business days

 

Superseded Planning Scheme Application: Aro UC yes

 

Assessment Manager / Council Officer Previously Involved: Not Applicable

 

 

Applicant Contact Person: Nicholas Bailey

 

'ifit is an extensive list then attach to the overview as a schedule

2 Preliminary Approval (PA), Development Permit (DP), Material Change of Use (MCU), Reconfiguration of a Lot (RoL),

Building Works (BW), Operational Works (OW).
3 Concurrence (C), Advice (A).

 

A05255A.doc

5

 

 

Page 28

February, 2008 OTS Group Qld - Assessment Report

 

{ Noosa'G

      

oY
v

6
Os

en

SC
Sod

“I

se

8

 

 

Client: Jovershire P/L
Plan Showing: Figure 2: Simple Site Plan

Date: January 2008
Application: Detached Dwelling DTS

GROUP QLD

 

 

 

 

AQ6255A doo j 6

Page 29

a

2

February, 2008 OTS Group Qld - Assessment Report

 

Introduction ee Loe

This planning assessment report accompanies a development application
for a Material Change of Use and Preliminary Approval for Building Work at
the subject site located at 34 The Quarterdeck, Noosa Heads. The
development is to be assessed against the Planning Scheme for Noosa
Shire.

Having regard to the definition of “development” at section 1.3.2 of the
Integrated Planning Act 1997, the proposal is considered to constitute:

e Material Change of Use
e =Carnying out Building Work

This report includes an assessment of the proposed house design against all
relevant locality, develooment and overlay codes:

1. Noosa Heads Locality Code
2. Detached Dwelling Code
3. Natural Hazards Overlay Code

 

'A05255A.doc . J

7

Page 30

y a

February, 2008 OTS Group Glid - Assessment Report

 

3 Site Information and Analysis

3.1. Physical Description

3.1.1 Topography and vegetation

According to the detail and level survey, the allotment generally
grades in an east west direction which reflects the fall from the
National Park down towards Noosa Drive. Levels vary between RL75.0
in the eastern corner of The Quarterdeck frontage and RL72.0 in the
rear south western corner.

3.1.2 Physical environment

The site is located within a low density residential environment where
detached housing is the predominant built form. Residential dwelling
generally oriented north south to appreciate views out to Laguna Bay.
Land to the east of The Quarterdeck is the substantial National Park

e@ that sits between Noosa Heads and Sunshine Beach. Detached
housing is predominant in the immediate area before multiple
dwelling developments predominate closer to Noosa Drive.

3.1.3 Area and site frontage

The is 506m? in area and has a 15m frontage to The Quarterdeck. The
proposal house will gain access from a residential crossover to the. -
same frontage. Refer to Plan.

3.2 Existing Uses

3.2.1 Existing Improvements

The subject site is currently improved by a detached dwelling that will be
removed prior to construction of the proposed house.

3.2.2 Existing Infrastructure
e@ The subject allotment has connection to all reticulated services.

3.3 Pre-Application / Consultation and History

e Past applications / approvals

There are no known previous development applications lodged over the
allotment.

« Pre-lodgement meetings

No pre-lodgement meetings were held with regard to the proposed
design.

 

‘AN5255A.doc_ _ 1

8

poe in ee

Page 31

¥

February, 2008 OTS Group Qld - Assessment Report

 

4 Proposal

4.1 General Description

We request your consideration to remove the existing house and
establish a Detached Dwelling under the Noosa Shire Plan at 34 The
Quarterdeck, Noosa Heads. Under the current Noosa Plan 2006 the
site is located in the Noosa Heads Locality, Detached Housing Zone
and is also included within the Natural Hazards Overlay. As a
consequence of the proposed design including a_ partially
subterranean basement level, the proposed dwelling is partially non-
compliant with acceptable solution $6.1 (f) of the Detached Dwelling
Code and triggers a Code Assessment.

In this circumstance, it is considered that the proposed design which
offers a contemporary lightweight style inclusive of energy efficient
design elements such as the recess and projection of built form and
inclusion of greywater reuse and waier collection, can achieve the
specific outcomes set for detached houses within the Noosa Heads
locality.

More specifically, whilst the dwelling will present as a three storey
house on the western elevation, the design is considered to have
taken into consideration the topographic features of the allotment
and minimise site cut and fill. Orawing DA-106 clearly illustrates the
inclusion of the basement level has not affected the maintenance of
a domestic building scale to the Quarterdeck frontage, and is similar
in design to a number of recently approved and constructed
detached houses within the immediate locality and greater shire.

In accordance with the height performance criteria of the code, it is
evident that the proposed design:

¢ can maintain adjoining residential amenity and access to
sunlight:
¢ be considerate to the scale of street and adjoining vegetation

by virtue of the house remaining below the maximum 8m building
height. The proposed house is an acceptable response to the built
form of the streetscape.

Carparking

The proposed building includes off street parking in the two car
garage that sits below kerb level of the Quarterdeck. The garage is
accessed via driveway that falls at approx 1:8 from the frontage at
RL74.2 down to a proposed basement level of RL73.0.

 

‘A05255A.doc

9

Page 32

February, 2008 DTS Group Qld - Assessment Report

 

Recreation / Landscape areas

The proposed house includes private open space and verandah
areas to provide access to sunlight and articulate the building form.
Landscaping will be applied to the site as part of the redevelopment.
It is considered that the design has allowed sufficient space on alll
boundaries for landscaping areas, however, particularly on the
western boundary at ground level to shield the proposed drying court
and also visually reduce the presence on the buildings ground storey.

Service arrangements
The subject allotment will be provided with all required services.

"4.2 Proposal Context

The below aerial photograph illustrates that the allotment to the east,

e that will be subject to the majority of overshadowing from western
sun, is large in area with a significant setback from the common
boundary with the subject site.

 

 

 

 

4.3 Staging

Not Applicable to the subject application.

 

‘A05255A.doc ae w= and 10

Page 33

v

February, 2008 DTS Group Qld - Assessment Report

 

4.4. Summary and List of Supporting Specialist Reports

 

: + Attached in support-of-this-application-is:

e = Architectural Plans undertaken by Willis Greenhalgh Architect

4.5 Approval Requirements

No special conditions are considered to be required as part of the
assessment of this application.

 

‘A05255A.doc : fil

Page 34

February, 2008 DTS Group Qld - Assessment Report

 

5 Assessment Framework

5.1 State Framework
5.1.1 Integrated Planning Act 1997 (IPA}

The Integrated Planning Act 1997 (IPA} provides an all encompassing
statutory planning framework for the State of Queensland. The
Brisbane City Plan 2000 being an IPA compliant planning scheme
should accordingly be read in conjunction with the IPA.

3.5.4 Code assessment

(1) This section applies to any part of the application requiring code
assessment.
. (2) The assessment manager must assess the part of the application
e@ only against—
(a) applicable codes (other than concurrence agency codes the
assessment manager does not apply); and
(b) subject to paragraph (a)—the common material; and
(c) if they are not identified in the planning scheme as being
appropriately reflected in the planning scheme—
(i) State planning policies, or parts of State planning policies;56 and
(ii) for the planning scheme of a local government in the SEQ region—
the SEQ regional plan; and
(d) if the assessment manager is an infrastructure provider—the priority
infrastructure plan.57

The applicant seeks to gain approval for a Detached Dwelling that is
non-complaint with the acceptable solutions of the Detached Dwelling
Code. To enable this proposal a Code assessable development
application is required. A Local Area Plan does not change the level of
assessment applicable to the application.

@ 5.1.2 State Planning Policies {Identifying relevant Policies only)

No State Planning Policies apply to this application.

 

‘A05255A.doc : _. : : 112

Page 35

a a

February, 2008 BTS Group Qld - Assessment Report

 

5.2 Regional Framework

5.2.1 South East Queensland Regional Plan {SEQRP)

The SEQ Regional Plan defines a spatial framework for the region and
allocates land into one of five regional land use categories. Under the
SEQ Regional Plan the site is contained within the ‘Urban Footprint’.

The Urban Footprint identifies land predominantly allocated to provide
for the region’s urban development needs to 2026. The area includes
more than sufficient land to accommodate the full range of urban uses
such as industry, business, housing, infrastructure and open spaces
projected to be required over the next 20 years.

 

 

 

 

5.2.2 Category and other specifically relevant provisions

Not Applicable to the proposed application.

 

‘AN5259A.doc J 13

Page 36

a a

February, 2008 DTS Group Qld - Assessment Report

 

5.2.3 Urban Land Development Authority (ULDA)

 

owt tamnee oer eas em = — == Not Applicable to the proposed application: ~

5.3. Local Framework
5.3.1 Desired Environmental Outcomes

i) RESIDENTIAL USES

Urban and rural settlement for residential use is developed to be
consistent with—

i the planned capacity for roads, community services and infrastructure
for the particular locality; .
ii the expectations of the Shire’s population to have access to a broad
~ range of safe, secure and affordable housing;
@ ii the expected character and amenity for the particular locality;
iv the landform, natural environmental and climatic conditions of the
locality;
v energy efficiency and water conserving design principles;
vi convenience and accessibility to urban services; and
vii suitable separation from incompatible land uses.

The proposed design maintains the reasonable expectations of the
shires population in that the proposal replaces a detached dwelling
with another that is consistent with the natural environment, energy
efficiency and water conserving principles and by virtue of remaining
below the maximum building height within the expected character
and amenity of the particular locality.

5.3.2 Overall Outcomes for Noosa Heads Locality - Detached Housing

m) For the Detached Housing Zone—Detached housing prevails which

maintains—

e@ ia low impact, low density development form of domestic scale;
li a high level of residential amenity: .
iii building styles befitting the character of the locality and which
respond to, and are integrated with, site characteristics including slope,
vegetation and water frontage where applicable; and
iv landscaped settings consistent with the character of the locality;

Similarly to above, the proposed design represents a vast improvement
to the allotments current streetscape contribution. It is considered that
the house maintains a two storey domestic scale to the street and on
elevations where the basement level is visible screening and recess and
projection of built wall have been used to provide for visual interest and
reduce building bulk.

 

‘AQ5255A.doc __. : : : " 114

ee oe he

Page 37

oe 4 *

February, 2008

DTS Group Qid - Assessment Report

 

 

-~-—--—~ 6 - Planning-Scheme-Codes -

'9.9..Effects of use

6.1 Noosa Heads Locality Code

Division 15 - Specific Outcomes and Probable Solutions for the Noosa Heads Locality

Table 9.11

   

 

 

Amenity

O} Uses are located, designed and
operated to avoid significant adverse
changes to the light, air quality, noise,
accessibility, or other conditions
enjoyed by users of associated,
adjoining or nearby uses.

No solution provided

Complies

The proposal applies a detached
dwelling to an existing residential
allotment. The use is consistent
with the area and will not result in
adverse changes to light, air
quality and noise conditions for
adjoining residents.

 

Major road network

©2 The visual amenity and character
surrounding the major road network,
including Sunshine Beach Road
(David Low Way), Eenie Creek Road,
Noosa Drive and Noosa Parade, is
protected and enhances the
entrances to Noosa Heads through—

‘| retaining and enhancing the visual

and physical separation of Noosa
Heads from neighbouring localities:
ensuring future development does not
encroach upon existing vegetation
within the road reserve; and

Utilising dense landscaping and earth
mounding (rather than fencing and
walls) for visual screening and noise
attenuation;

AND

03 Development generates traffic
demands that are consistent with the
future capacity of the road network.

No solution provided.

Compiies

The site is not located on the major
road network. The proposal will not
result in any additional traffic
generation.

 

 

Scenic vistas

O4 Aesthetic and cultural vaiues of

the natural landscape are maintained

through protecting important scenic
vistas—~

a) from the streets, beaches and other
public spaces;

b) to the ocean, river, coastal
lowlands and the vegetated
backdrop of Noosa Hill;

c) within Little Cove— vistas over
Laguna Bay and to the Noosa
National Park and the vegetation
stands, part of the hills and sand
dunes;

 

No solution provided.

 

Complies

The proposed house is within the
maximum building height and will
not result in any change or impact
to scenic vistas within the shire.

 

 

‘AQ5255A.doc.

_j 15

 

Page 38

February, 2008

DTS Group Qld - Assessment Report

 

Specific Outcomes
d) within Cooloola and Weyba Park
_._ Estates— the scenic view of Noosa
National Park and Weyba Creek;
and
e) within Noosa Sound- vistas across
Noosa River.

Probable solutions

Proposal

 

ItMobile business uses 77 aMEEPAGIPEE | 5

 

 

9.10 | Bulit (ori) a a |

 

Density

06 The density of development within

the site area—

a) is compatible with surrounding
development;

b) does not exceect—
i. for the Semi-Attached Housing
Zone ...
ii. for the Attached Housing Zone ...
ji. Business Centre Zone...
iv. Visitor Mixed Use Zone...; and

c) has a low site impact to enhance
the opportunity to maintain natural
site characteristics, including native
vegetation and natural landforms.

  

~| Complies:

The proposed building

development
compliance

by
with

virtue
maximum

is of
compatible scale with surrounding

of

building height, setbacks and site

coverage. The design
vegetation where not
removal for construction
intends to apply landscap
part of the redevelopment.

retains

requiring

and
ing as

Site works are minimised to the

extent

the house provides a

functional entry and sufficient off

street parking.

 

Height

O07 Buildings and other structures—

a) present a building height consistent
with structures on adjoining and
surrounding land; ~ °

b) do not exceed a maximum building
height of—

i. For the Business Centre Zone
OF :
li. For the Visitor Mixed Use Zone
ee OF
iii. For Attached Housing Zone

7 OF
iv. For any other zone— 2 storeys:

c} do not visually dominate the street
or surrounding spaces;

d) preserve the amenity of surrounding
land;

e) respect the scale of surrounding
vegetation;

f} respond to the topography of the
site by minimising cut and fill (eg.
stepping down the site or using a
suspended pole construction); and

57.1 Buildings and other

structures do not exceed a

maximum building height

of—

a) for the Business Centre
Zone ... ; or

b) for the Visitor Mixed Use
Zone ...; OF

c) for Attached Housing
Zone ...; or

d) for any other zone— 8m:

Complies

In accordance with
performance criteria of the

the
code,

it is evident that the proposed

design:
* can maintain adjoining
tesidential amenity and

access to sunlight; and

° be considerate to the scale of

street and

vegetation

adjoining

by virtue of the house remaining
below the maximum 8m building
height. The site uses the variance is

site levels to apply a
basement level.

semi

Being within the maximum building
height requirement from natural
ground it is considered that the
proposal is within the reasonable

 

O08 Buildings and other structures are

appropriately designed and sited to—

a) provide amenity for users of the
premises as well as preserve the
visual and acoustic amenity of

 

adjoining and nearby properties:

comply with the minimum
setbacks identified in
Schedule } - Minimum
Boundary Setbacks.

 

 

g) maintain a mature vegetated expectations of adjoining
skyline. landowners.
Setbacks $8.1 Buildings and structures | Complies

The proposal applies setback in

accordance with Schedule 1

in

that the dwelling maintains a 6m

frontage and a 2m
between 4.5m - 7.5m height

setback

 

 

‘A05255A.doc.

} 16

 

Page 39

February, 2008

DTS Group Qld - Assessment Report

oo

 

 

Specific Outcomes

b) preserve any existing vegetation
that will buffer the proposed
building:

c) allow for landscaping to be
provided between buildings:

d) maintain the visual continuity and
pattern of buildings and landscape
elements within the street;

e) protect public safety and property
within erosion prone areas by
ensuring such areas are maintained
largely free of development; and

f} protect the natural character and
visual amenity of coastal areas and
watercourses.

Probable solutions

Proposal

 

 

Site cover, gross floor area and plot

ratio

O9 The site cover, gross floor area

and plot ratio of buildings and other

roofed siructures—

a) results in a building scale that is
compatible with surrounding
development;

b) does not present an appearance
of excessive bulk to adjacent
properties, roads or other areas in
the vicinity of the sife;

c) maximises the retention of existing

-vegetation and allows for
additional soft landscaping
between buildings;

d) allows for adequate area at ground
level for outdoor recreation,
entertainment, clothes drying and
other site facilities; and

e) facilitates onsite stormwater
management and vehicular
access.

O10 Site cover does not exceed—

a) for the Detached Housing Zone—
50% for a single storey building and
40% for a double storey building;

b) for the Semi-attached Housing Zone

c) for the Attached Housing Zone...
d) for the Visitor Mixed Use Zone...

O1T For Multiple Housing Type 2...
O12 For Multiple housing Type 3 ...
O13 For the Attached Housing Zone...

O14 For the Visitor Mixed Use Zone ...
does not exceed a total of 13,600m2.

 

No solution provided

 

Complies

As stated below the proposed floor
area and site coverage have
ensured that the proposed
dwelling creates a compatible
building bulk with houses in - the
street and immediate area. The
building articulates the built form
through the recession and
projection of walls, varying eave
widths and mixture of external
materials. The proposal retains
significant vegetation and
provides adequate areas of
external open space .and soft
landscaping. A Landscape
concept plan will be provided
under separate cover.

The site cover area is shown in red
on the DA-101.

Complies
The proposed site cover is 203m?
which is 40% of the site area.

N/A
N/A
N/A

N/A

 

 

 

‘A05255A.doc

4
]

:
‘

Page 40

 

 

and Semi-attached Housing Zone—
soft landscaping is provided and
retained over a minimum of 20% of
the site area.

The architectural plans illustrate
that is the intension to apply soft
landscaping as part of the
development. The plans also
illustrate that 20% is achievable. A
jandscape architect is currently in
the process of preparing a plan
illustrating detailed planting.

 

Roof form

O17 Roof forms—

a) contribute positively to the local
skyline;

b) complement the character of the
locality;

c) use soft and articulated, pitched,
skillion or curved roof forms;

d) avoid low pitched (eg. less than 5
degrees) or box profiles/parapets;
and

e) do not create opportunities for
residents to overlook the private
open space areas of neighbouring
properties.

$17.1 The main roof of the
building has a roof pitch no
less than 5 degrees and has

roof forms a minimum of
600mm wide;

AND

$17.2 Buildings and structures
do not include roof top
terraces.

Complies

The houses proposes the use of a
mixture of flat and pitched skillion
roofing, which complements
contemporary house styles in the
area. The house includes eaves

Complies
No roof terrace is proposed.

 

Stoping sites and ridgelines

O19 Development on sloping sites—

a) is responsive to the natural
topography of the site and
minimises cut and fill;

b) does not visually dominate the hill
slope or interrupt the skyline;

c) is integrated with the natural site
characteristics including
vegetation; and

4) for Multiple housing, takes the form
of smail separate buildings:

AND

 

O20 On steep slopes or ridgelines

 

 

$19.1 Buildings and
associated accessways are
not constructed on land with
a slope greater than 25% (1
in 4);

AND

$19.2 Buildings are of split
level design that step down
the slope or have suspended
floor construction;

AND

$19.3 Cut or fill is less than
1.2m in depth;

AND

|

$19.4 The distance between
the ground and the lowest
part of the floor of the
building does not exceed
3m;

AND

$19.5 Buildings present no
more than 2 or 3 storeys at
any one point.

N/AMM Site f not ging 4 noes
drainage problem area}

N/A.

The proposal does not result in

building on land with greater slope
than 1 in 4. '

Complies
Buildings have
construction.

suspended floor

Complies

It is not anticipated that there will
be any cut or fill greater than 1.2m
in depth.

Complies

The distance between the ground
and lowest part of the building
does not exceed 3m

Complles
Building does not exceed 2 or3
storeys at any one point.

 

 

 

 

‘A05255A.doc

_I 18

Mea ee. * wo * “Al
« *

February, 2008 DTS Group Qld - Assessment Report .

!

,

Specific Outcomes Probable solutions Proposal

O15 For the Neighbourhood Centre 1

Zone and the Business Centre Zone... _ .| N/A :

O16 For the Detached house Zone Complies :

Page 41

February, 2008

OTS Group Qld - Assessment Report

 

Specific Outcomes
which are visible from the major road

Probable solutions
$20.1 No solution provided

Proposal
Complies

 

| the | Noosa River or the beaches—

a) new buildings and structures
including outbuildings, are
designed so as not to dominate or
detract from the scenic and
environmental qualities of the site
and its setting: and

b) the external colour scheme of
buildings is designed to blend with
the natural elements of its
surroundings.

The proposed dwelling has been _
sensitive to its ridgeline location
and will not be visible from major
roads or areas of public open
space. The design colour scheme
will be compatible with elements
of the natural surroundings.

 

Public transport node. a.

 

recreations 7+, Pg

  

 

 

Environmental and cultural heritage

values

O22 There are no significant adverse

effects on biodiversity, native

vegetation, habitats, iandscape

quality, water quality or cultural

heritage values, including those

related to—

a) changes to natural drainage;

b) disturbance to any of the wetland
systems; _

¢) management of landslide and fire
risk;

d) erosion and the transport of
sediments off site;

e) unmanaged public access;

f) changes to fauna habitat and
behaviour; and

g) disturbance of buildings and

features, including natural features,

of cultural heritage significance.

No solution provided

N/A

The proposal does not result in any
disturbance to natural drainage
paths, wetlands systems or the
areas biodiversity. A smatl number
of generally ornamental species
will be removed with vegetation
clear of the building platform
being retained.

 

Open space network, ~

oa ae ohne

 

 

 

 

'Pedesitian and bicycle Pater s' ny

 

 

 

 

 

 

cmos Pears

 

 

 

 

Division 16 — Specific Outcomes and Probable Solutions for the Detached Housing

Zone

Table 9.12
Specific Outcomes

 

9.12 Consistent uses

Probable solutions
rarer rca

Proposal

  

 

 

026 The following defined uses and
use classes are consistent uses and
are located in the Detached Housing
zone—

No solution provided "

 

 

Complies
The proposal is for a detached
house.

 

 

 

‘A05255A.doc

J 19

Page 42

Arm
e %

em te

February, 2008

iene

DTS Group GQid - Assessment Report

 

 

Specific Outcomes

a) Home-based business Types 1 or 2:
.b) Transport Type 5;
c) Detached house;
d) Multiple housing Type 1; and
e) Visitor accommodation Type 1

Probable solutions

Proposal

 

19.131 Inconsistent uses =

 

027 The following defined uses and

use classes are inconsistent uses and

are not located in the Detached

Housing Zone—

a) All Agricultural Uses;

b) Commercial business;

c) Entertainment and dining business;

d) Home-based business Type 3;

e) Industrial business;

f) Retail business;

g) All Community Uses;

h) Service and utility;

i) Transport Types 1, 2, 3, 4 or 6;

j) Ancillary dwelling unit;

k) Multiple housing Types 2, 3, 4 or 5;

l) Visitor accommodation Types 2 or
3; and

m) Visitor accommodation Type 4.

No solution provided

 

 

i 9.114} BUIlt forty Sean

 

 

Streetscape character

028 Buildings and structures—

a) are at a scale and nature :
complementary and respeciful to
their surroundings:

b) maintain the visual amenity of
adjoining and surrounding
development: '

c) are designed to address the street
and contribute positively to the
streetscape character;

d) are not visually dominated by
garages or carports;

e) orientate front doors, feature
windows and roof treatment
towards the street;

AND

029 Buildings and other structures

provide for visual interest and amenity

by:-

a) staggering or separating
continuous walls into smaller
sections to vary the elevation; and

b) providing well articulated building
forms with strong vertical design
features.

AND

030 Buildings give the physical

appearance of being one Detached

house, or a series of small separate
structures having the appearance of

Detached houses;

$28.1 The main entrance of
the building faces and is
recognisable from the street;

AND

$29.1 For buildings and other

structures—

a) the maximum wall length
is 15m; and

b) each external wall plane
incorporates at least one
design element to add
visual interest and
amenity (such as
windows, pergolas, sun
shading devices,
balconies or a change of
building material}.

$30.1 No solution provided

 

Performance Solution
The northern elevation illustrates
_that the proposed design provides
substantial verandah and window
frontage to the Quarterdeck to
facilitate surveillance and public
ownership of the street. The entry
to the house is located.on the
eastern elevation, however, the
proposal is considered to comply
with the performance criteria in
that the house maintains a
compatible scale with a legible
pathway from the property
boundary that clearly indicates the
entry.

Complies

Maximum wall length does not
exceed 15m and incorporates
design elements to add visual
interest.

 

 

 

‘A05255A.doc

j 20

 

 

Page 43

SRT ea

*

-

February, 2008

DTS Group Gld - Assessment Report

 

Specific Outcomes

AND

orientated to take advantage of
views, breezes and in the case of
waterfront properties, access to the
water

031 Buildings and living areas are

Probable solutions

..531.1 No solution provided |_| _

Proposal

Complies

The proposed design provides the
physical appearance of being a
detached house.

Complies

The house maintains a north —-
south orientation which provides
access to breezes and views out to
Noosa River.

 

Garages and carports

O32 Garages and carports are
designed and sited to visually
integrate with the building and avoid
dominating the street.

 

$32.1 Garages and

carports—

a) have a front boundary
setback of at least 6m;
and

b) adopt a roof form and
building style that are the
same as that of the
building; and

¢) present a minimum width
to the streetscape (the
total width of garage
doors is no more than 6m
or 50% of the frontage
width, whichever is the

lesser, where the structure

faces the street); or

d) that are visible from, but
do not face the street,
include windows or other
articulation and have a
6m landscaped buffer
between the structure
and the road frontage.

 

 

Complies

The proposed garage is located
within the built form of the house
and is set below street level which
reduces visual prominence.

 

 

6.2 Detached House Code

Table 26 — Detached houses, Ancillary dwelling units and Multiple housing Type 1

"14.65 ‘Sting “~ T

3

Specific Outcomes Probable solutions Proposal

 

 

Setbacks

O1 Buildings and other structures are

appropriately designed and sited to—

a) provide amenity for users of the
premises as well as preserve the
visual and acoustic privacy of

 

$1.1 The minimum setback
of the Detached house or
dwelling unit and associated
buildings and structures from
boundaries is not less than

 

the minimum specified in

Complies

 

The minimum setback of the
Detached house or dwelling unit
and associated buildings and
structures from boundaries is not
Jess than the minimum specified in

 

 

 

‘A05255A doc

$21

Page 44

“

iy

February, 2008

DTS Group Qld - Assessment Report

 

Specific Outcomes
adjoining and nearby land uses;

b) preserve any existing vegetation
that will buffer the proposed
building from adjoining uses;

c) allow for landscaping to be
provided between buildings; and

d) maintain the visual continuity and
pattern of buildings and landscape
elements within the street.

SBR alternative provision to QDC Parts

11 and 12, Pl, P2 and P7

Probable solutions
Schedule 1; or

$1.2 Where there is a
conflict between boundary
setbacks in Schedule |, the
greater of the setbacks
prevails;

AND

$1.3 If there are no
applicable setbacks shown
in Schedule 1, the siting
provisions of Part 11 or 12 of
the Queensland
Development Code apply.
SBR alternative provision to
QDC Parts Il and 12, Al, A2
and A7

Proposal
Schedule |

 

Flooding and drainage

N/A. Site not in a flood or
drainage problem area.

 

Electicity supply infrastructure
O4 Uses and works maintain an
adequate safe distance from
electrical infrastructure including
substations, overhead powerlines,
power poles and transformers.

$4.1 Buildings and structures
{including swimming pools,
sheds, tennis courts or
outbuildings) are not
constructed under overhead
electricity transmission lines,
or within electricity
easements.

Complies

No building works are proposed
under overhead electricity
transmission lines or within

electricity easements.

 

 

Landslide hazard areas

O5 Detached houses, Ancillary
dwelling units and associated uses are
sited or constructed to maintain the
safety of people and property from
the risk of landslide.

 

$5.1 If on land identified as

a Landslide Hazard Area on

Overlay Maps OM1.3-9.3,

the use does not-

a) involve the removal of
vegetation other than
grass from use areas: or

b) involve excavating or

filling of more than 50m3

of material (other than
placement of topsoil not
exceeding 100mm in
depth: or

involve cut or fill with a

vertical depth of more

than 1.5m relative to
ground level; or

redirect or impede water

flows in an existing

watercourse or
stormwater drain; or
involve construction of an
on-site effluent disposal
system; or

55.2 A site specific geo-

technical report prepared

by a registered professional
engineer either—

a) certifies that the site is not
at risk from landslide
emanating from the site or

CG

d

e@

 

Complies

The subject allotment is not
located within a Landslidé Hazard
Area. :

N/A

 

 

 

‘AN5255A.doc

§ 22

Page 45

*

«.

February, 2008

DTS Group Qid - Assessment Report

 

Specific Outcomes

ako) eel eo Lous)
from other land; or
b) identifies methods of
stabilising all buildings,
accessways and use
areas;
AND
$5.3 If the geo-technical
report identifies methods of
stabilising buildings,
accessways and use areas,
those methods are
implemented.

Proposal

 

14,661 Built form: oh esa

AEE LB BEE,

   

RRC

 

Height

O6 Buildings and other structures—

a) are low rise and present a building
height consistent with structures on
adjoining and surrounding land;

b) have a maximum building height
of~

i) Visitor Mixed Use Zone ...; or

ii) if in the Noosa Heads Locality
Attached Housing Zone ...: or

iii) if in the Noosaville Locality
and the Attached Housing
Zone ...; or

iv) otherwise— 2 storeys;

c) do not visually dominate the street,

surrounding spaces or the existing

skyline;

d) preserve the amenity of

surrounding land including access to

sunlight:

e) respect the scale of surrounding

vegetation; and

f} respond to the topography of the

site by stepping down the slope or

siting above the ground level on
stumps, for sloping sites.

SBR alternative provision to QDC Parts

11 and 12, P4.

$6.1 The maximum number
of storeys and building

height is—
a) if in the Visitor Mixed Use
Zone ...; OF

b) if in the Noosa Heads
Locality, Attached Housing
Zone ...: or
¢c) ifin the Noosaville
Locality and the Attached
Housing Zone ...: or
d) ifin the Noosa North ~
Shore Locality ...; or
e) if in the Rural Zone or Rural
Settlement ...; or
f) otherwise - 2 storeys and
8m.

SBR alternative provision to
QDC Parts Il and 12, A4.

Performance Solution

tn accordance with the
performance criteria of the code,
it is evident that the proposed
design:

« can maintain adjoining
residential amenity and
access to sunlight; and

¢ be considerate to the scale of
street and adjoining
vegetation

by virtue of the house remaining
below the maximum 8m building
height. The site uses the variance is
site levels to apply a= semi
basement level.

Being within the maximum building
height requirement from natural
ground it is considered that the
proposal is within the reasonable
expectations of adjoining
landowners.

 

|| Height and bullf form —'Noosaville
} oe

Locality ’Attached Housing Zone

B

 
   

 

 

Site cover

O08 The site cover of buildings and

other roofed structures—

a) is of a scale that is compatible with
surrounding development;

b) does not present an appearance
of bulk to adjacent properties,
roads or other areas in the vicinity
of the site;

c) maximises the retention of existing

$8.1 With the exception of
Ancillary Dwelling Units, the
site cover of class 1 and
class 10 buildings and other
roofed structures does not
exceed 50% for a single
storey building and 40% for a
building of 2 or more storeys
SBR alternative provision to

 

QDC Parts 11 and 12, A3

 

Complies

The proposed building site cover
maintains a 40% site coverage and
can apply the 20% © soft
landscaping area.

 

 

 

‘A05255A.doc

4 23

av

Page 46

a

February, 2008

DTS Group Qld - Assessment Report

 

 

Specific Outcomes
vegetation and allows for
___ Additional soft landscaping

Probable solutions
AND
$8.2 |fin the Eastern

Proposal

 

   
   

 

~~ Between buildings;

d) allows for adequate area at ground
level for outdoor recreation,
entertainment, clothes drying and
other site facilities; and

e) facilitates on-site stormwater
management and vehicular
access.

SBR alternative provision to QDC Parts

1 and 12, P3

Beaches, Noosaville, Noosa
Heads or Noosa North Shore
Locality and in the
Detached Housing or Semi-
attached Housing Zone-soft
landscaping is provided and
retained over a minimum of
20% of site area.

 

Site cover - Noosa Heads Locality,
Detached House Zone, 6-14 Park Road
Noosa Heads

O10 The site cover of buildings and

other roofed structures—

a) has a low site impact to maximise
the opportunity to retain natural site
characteristics such as native
vegetation and natural landforms;
and

b) maintains the safety of people and
property from the risk of landslide
and bushfire.

SBR alternative provision to QDC Parts

tT and. 12, P3 . wee

 

Materials and, id finishes=-Eastern

il Beaches Noosa North h Shore Localities i

$10.1 if on premises at 6-14
Park Road Noosa Heads, the
maximum site cover of all
buildings and structures does
not exceed 150m?,

SBR alternative provision to
QDC Parts 11 and 12, A3.

‘N/A The site is not located at 6-14

 

Park Road Noosa Heads.

 

Roof form

O12 Roof forms—

a) contribute positively to the local
skyline;

b) complement the low density
character of the locality:

c) do not present an appearance of
excessive bulk to side neighbours
(eg. avoid low pitched roofs or box
profiles/parapets);

d) use simple traditional roof designs:

e) do not create opportunities for
residents to overtook the private
open space areas of neighbouring
properties.

$12.1 The main roof of the

Detached house or Ancillary

dwelling unit has-

a) a roof pitch no less than—

i. if in Kin Kin village or
Boreen Point village - 12
degrees;

li. otherwise - 5 degrees;
and if not in Precinct C

or D of Noosa Springs -- roof

overhangs a minimum of

600mm wide;

AND

$12.2 Buildings and

structures do not include

roof top terrace areas.

Complies
The main roof form has a pitch
greater than 5 degrees and
includes eaves no less than 600mm
in width,

 

Privacy

O13 Detached houses and Ancillary
dwelling units are designed to provide
adequate visual privacy for people
using the building and buildings on
adjoining premises.

SBR alternative provision to QDC Parts
1] and 12, P5.

$13.1 The Queensland
Development Code, Part 11,
AS5 applies

Complies

The proposed incorporates a
mixture of fixed screening and
building articulation to maintain
privacy. Landscaping is used on
common boundaries to screenj.
ground level courts and drying
areas.

 

 

Streetscape character
O14 Buildings and structures provide

$14.1 fin the Detached
Housing Zone, for buildings

 

 

Complies
Maximum wall length does not

 

 

 

‘AQ5255A.doc

i” J 24

Page 47

* Pay

February, 2008

DTS Group Qld - Assessment Report

 

_|.a) staggering or separating

 

Specific Outcomes

for visual amenity by—
Continuous walls into smaller
sections to vary the elevation; and

b) providing well articulated building
forms with strong vertical design
features.

Probable solutions

and structures—

a) the maximum wall length_|

“is 15m; and

b) each external wall plane
incorporates at least one
design element to add
visual interest and
amenity (such as
windows, pergolas, sun
shading devices,
balconies or a change of

 

 

pe chardcter-Kin Kin village

 

   

_ building material ___|

Proposal

exceed 15m and_ incorporates
design elements to add_ visual
“interest. Refer to elevations.

 

Streetscape character-Boreen Point
village

 

 

Streetscape - Casual surveillance
O17 Detached houses and ancillary
dwelling units provide opportunity for
casual surveillance to and from the
street to protect the personal safety
and security of residents and visitors.

$17.1 Ifin the Detached
Housing, Semi-attached
Housing, Attached Housing
or Village Mix Zone -- the
main entrance of the
Detached house or Ancillary
dwelling unit is clearly
defined and visible from the
street.

Performance Solution

House not visible from street due to
access arrangement.

 

Garages and carports - ofher than Kin

Kin or Boreen Point villages

O18 Within the Detached Housing,

Semi-Attached Housing, Attached

Housing and Visitor Mixed Use Zones,

garages and carport structures are

designed and sited to visually ,

integrate with the dwelling unit and

avoid dominating the street by—

a) minimising the width of the
structure;

b) minimising projection of the
structure forward of the main face
of dwelling unit; and

c) ensuring the roof form, materials
and detailing complement that of
the associated dwelling unit.

 

 

$18.1 Within the Detached

Housing, Semi-Attached

Housing, Attached Housing

and Visitor Mixed Use Zones,

garages and carports—

a) have a front boundary
setback of at least 6m;
and

b) adopt a roof form and
use building materials that
are the same as that of
the building; and

c) if the front elevation is
visible from road
frontages-

i. present a minimum

width to the streetscape (the

total width of garage doors
is no more than 6m or 50% of
the frontage width,
whichever is the lesser,
where the structure faces
the street); or

ii. for more than a 2

car garage - additional

garages are set back from
the frontage not less than
the width of the additional
garage door; or

that are visible from, but do

 

not face the street, include

Complies

The proposed garaging is set within
the: built form. of the house and
below street level. The proposed
garage will visually integrate and
not be dominating.

 

 

‘A05255A doc _

J 25

 

Page 48

“

February, 2008

~

OTS Group Qld - Assessment Report

 

 

 

 

 

 

 

Specific Outcomes Probable solutions Proposal
windows.or other articulation
and have a 6m vegetated
mF puffer area between the
structure and the frontage.
Garages, carports, boatsheds and N/A
sheds - in Kin Kin village or Boreen
Point village
514.67 | Water Storage 428-8 4 Ene enti oe kk coe Lo ee iin ee
Wafer conservation and storage $20.1 Ifin a designated Complies

020 On-site water storage is
provided, designed and operated to
support the efficient use of water:
AND

O21 On-site water storage is
adequate for occupants every day
use;

AND

©22 Detached houses and Ancillary
dwelling units within Bushfire Hazard
Areas have sufficient water supply for
fire fighting purposes.

rainwater tank area as
identified in Map 1 of
Schedule 8, detached
houses have a rainwater
tank in accordance with
Schedule 8.

AND

$21.1 If notin a reticulated
water service area a
rainwater tank of a minimum
of 60,000 litres is provided for
each dwelling unit;

AND

$22.1 If not in a reticulated
water service area and an
on-site assessment
undertaken by a private
certifier in accordance with
Australian Standard AS3959
indicates the premises is in a
Medium or High Bushfire
Hazard Area—there is, on
the lot, an accessible dam,
swimming pool or water tank
with fire brigade fittings, that
contains at least 5000 litres of
water.

Reticulated water is available to
the allotment. The lower ground
floor illustrates the intention to
apply substantial water storage
below the drying court area.

 

114.68 Effluent Disposal

ie

fon o> SR art

RRB SR OO Rn aes a?

 

023 Effluent disposal does not have a
significant adverse effect on
biodiversity, natural vegetation or
water quality.

024 Treatment and disposal of
wastewater does not have any
detrimental impact on Council's major
water storage and supply - Lake
Macdonald.

No solution provided {no
requirement for self-
assessable development}

N/A

 

14.69: Carparking ss

we Sn

 

t - wee a Jb oe
Carparking spaces $25.1 A minimum of 1] Complies
025 Sufficient carparking is provided | carparking space is} The minimum of 2 onsite carparks

to accommodate the number of
vehicles likely to use the sife.

SBR alternative provision to QDC Parts
1l and 12, P8&

provided on-site;
SBR alternative provisions to
QOC Parts 11 and 12, A&

are provided

 

14.70 Effects ofuse:' |

 

Amenity

 

 

026 Detached houses and Ancillary

$26.1 No solution provided
(no requirement for self-

 

Complies
The proposed application applies

 

 

‘A05255A.doc

i 26

 

Page 49

* ib

February, 2008

DTS Group Qld - Assessment Report

 

Specific Outcomes

dwelling units are located, designed
and operated to avoid significant
‘adverse changes to the light, air
quality, noise, accessibility or other
conditions enjoyed by users of
associated, adjoining or nearby
premises;

AND

027 Lighting associated with the use
of Detached houses and Ancillary
dwelling units does not have an
adverse impact upon the amenity
enjoyed by users of adjoining or
nearby premises.

 

 

[0splcy hones eT |

a —

Probable solutions
assessable development)

$27.1 For lighting-

a) the vertical illumination
resulting from direct,
teflected or other
incidental lighting
emanating from the site
does not exceed 8 lux
when measured at any
point 1.5m outside the
boundary and at any
level from ground level
upward;

b) all flood lighting is hooded
or baffled to direct
lighting downward or is of
a type that gives no
upward component of
light when mounted
horizontally;

all flood lighting is setback a

minimum of- -

i. 6m from the

boundary to any frontage:

and

ii. 2m to any other

boundary:

lighting structures are not

more than 8m in height.

  

 

 

Proposal

a detached house within the
detached dwelling precinct. The
Use will Not detract for adjoining or |”
nearby premises amenity.

N/A
This can be conditioned as part of
approval.

 

 

6.3 Natural Hazards Overlay Code

Table 13.9 Bushfire Hazard Areas

“13.33 Effects of-use and works ~.

—_—e—

Specific Outcomes Probable solutions Proposal 7

A. iA te ep Pa

 

New Uses

O4 The proposed use does not
compromise the safety of people or
property from bushfire.

$4.1 The use is sited on land
that is not in a Medium or
High Bushfire Hazard
Area3é,

Complies

Only the very rear portion of the
subject allotment is included within
the Medium Bushfire Hazard Area
on the overlay mapping. _ This
portion of the allotment generally
falls within the proposed rear
boundary setback. The proposed
structure falls outside the Hazard
Area overlay.

 

Protection of infrastructure and
Community Uses

 

 

$5.1 Community Uses and
Infrastructure Uses are not

 

N/A
The proposal is for a detached

 

 

 

“A05255A.doc

{27

Page 50

February, 2008

>

DTS Group Qld - Assessment Report

 

Specific Outcomes

O05 Community Uses and
Infrastructure

Uses , including that identified below,
are able to function effectively during
and immediately after bushfire
events—

a} Emergency service facilities;

b) Hospitals;

c) Education Type 4 uses, including
stores for valuable records or items of
historic or cultural significance; and

d) Service and utility Uses, including
electricity substations, major electrical
depots and water treatment plants.

ldkol eis le aU laes

-| located in a High or

Medium Bushfire Hazard
Area identified on Overidy ©
Maps OM1.4 to OM9.4;

OR

$5.2 Building work will not
involve more than an
additional 20m2 of gGross
fFloor aArea to an existing
building;

OR

$5.3 Where located ina
High or Medium Bushfire
Hazard Area identified on
Overlay Maps OM1.4 to
OM9.4, uses are designed to
function effectively during
and immediately after
bushfire events37.

Proposal
dwelling.

 

Hazardous materials

O6 Public safety and the environment
are not adversely affected by the
detrimental impacts of bushfire on
hazardous materials manufactured or
stored in bulk.

$6.1 Hazardous materials
are not manufactured and
stored on the site.

Complies

Hazardous materials are not
manufactured and stored on the
site

 

k13.34 Siting” design.and construction

 

 

O7 Uses and works including building:
works are sited, designed and
constructed to—

a) minimise the number of people
and property subject to bushfire risk;
and

b) maximise the protection of people
and property during the passage of a
fire front.

 

$7.1 Uses and-works
including building works are
sited—

Q) on lots greater than
2500m2;

i} in locations of lowest
hazard within the lot (Figure
13.5 provides guidance);
and

il) to achieve setbacks from
hazardous vegetation of 1.5
times the predominant
mature canopy tree height
or 10m whichever is the
greater; and

ili) 10m from any retained
vegetation strips or small
areas of vegetation;

and

iv) so that the elements of
the development least
susceptible to fire are sited
closest to the bushfire
hazard;

b) on lots 2500m2 or greater
- to maximize setbacks from
hazardous vegetation37

| Complies - .
As stated above the site only

 

slightly encumbered by the overlay
in the rear of the allotment. It is
considered that the house is
located outside of the overlay. In
any case, the rear of the house will
be provided with setback from the
canopy line of mature vegetation,

 

 

li13.35 Water supply for fire fighting

 

 

 

 

'AO5255A.doc

J 28

 

reed eee eek

Page 51

ro oO

February, 2008

ae

BTS Group Qld - Assessrnent Report

 

Specific Outcomes

08 An adequate and accessible
|_ water supply is provided for fire
fighting purposes.

dkod exe en cae xe) (OL ce lsd

58.1 For premises not in a
water service area—
each lot has an accessible
dam, swimming pool or
water tank with fire brigade
fittings that contains at least
5000 litres per dwelling.

 

13.36 Vehicle access and fire tralls

   

 

 

Firebreaks and fire access tracks
O09 Firebreaks or fire access tracks
provide—

a) adequate access for fire fighting
and

other emergency vehicles; and

b} adequate width to minimise the
risk of fire crossover.

 

   

ld13.37'Recontiguring-a Lot

7 Referral Agencies

Table of Referral Agencies

$9.1 Firebreaks are provided

 

by—

a} a cleared road reserve
not less than 20m wide
tocated around the
perimeter of the
development;

OR

b) fire access tracks
between the development
and surrounding vegetated
lands that—

i, are a minimum cleared
width of 6m;

ii. have a maximum grade
of 1 in 8 (12.5%) (1:8);

iii, have a formed
pavement;

iv. have access at each

‘| end and:in other

locations where necessary;
v. have passing areas and
turning areas;

vi. have clearly identified
access points for
emergency vehicles; and
vii. are located on public
land or within access
easements that are granted
in favour of Noosa Shire
Council and the
Queensland Fire and
Rescue Service.38

 

Proposal

Complies - N/A

The proposed dwelling is located
ona site with access to reficulated |"
services.

N/A
The site is located within an
established urban area with

access to designated roads. No
firebreaks or fire access tracks are
required.

 

 

Referral Agency

 

Trigger

Codes

 

Referral Agency

Critical Issues
(as relevant)

 

 

Not Applicable to this development application.

 

 

 

 

‘A05255A.doc

j 29

Page 52

e

a

a

February, 2008 OTS Group Qid - Assessment Report

 

 

 

8” Kéy Planning Issues / Recommendations

This assessment report has identified and analysed the relevant planning issues
of this proposed development, which requires a Development Permit for
Material Change of Use requiring Code Assessment. The conclusions that can
be drawn from this assessment report are as follows:

The development application has been made in accordance with the
requirements for development under IDAS.

The proposal is in accordance with the desired environmental outcomes and
intent of the Noosa Heads Locality.

The proposal is in accordance with the Development Principles of the
Detached House Zone.

The proposal complies with the performance criterion and / or acceptable
solutions of the Noosa Heads Locality Code, relevant sections of the
Detached House Code and the Natural Hazards Overlay Code.

Where performance solutions have been proposed it is considered that there
is genuine planning merit to justify the alternative. The house is
complementary to the street and similar in built form to any number of.
detached houses within thé Noosa’ Heads and surrounding localities as
illustrated below.

This Assessment Report supports the development application and _ is
recommended to Council, as the Assessment Manager, for approval subject
to reasonable and relevant conditions.

 

‘A05255A doc

 

_| 30

Page 53

te tart. ™ :

February, 2008 OTS Group Qld - Assessment Report

 

9 Site Photos

 

 

 

 

 

 

 

 

 

 

 

 

Photos 1 & 2 illustrate the existing house to be removed from front and rear

 

 

 

A05255A.doc

j 31

 

Page 54

February. 2008 OTS Group Qld - Assessment Report

 

  
 
 
  

 
 

Photo 3 illustrates the dwelling nearest to the subject site to the east. It is noted that
this houses is considerably setback from the common boundary and screened by
substantial areas of vegetation.

mae

 

 

 

 

 

 

‘A05255A.doc iy

 

 

Page 55

 

February, 2008 DTS Group Qld - Assessrnent Report

 

 

 

 

  

 

-_ z ma
| Photos 5, 6 & 7 illustrate examples of three storey houses approved and constructed .
within the shire. The proposal has provided for a semi basement level whilst :
maintaining a predominantly two storey built scale to the street and eastern
elevation.

 

 

 

 

Appendices

¢ = Architectural Plans undertaken by Willis Greenhalgh Architects.

 

‘A0S255A.doc — a 1 33

Page 56

 

SITE INFORMATION

LOT 82. on RP 88934
34 THE QUARTERDECK i 1
)

 

        

 

     

 

   

NOOSA HEADS i
SITE AREA: 505M2 . , } 3
& — © 2
SITE COVER: ; |
- PROPOSED 203M2 (40%) :
GFA- Beno — oe e
LOWER GROUND | 85.42 aan ‘ [ a
GROUND 218M2 i
UPPER 215M2 _- | i
TOTAL GFA 518.4M2 iS To
. \ WM Lone 17 We | j
toy bo Ike ty.
‘ \ ORYING COURT i 1

 

 

 

 

1:8 RAMP
APPROX

 

 

 

 

ART ROOM
CONC

 

    

 

 

 

 

 

 

 

 

 

 

 

 

 

 

      

o.

TING TREE |

 

 

 

Zo1\\_LOWER GROUND FLOOR PLAN
(oo eaciinon

  

 

 

 

GENERAL NOTES witlisgroonhalgharchitoctswiltisgraanhalg CUENT LocaTion AY scale gare CRAWN BY
RERo eee eee ’ harehitectswillisgreenhalghWGAarchitects MAL AND GAIL THOMS 34 THE QUARTER DECK 1:100 @ A3_ JUNE 2007
=e willisgrecnnaisharcnitectowtittsgreennels NOOSA HEADS | — Se ae
ounce, - Mwillls/groonhalghiarchitocts/willisgreanhe = ——— ae 5 b 6
oe Suite 27 | p07 3216 0555 ; iy 06006 A-100

Siro ‘ Breakfast Greek Wharf | f 07 3216 0557 PROPOSED NEW RESIDENCE LOWER GROUND FLOOR PLAN

‘Spun OA Teri mv Pn oY LEAD NPN ONO HRT PEN
RRO LL NEN AOE

Y

|

194 Breakfast Creek Rd | ABN 42 098 752 384
Newstnad Old 4006 | werw.wparchitects.com.au

Fee aR SRNR aE
|

   

\2006\20060006 The Quarter Deck\CAD\Plot Files\DA-100.dwg, 31/01/2008 6:16:18 PM

Page 57

     

LOT 88
“RP88934

        

  
 

RL 74,770 RL 74,320

LOT 89
_RP88934

 

         
 

 

RL 73.550

  

RL 73,640

EXISTING

3a

TREE

 

 

LOT81

LOT 90
RP88934

RP88934

       

01 \\_UPPER GROUND FLOOR PLAN

     

  
  

    

 

 

GENERAL NOTES isgreenhatgharchitectswillisgreenhalg Hr LocaTion a SeaLe pare DRAWN EY

err esaoon wae tauecs > Simat Glewraevewiste MAL AND GAIL THOMS 34 THE QUARTER DECK 1:100 @ A3. JUNE 2007

a ee cement news NOOSAHEADS ea

Siocon i ana Sinanevenese iwiltis/greenhalgh/architects/willisgreenha i ene Seaman te Revisto

neweeounarmamnnos  § Oh Setgnenoun shen |n tronteese rmoner ome Xi 06008 DA101 B

SST pret cme |? OTROS PROPOSED NEW RESIDENCE UPPER GROUND FLOOR PLAN — ee
1494 Breakfasi Creek Rd | ABN 42 08 752 384 ne era AN ENA ATOR MELE EMER AIT

Newstead Qid 4006 | www.wgarchitects comau - |

ii

! . ;

aye

 

Page 58

aed Osa

 

Z01\_FIRST FLOOR PLAN

cet ae oe

 

 

CAE Aga
. i

GENERAL NOTES Ws5uE DATE REVISION willlsgroonhatgharchitactswillisgreenhalg SUT tocanon a Beau Dare ORAWH BY
cmemogeenmrecernminy y Saar cur revewe harchitectowlillsgreenhalghWGAarchitects MAL AND GAIL THOMS 34 THE QUARTER DECK 1:100 @ A3._ JUNE 2007
Seeermmemnrarrr Ame GUT REVEWISLE witllsgreanhaigharchitectswillisgreennaig N HE
ae manmeaawor {ee cuomrevewesse harchitoctswilllsgreenhalgharchitectswilll OOSA HEADS il Jonna pW as RTO
Gnmeener. ieee fwillis/groonhalgh/architects/willisgreonha cmawmo - 06006 ~DAIO2 A
scorer es ezopacr ream Suite 27 19 07 3216 0555
fewes eterna Breakfast Creck Wharf | 1 07 3218 0557

194 Breakfast Creok Ré | ABN 42 098 752 284
Newstead Qi 4006 | www.wgarchttects.com ay

een ms rE SORTEET AL ITUREDORAD Mo ORI UAT OTH
Reece ot Msi Cs OF IRE PRE ER TO HAT
Peake OF LS ACDOAL LLANE,

PROPOSED NEW RESIDENCE FIRST FLOOR PLAN

 

4

 

L_seynroyPrjcsz006:2008000 The Quarter Deck\CAD\Plot Files\DA-102.dwg, 31/01/2008 6:15:48 PM

. oF

Page 59

  

BOUNDARY

   
 

BOUNDARY

RL 82.770

   

METAL ROOF SHEETING

LIGHTWEIGHT CLADDING — RL 81.550 RL 81,700 AHD

CEILING

     

 

SUN SHADING BLADE
ELEMENTS i

yh

*

 

 

00L2

PRIVACY SCREENING

    

— GLASS BALUSTRADE RL 79,000AHD

aes . vee es . . edie | sae ma : oe A UPPERLEVEL 2 mn
AWNING OVER WALKWAY p

 

000€

RL 76.000AHD
GROUND LEVEL

OUND LEVEL

 

B00E

«

RL 73.000AHD -LOWER GROUND LEVEL

 

 

   

GENERAL NOTES: fssue_ DATE REVISION willtisgreanhalgharchitectswillisgreenhalg

 
 

 

 

 

CENT wocaTion 1" scans CATE RAW RY

cago vows tan END faa Gent RevEw issue harchitectswitiisgroenhalghWGAarchitacts MAL AND GAIL THOMS 34 THE QUARTER DECK 1:100 @ A3_ JUNE 2007

Suinemmanarcwicar:  ~ sie ORME willisgreenhalgharchitestswillisgraanhalg .

vorviemnmet para sce eres harchilectswillisgraenhalgharchitectswilll NOOSA HEADS i oan ORAWNG Re RENIBON

Se en cvvemame swiisigreenhalgh/architects/willisgreenha = ——— =a ; 06008 DA4O4 8

Een scee. preaestCectinet |) Grins PROPOSED NEW RESIDENCE NORTH H eraas eg moos an

194 Breakfast Creek Rd | ABN 42 098 752 284 ELEVATION pares recat erates hear pen conta

Newstead ld 4006 | war. wparchitects.com.au nove

 

4

0 |

Page 60

      

BOUNDARY
BOUNDARY

  
   

RL 82.770 RL 82.770

RL 82.505

 

RL 82.320

RL 81700AHD — LIGHTWEIGHY CLADDING

CEILING

 

 

V

RIVACY SCREENING.

\

 

   
   

RL 79.000AHD_
UPPER LEVEL

 

  

RL 76.000eH0
GROUNBTLEVEL

RL 74.890

    

td

 

RET3O00AHD 2
LOWER GROUND LEVEL

   

ae
°

 

        

 

    

 

 

 

 

i
{
GENERAL NOTES w isgreenhalg ‘HEN Locanien 4 a ecaue are Daawn er
Sateen aT Ae Mn > Ae remivocts MAL AND GAIL THOMS 34 THE QUARTER DECK 1:100 @ A3_ JUNE 2007
ae eonomneaint h tectswiht ms NOOSA HEADS a oe
aa ee cccsenane fwillls/greenhalgh/architects/willisgrocnha = ——— =aw 0600s A405
Feggguervny connie nen arealtost Cros ney [PO R216 0585 PROPOSED NEW RESIDENCE EAS | Soree ws pcheninmon acy mmorvaseracaoemenr era
194 Breakfast Creek Rd | ABN 42 098 752 384 ELEVATION ill Sa DOO TE EN ARRON TT

 

Newstead Qid 4006 | www.wgarchitects.com.au

 

 

-%,
ee |

Page 61

u

:
|
|

 

eo ee

 

BOUNDARY
BOUNDARY
i

RL 82.770

  

METAL SHEET ROOF

 

 

 

4. 4
@ RL 81.700AHD oe
CEILING EAVES GUTTER

 

   

SUN SHADING BLADES

 

LIGHTWEIGHT CLADDING

RL_79,000AHD
UPPER LEVEL

 

 

SUPPORT POSTS

 

O00€

       

 

RL 76.000AHD BALUSTRADE TO DECK

GROUND LEVEL

   

oil
\
4

 

    
   

‘cuEMT LOCATION

 

GENERAL NOTES sgreenhalgharchitectswillisgreenhaig

 

 

 

 

noon ewermoisn esis yee Rat arvew ae nitectaws 'sg rSenhota hWGAorchitects MAL AND GAIL THOMS 34 THE QUARTER DECK
Bees {ES Ethene - Mae Pactncuiiagiaesaisnarentecsen NOOSAHEADS |
Capea” NE OOS fwilllsigreenhalgh/architects/willisgreanha = oaawnea
ESE rone einen sreattos creck inet Lh orasteusee PROPOSED NEW RESIDENCE SOUTH |

194 Breaktast Creek Rd { ABN 42 068 762 304 ELEVATION

Newstead Qk) 4006 | wew.wgarchitects.com.au

       

 
 

‘Bea Dare
4:100 @ AZ JUNE 2007"

DRAWN BY

“aN COATING te, REVISION
06006 DA-106 B

oem sesm ree MOIETY MT RUA. ME Dame TC
SERCO TURGaET TOR or PCM at MEMS PATER WOOL ME ATEN
(MNO ML RT LEN OCTET.

 

Page 62

          
    

td 28F

- Poles ee wee - oe Se eee - -- —- -. ~ —

BOUNDARY
BOUNDARY

 

RL 81.550

 

} AN. RL 81.550
JN
WA SHADING

Ae

RL 81.330 RL 81,700AHD

CEILING

00L2

 

RL_79.000AHD
UPPER LEVEL

000E

RL 76.000AHD
GROUND LEVEL

  

 

 

J

RL 73.550

 

 

 

 

 

 

RL 73.000AHD
LOWER GROUND LEVEL

 

 

 

GENERAL NOTES: feaue ATE REWISIOW isgreonhalgharchitectswillisgreenhalg cuwr . kacaTion [k ocane BRAT BY
caren aT mG 1 Baar Ger ew RSE harchitectswillisgreenhalghWGAarchitects MAL AND GAIL THOMS 34 THE QUARTER DECK 15100 @ A3 SNE 2007 ~
Seettemsamamewreetinet Ge LEVELS ADDED willlagreenhaigharchitactswillisgreenhalg

ver coto Car Ee AL harchitectéwillisgreenhalgharchitectswilli ” 7” : NOOSA HEADS dif Foam DRAWING a, REVISION

Ne iwitlis/greenhalgh/architects/wittisgreenha

sucoammenon oy cmones ed nn suite2? |p 07 32160888 PROJECT BRAMING t 06006 DA-107

ai gan ne) HEMT A

te" Breakfast Creek Wharf | f 07 3216 0557 PROPOSED NEW RESIDENCE WEST Soecnn oem mor anon mwa rere rere

194 Breakfast Creek Rd j ABN 42 098 752 384 . PEPROOUCED OF Téa TEE ANY POR ORY AA MEE PAT COR HOLE THOU RTE,
Newstead Gld 4008 | www.wgarchitects com.au e ELEVATION } Sonn eT,

 

Page 63

 

 

 

xu EB LAND USE SECTION FEES.
om NOOSA |

RECEIPT TYPE
SALE OF DOCUMENTS .
Superseded Planning Scheme Documentation 520
Copy of Permit/Approval Letter 110
The Noosa Plan Documentation 111.

APPLICATION FEES

Material Change-of Use -Codedfnpact ,
roonssiet 6 521
consistent 521

SO
- Assessment under Superseded Planning Scheme . 521°
Modification to a Development Permit 521
Extension of a Currency Period : 521
Operational Works - Landscaping : : 521
e@ Bldg Work assessable against the Planning Scheme 521
PRE LODGEMENT REVIEW
Half Hour 522
One Hour 522
ADVERTISING
: Purchase Advertised Applications — 523
* JETTIES ©
Jetty Application Fee 524
Jetty Bond : 51
: (Category 4)
BONDS
Performance Bond . . 51
(Category 9)
SIGNS
Registration Fee . uo 222
seu FEE . :
. Search of Land Use Section file 112
Liquor Licensing Request 113 .

 

 

ToTAL. ¢ ESO

Name: M1. J Thens

 

ADDRESS: <{~ DTS Grey, Qos

: _ Po bea. Zor PASBEING OS oo by
FILENO:  . og] Oss DATE: (u/ rfoF :
RECEIPT NO: | 32663 al} Signature of TP Officer: PS Reo
AUTHORITY NO: a At

 

7

3[ too Florss], 7

Used in these records

About this file

File size
3.8 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

08_0255 - MCU - Detached House [As Published].pdf · 3.8 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.