Council archive · source document
Re Request for Veg removal approval for Fire Mitigation from STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads · OPW24/0118
Officer Name: Michael Lyons
Officer Email: [email protected]
Phone No: 07 5329 6500
CRM No: RM2020/53583
7 October 2020
Anna Gorgijeski
66 River Terrace
Kangaroo Point QLD 4169
Dear Anna,
RE: Request for approval to remove vegetation for Fire Mitigation
Further to your request for approval to undertake work to remove specified vegetation to
20m along the North-eastern boundary and 15m along the south-eastern boundary, I am
advising the results of the inspection and assessment undertaken by council’s
Assessment Officer.
Approval for removal of the vegetation for fire mitigation will be granted, subject to
conditions, and upon receipt of further information and payment of an application fee and
a bond. Particulars contained in this letter are for your information only - this letter does
not grant approval.
The following conditions will be applied:
1. Payment of an application fee of $187.00 and a bond of $643 to be made at our
Customer Service Counter located at level 1, 9 Pelican Street, Tewantin. Please
note that return of the bond will be subject to an inspection of the site after
completion of works and the inspection may take up to 10 working days from date
customer advises completion of the works.
2. Contractors that are engaged to undertake tree removal are required to be trained to
AQF Level 3 in Arboriculture or equivalent recognised and with relevant experience.
3. Contractors must hold Public Liability Insurance in the sum of $20 million.
4. A Dial Before You Dig must be obtained; this can be done online at
https://www.1100.com.au/ and evidence provided that the tree works will not
interfere with existing underground services.
5. Residents who may be affected by the removal of the tree must be notified of the
work at least three days in advance.
6. All debris associated with the removal must be removed from the site.
7. Traffic and pedestrian access and management is the responsibility of the
contractor/client.
8. Work must be undertaken and completed within 28 days of receipt of approval.
9. If required, stumps must be ground to specifications.
10. Applicant is to submit on behalf of the contractor WH&S Risk Assessment form,
identifying hazards and relevant control measures prior to commencement.
Page 1|2
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 1 page
Page 2
To further your request, please complete and return to council:
• Payment of the application fee and bond required; and
Your application will be processed within 10 business days.
Please note – if your completed application form with payment of the application fee and
bond is not received within three (3) months of the date of this letter, your request will
lapse and be closed. If you require further time to complete your application, please
advise Council within the three month timeframe.
Should you wish to discuss this issue further, please do not hesitate to contact Council’s
Parks team at [email protected] Please quote RM2020/53583 for any future
communication regarding this matter.
Yours faithfully,
Michael Lyons
Environment and Sustainable Development
Technical Officer – Natural Areas I Noosa Council
Page 2|2
Used in these records
Re Request for Veg removal approval for Fire Mitigation from STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdfRelated documentApplication case desk ↗
About this file
- File size
- 31 KB (small file)
- File type
No other editions are linked here.