20240510_NSC_M1717P_MCU minor change request.pdf

of 8

Page text read automatically using OCR, there may be inaccuracies

.


          prepared by Land Graphics;
          1.24 The Singleton Floor Plan, prepared by Greg Gibbs 1514 WD02, December 2015
          1.25 The Singleton Elevations, prepared by Greg Gibbs 1514 WD04, December 2015
          1.26 The Singleton Site Plan + Finishes, prepared by Greg Gibbs 1514 WD01, December
          2015

Comment
The list of approved plans needs to be updated to reflect the site works, which were endorsed by the operational works
approvals and the addition of 7 new visitor parking spaces to the east of the existing covered spaces provided as part of
the Stage 5 and abutting Eenie Creek Rd. No vegetation was cleared to accommodate these additional car parks.

It is also recommended that the approved plan ‘1.2 Road Network and Parking Plan (0379 SK04C) dated October 2004’,
be deleted, as it has been superseded by previously constructed changes to the development. The road network and
parking plan it is no longer relevant as the development is now established and does not reflect the original development
layout which was circa 2004. The additional existing visitor parking sought to be approved as part of this application is
considered inconsequential as it is provided in addition to the car parking requirements of the original approval.

In addition to the updated architectural plan set (refer to Attachment C), we also attach the existing approved MCU plans
for completeness (refer to Attachment D).



Amended Condition 1
Please amend condition 1 as follows:

Revised Site Plan, prepare d by Greg Gibbs 1519 WD01, December 2015
1.2 Road Network & Parking 0379 SK04C dated October 2004,
1.3 Drainage Design 0379 SK 05B dated October 2004,
1.4 Proposed Site Plan, Drawing No TP‐01 Rev P1P5 dated 03 December, 2020 22 April 2024 and
prepared by Select Architects;
1.5 Proposed Ground Floor Plan (Building A), Drawing No TP‐02 Rev P1P3 dated 16 May
2017 22 April 2024 and prepared by Select Architects;
1.6 Proposed First Floor Plan (Building A), Drawing No TP‐03 Rev P1 P3 dated 16 May 2017 22 April 2024
and prepared by Select Architects;
1.7 Proposed Roof Plan (Building A), Drawing No TP‐04 Rev P1 P3 dated 16 May 2017 22 April 2024 and
prepared by Select Architects;
1.8 Proposed Elevations (Building A), Drawing No TP‐05 Rev P1 dated 16 May 2017 and
prepared by Select Architects;
1.9 Ground Floor Plan (Building A B), Drawing No TP‐06 Rev P1 P4 dated 16 May 2017 22 April 2024
and prepared by Select Architects;
1.11 Proposed First Floor Plan (Building B), Drawing No TP‐07 Rev P1 P3 dated 10 November,
2020 22 April 2024 and prepared by Select Architects;
1.12 Proposed Roof Plan (Building B), Drawing No TP‐08 Rev P1 P4 dated 10 November, 2020




JFP Ref: M1717P.                                                                                               Page 4


[OCR of page images]
   

JFOP

DAMIAN
URBANCONSULTANTS

prepared by Land Graphics;

1.24 The Singleton Floor Plan, prepared by Greg Gibbs 1514 WDO2, December 2015
1.25 The Singleton Elevations, prepared by Greg Gibbs 1514 WD04, December 2015
1.26 The Singleton Site Plan + Finishes, prepared by Greg Gibbs 1514 WDO1, December
2015

Comment

The list of approved plans needs to be updated to reflect the site works, which were endorsed by the operational works
approvals and the addition of 7 new visitor parking spaces to the east of the existing covered spaces provided as part of
the Stage 5 and abutting Eenie Creek Rd. No vegetation was cleared to accommodate these additional car parks.

It is also recommended that the approved plan ‘1.2 Road Network and Parking Plan (0379 SKO4C) dated October 2004’,
be deleted, as it has been superseded by previously constructed changes to the development. The road network and
parking plan it is no longer relevant as the development is now established and does not reflect the original development
layout which was circa 2004. The additional existing visitor parking sought to be approved as part of this application is
considered inconsequential as it is provided in addition to the car parking requirements of the original approval.

In addition to the updated architectural plan set (refer to Attachment C), we also attach the existing approved MCU plans
for completeness (refer to Attachment D).

Amended Condition 1
Please amend condition 1 as follows:

Revised Site Plan, prepare d by Greg Gibbs 1519 WD01, December 2015

42 Rood Network 2g. Parking 0379 SKOAC dated October 2004.

1.3 Drainage Design 0379 SK 05B dated October 2004,

1.4 Proposed Site Plan, Drawing No TP-01 Rev-P4P5 dated 03 December 2020 22 April 2024 and
prepared by Select Architects;

1.5 Proposed Ground Floor Plan (Building A), Drawing No TP-02 Rev P£P3 dated 16-Mey
2044.22 April 2024 and prepared by Select Architects;

1.6 Proposed First Floor Plan (Building A), Drawing No TP-03 Rev 24 P3 dated 16 May 2047 22 April 2024
and prepared by Select Architects;

1.7 Proposed Roof Plan (Building A), Drawing No TP-04 Rev 22 P3 dated 16 May2017 22 April 2024 and
prepared by Select Architects;

1.8 Proposed Elevations (Building A), Drawing No TP-05 Rev P1 dated 16 May 2017 and

prepared by Select Architects;

1.9 Ground Floor Plan (Building A B), Drawing No TP-06 Rev 24 P4 dated 16-May201Z 22 April 2024
and prepared by Select Architects;

1.11 Proposed First Floor Plan (Building B), Drawing No TP-07 Rev 24 P3 dated 10-November

2020-22 April 2024 and prepared by Select Architects;

1.12 Proposed Roof Plan (Building B), Drawing No TP-08 Rev 24 P4 dated 10-November 2020

JFP Ref: M1717P. Page 4

Log in to download the original (20240510_NSC_M1717P_MCU minor change request.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.