RFI - Attachment 6 - Technical Note

of 3

Page text shows just the words. Original shows the document exactly as it was published.

4 February 2021


Devcon Property Group
Attention: Mr Simon Drew

Email: [email protected]




PROPOSED INDUSTRIAL COMPLEX
11 LEO ALLEY ROAD, NOOSAVILLE

Dear Simon,
At the request of Devcon Capital 9 Pty Ltd (Devcon), Tectonic has reviewed supplied documents to enable
the provision of the geotechnical advice given below for a proposed retaining wall at the above site. The
following documents were reviewed:

       CSI Soil Testing (CSI) report 13971, dated 18/01/2021.
       Blackburne Jackson architectural drawings 31317-DA01 to DA-14, not inclusive, dated 13/01/2021.
       Covey Associates Pty Ltd (Covey) civil design drawings 192297-C001 to C-411, not inclusive,
        various issues and dates.

We understand that a cut is proposed along the western boundary of the site to depths of not more than
1.5 m below ground level (BGL). The Covey design specifies sheet pile walls to provide temporary support
to the cutting along most of the western boundary, with permanent support presumably to be provided by
concrete tilt panels which will form external walls to the adjoining industrial unit buildings. A short intervening
area between the units, at an existing sewer crossing, is to be retained using masonry block walls supported
on concrete bored piles taken below the sewer invert level (Covey ref. RW4). We are advised by Devcon
(email dated 3 February 2021) that the Covey design is to be amended to include concrete block masonry
walls along the western boundary of the units, in place of concrete tilt panels.

The CSI soil test indicates that three boreholes (denoted BH1 to BH3) were drilled along the western side of
the site, in proximity to the proposed sheet pile walls. These boreholes encountered similar subsurface
conditions comprising an upper layer of variable materials including soft to stiff clays, sands and gravels to
about 0.5 m BGL, then very stiff to hard natural silty clays to drilling termination at 3 m BGL. Soils in these
boreholes were mostly described as moist, however some very moist and wet soils were indicated by CSI in
the upper materials in boreholes BH2 and BH3.

Available aerial imagery, and anecdotal information provided by Devcon, indicates that there are no buildings
or sensitive structures within at least 2 m of the western boundary on the neighbouring property to the west.

Provided that the upper variable soils are benched no steeper than 1V:1H (e.g. 0.5 m horizontal bench), and
that significant groundwater seepage is not encountered during construction, the temporary, unsurcharged
cutting along the western boundary through very stiff to hard natural silty clays may be formed vertical to a
height of not more than 1.5 m. The cut must be retained within two weeks of excavation, unless a longer
timeframe is approved following inspection of the excavation by a suitably qualified and experienced RPEQ
geotechnical engineer (‘Geotechnical Engineer’).
We therefore suggest that the proposed concrete block walls for the western units could be used to provide
permanent support to the western boundary cutting, and that the proposed sheet piles would not be required
subject to implementation of the above advice during construction. Details for waterproofing, drainage and
backfilling behind the block retaining walls would need to be assessed and detailed by a structural engineer.


                                                    Tectonic Geotechnical Pty Ltd
                                                   PO Box 899, Buderim, QLD 4556
                                      Office: (07) 5478 9016 Email: [email protected]
                                                       www.tectonicgeo.com.au
                                                         A.B.N. 83 165 727 828
Log in to download the original file

RFI - Attachment 6 - Technical Note.pdf · 228 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 2 pages

Page 2

Devcon Property Group                                                                           4 February 2021


Design for lateral earth pressures could be based upon an effective friction angle of 30° and soil unit weight
of 19 kN/m³, with the following lateral earth pressure parameters:

       Ka (active)      0.33
       Ko (at-rest)     0.5
       Kp (passive)     3.0
Your attention is drawn to the document Limitations, which is attached to this letter report.

Please contact the undersigned should you wish to discuss any of the above matters.

Yours faithfully

TECTONIC GEOTECHNICAL PTY LTD




Ashley Davey BEng RPEQ 8159
Principal Geotechnical Engineer


Attachments: Limitations




                                                       2/2

Page 3

                                               LIMITATIONS


This document has been prepared for the purpose outlined in Tectonic’s proposal and no responsibility is
accepted for the use of this document, in whole or in part, for any other purpose.

The scope of Tectonic’s Services are as described in Tectonic’s proposal, and are subject to restrictions
and limitations. Tectonic did not perform a complete assessment of all possible conditions or
circumstances that may exist at the site referenced in the report. If a service is not expressly indicated, do
not assume it has been provided. If a matter is not addressed, do not assume that any determination has
been made by Tectonic in regards to it.

Conditions may exist which were undetectable given that economic and time constraints limit the practical
extent of geotechnical investigation. Variations in conditions may occur between investigation locations,
and there may be special conditions pertaining to the site which have not been revealed by the
investigation and which have not therefore been taken into account in the document. Where variations exist
on site, additional studies and actions may be required.

Tectonic’s opinions are based upon information that existed at the time that the work was performed. The
passage of time, man-made or natural events, may alter the site conditions. It is understood that the
Services undertaken allowed Tectonic to form an opinion of the actual conditions of the site at the time the
site was visited and cannot be used to assess the effect of any subsequent changes in the quality of the
site, or its surroundings, or any laws or regulations.

Any assessments made in the preparation of this document are based on the conditions indicated from
published sources and the findings of the investigation described. Actual subsurface conditions may differ
from those indicated in the document (e.g. between boreholes or test pits). No warranty is included, either
express or implied, that the actual conditions will conform exactly to the assessments contained in this
document.

Where data supplied by the client or other external sources, including previous site investigation data, have
been used, it has been assumed that the information is correct unless otherwise stated. No responsibility is
accepted by Tectonic for incomplete or inaccurate data supplied by others.

This document is provided for the sole use by the Client and its professional advisers. No responsibility
whatsoever for the contents of this document will be accepted to any person other than the Client. Any use
which a third party makes of this document, or any reliance on or decisions to be made based on it, is the
responsibility of such third parties. Tectonic accepts no responsibility for damages, if any, suffered by any
third party as a result of decisions made or actions based on this document.




Rev 1 (March 2016)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.