Council archive · source document
L05 extension of currency period · 132005.699.10
Attached to the e-mail 132005.220653.10 -Covering letter & Superseded form.
Council Reference: 132003.220653.6 Our Reference: 00475 L05 NG th 5 October 2016 Chief Executive Officer Noosa Council Po Box 141 TEWANTIN QLD 4565 Attention: Planning & Infrastructure Confidential Email Transmission: [email protected] Original in Post: No Dear Sir/Madam RE: REQUEST FOR EXTENSION OF RELEVANT PERIOD_______________________________ Development Permit for Material Change of Use of Premises for Multiple Dwelling (14 units) situated at 10 Serenity Close, Noosa Heads, described as Lot 902 on SP240848: Martoo Consulting has been engaged by CBD Settlers Cove Pty Ltd being the owner of the above site, to request an extension to the currency period for the above development approval. The applicant seeks nd to extend the relevant period by an additional 6 months to the 2 June 2017, to enable completion of construction works, building certification and titling. The background of the development application is detailed below: • October 2005 - Council approved an application for a Material Change of Use for a Multiple Dwelling of 42 Units. • August 2008 – Council approved an application to change the approved plans and conditions. • December 2008 – Council approved an application to change conditions. • th March 2010 – Council approved an application extend the relevant period until 13 October 2011. • December 2010 – Council approved an application to update the approved plans and reduce the number of units to 36. The revised plans reduced gross floor area and updated the design to be consistent with the provisions of the Noosa Plan. The relevant period was also extended until the 2 December 2014. • April 2011 – Council agreed to modification of conditions. • July 2013 – Council approved an application extend the relevant period until 2 December 2015. • December 2013 – Council agreed to issue a Generally in Accordance Approval. • June 2014 – Council approved an application to change conditions and extend the relevant period until 2 December 2016. • March 2015 – Council agreed to change the approved plans and conditions
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 2 pages
Page 2
Page 2
As part of the above approvals, the development was split into two stages under a principal and
subsidiary scheme arrangement, creating lots and common property from former Lot 5 Serenity Close.
The first stage of development was completed in 2013. The second stage is being constructed on the
balance Lot 902.
The applicant now seeks approval to extend the current approval for a further 6 months noting:
• The site is included in the Attached housing zone and Open Space Conservation zone
and the existing unit development and built form is consistent with this zoning;
• The existing development yield is consistent with the current 2006 Noosa Plan;
• Construction was expected to commence early 2015 however procurement delays
resulted in construction works commencing later that year;
• The construction of the second stage is almost complete;
• Approvals required to effect the commencement of the approved use include the issue of
a certificate of classification for the building, the transfer of easements and the sealing of
the community management statement and the strata plans;
• Taking into consideration Christmas closures, further time (approximately 6 months) is
sought to ensure the development is properly completed, new and existing easements are
surveyed and all building and development approval compliance requirements are met in
order for the use to commence.
STATUTORY REQUIREMENTS:
In accordance with Section 388 of the Sustainable Planning Act 2009, in deciding a request to extend
the relevant period, the assessment manager must only have regard to:
a) the consistency of the approval, including its conditions, with the current laws and policies
applying to the development, including, for example, the amount and type of infrastructure
contributions, or charges payable under chapter 8, parts 2 and 3; and
(b) the community’s current awareness of the development approval; and
(c) whether, if the request were refused—
(i) further rights to make a submission may be available for a further development application;
and
(ii) the likely extent to which those rights may be exercised; and
(d) the views of any concurrence agency for the approval given under section 385.
ASSESSMENT:
The current development approval was assessed and granted under the superseded planning scheme
prior to the current Noosa Plan. The proposal was reviewed against the 2006 Noosa Plan provisions
under the 2010 application for extension of the relevant period, wherein it was determined that the
development form generally was consistent with the current requirements of the Noosa Plan and the
areas of non compliance were minor. The current approval and development is therefore consistent
with the current laws and policies.
With regard to infrastructure charges it is noted that as part of previous changes to the approvals and
extensions, infrastructure charges for missing networks have been charged.
The Sustainable Planning Act details that the community’s awareness of the proposal is to be
considered in determining a request to extend the relevant period. The community is well aware that
the site is being developed for units as evidenced by the construction works on site.
The development under construction is consistent with the current planning scheme requirements and
policies and the current conditions protect the environmental considerations of the site. The proposed
extension is considered to meet the criteria of the Act and the applicant therefore requests an
extension of the currency period for a further 6 months until 2 June 2017.
Page 3
Page 3
This development application has been prepared in accordance with the Sustainable Planning Act
2009 and is being submitted with the following attached:
1. The completed Council form.
2. Power of Attorney document on behalf of the owner.
3. A cheque totalling $2,406.00 from the applicant, being payment of the relevant application
fee.
Please contact me if you require any further information and/or clarification.
Yours sincerely,
Nadine Gorton
Senior Planner
martoo consulting pty. ltd.
Used in these records
L05 extension of currency period.pdfRelated documentApplication case desk ↗
About this file
- File size
- 381 KB (small file)
- File type
No other editions are linked here.