                                                                                  Officer:            Samuel Osakwe
                                                                                  Direct Telephone:   07 5329 6316
                                                                                  Our Reference:      132005.638.03
                                                                                  Your Reference:     n/a

                 22 February 2024


                 Noosa Shire Council
                 C/- Adamson Town Planning Pty Ltd
                 PO Box 894
                 COOROY QLD 4563
                 [email protected]



                 Dear Sir/Madam,
                                          Decision Notice – Other Change
                                                       Planning Act 2016

                 I refer to your application and advise that on 15 February 2024, Council decided to approve
                 the application, subject to conditions.
                 Details of the decision are as follows:
                 1.      APPLICATION DETAILS

                     Application No:           132005.638.03

                     Street address:           Eumundi Land Fill 561 Eumundi Noosa Road, Doonan

                     Real property description: Lot 77 SP 298776

                     Planning Scheme:          Noosa Plan 2020 (25 September 2020)

                 2.      DECISION DETAILS

                 The following type of approval was issued on 24 November 2005.
                 •       Material Change of Use – Expansion of Special Purpose (Waste Disposal & Recycling
                         Facility) & Ongoing Clearing Purposes.
                 In relation to the request to make an Other Change to the existing approval, Council on 15
                 February 2024, decided to approve the requested changes. The changes are detailed
                 below.
                 A.     Approve the Change; and
                 B.     Include additional conditions 14 - 45.
                 3.      CURRENCY PERIOD OF APPROVAL

                 The currency period for this development approval is stated in the conditions below.




                 ABN 97.969.214.121                                                             PO Box 141
                 noosa.qld.gov.au                                                        Tewantin QLD 4565
                 [email protected]                                                        07 5329 6500
                                                                                                           Page 1 of
                  24
Document Set ID: 22816452
Version: 8, Version Date: 22/02/2024
Log in to download the original file

SUPERSEDED Decision Notice - Other Change - Council Meeting Decision 132005 638 03 [As Published].pdf · 1.0 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 23 pages

Page 2

                 4.     ASSESSMENT MANAGER CONDITIONS

                 PLANNING
                        When Conditions must be Complied With
                        Land Use
                 1.     Development undertaken in accordance with this approval must generally comply with
                        the approved plans of development. The approved plan is titled Proposed Future
                        Development of Noosaville Landfill stamped and dated 24 November 2005 and as may
                        be amended by these conditions.
                 2.     The development must be undertaken and operated in a manner that causes no
                        detrimental effect upon the amenity of the neighbourhood by reason of the creation of
                        excessive noise, lighting nuisance or other emissions.
                 3.     Existing trees on the site and within road reserves are to be retained, except where
                        required to be removed due to building operations or the conduct of the approved use.
                 4.     Cleared vegetation is to be suitably processed by one of the following methods and
                        removed from the site:-
                        4.1. Processing through a woodchipper or shredder. The resulting mulch is to be
                             stockpiled loose in heaps of less than 1000 cubic metres, less than 2.5 metres
                             high with a minimum of 10 metres between edges of heaps.
                        4.2. Disposal for firewood.
                        4.3. Disposal for landscaping purposes.
                        4.4. Transport to alternative site for breaking down materials provided that all
                             necessary permits have been obtained to allow the alternate site to be used for
                             this purpose.
                        4.5. The Applicant is advised that burning off is an unacceptable method of disposal.
                 5.     Any advertising sign or device is to comply with Council's policies on advertising.
                 6.     A Bushfire Management Plan is required to be prepared by a suitably qualified expert
                        detailing any measures that are required to be undertaken on the subject site to ensure
                        the risk of bushfire hazard is minimised and managed. The plan shall be to the
                        reasonable satisfaction of the Queensland Fire and Rescue Service.
                 7.     The proposed extensions to the Waste disposal and recycling facility shall incorporate
                        requirements for the management of acid sulfate soils in accordance with State Planning
                        Policy 2/02 - Planning and Managing Development Involving Acid Sulfate Soils.
                 8.     A Koala Management Plan is required to be prepared by a suitably qualified expert
                        detailing any proposed relocation of koalas and rehabilitation of other areas of the site
                        with suitable koala food trees, if appropriate.
                 9.     The Development Permit for a material change of use of premises lapses if the use has
                        not happened by 24 November 2009 unless an application to extend the currency is
                        approved by Council.
                         Land Development
                 10.    Any person acting on this permit shall prevent erosion and sediment export from leaving
                        the site. Site control measures such as silt fencing, controlled gravel access to the site
                        and controlled disposal of waste, will be necessary.
                 11.    Prior to undertaking any excavation, the person acting on this permit shall contact public
                        utility service providers to ascertain the location of their underground services




                                                                                                        Page 2 of 24
Document Set ID: 22816452
Version: 8, Version Date: 22/02/2024

Page 3

                 12.    The person acting on this permit shall apply and obtain all other necessary permits
                        including crane, road opening, hoarding, footpath occupation and/or any other approvals
                        required under any other Act or By-Law.
                 13.    The transportation of all materials to and from the site shall be undertaken in a manner
                        such that no particulate matter escapes onto a public road. All vehicles carrying
                        materials either to or from the site shall be covered to prevent materials including dust
                        being windblown from the vehicle.
                  Additional conditions 15 February 2024
                 14.    Unless otherwise stated, all conditions of this Decision Notice must be complied with
                        prior to the use commencing, and then compliance maintained at all times while the use
                        continues.
                        Approved Plans
                 15.    Development authorised by this approval must be undertaken generally in accordance
                        with the Approved Plans listed in the table/s below. The plans must be amended to
                        incorporate the amendments listed within the table below and resubmitted to Council
                        prior to the commencement of any works commencing on the site.

                          Plan No.           Rev.    Plan/Document Name                          Date

                          501042 CO2         A       Proposed site layout plan prepared by 7/12/2023
                                                     Noosa Council

                          501042 CO2         A       Proposed offset planting plan prepared 7/12/2023
                                                     by Noosa Council

                          JOO352R1V2         -       Noosa Landfill RRA flood Assessment 6/04/2022
                                                     prepared by Hydrology and Water
                                                     Management Consulting

                        The following plans require amendment.

                          Plan No.           Rev.    Plan/Document Name                          Date

                          <R2015             B       Noosa   Landfill   –     Stormwater 7/12/2023
                                                     Management Plan prepared by Topo
                                                 ▪   Update the report to reflect the current masterplan for the
                          Amendments
                                                     site and the specific changes for the site encompassed by
                                                     the application
                                                 ▪   Specify the final HES basin detail from the range of options
                                                     presented in the report, including consideration of whether
                                                     a Type-B HES basin may present a lower-risk option
                                                     compared to the flap-gated arrangement proposed to
                                                     prevent back-flows into the Type-A arrangement as
                                                     currently proposed
                                                 ▪   Include all details for the sizing and proposed levels of the
                                                     HES basin within the body of the report, based on recent
                                                     detailed survey at the point of discharge and downstream;
                                                     and
                                                 ▪   Include construction-phase erosion and sediment control
                                                     plans which document how the transition from the current




                                                                                                         Page 3 of 24
Document Set ID: 22816452
Version: 8, Version Date: 22/02/2024

Page 4

                                                     HES basin location to the ultimate location (including filling
                                                     for the RRA pad) will be achieved


                        *(Refer to Advisory Note)
                        Nature and Extent of Approved Use
                 16.    This development permit authorises a Utility Installation (Waste disposal and recycling
                        facility) to be established on the site. The subject use is limited to waste management
                        and ancillary activities associated with the primary use occurring on the site.
                 17.    The landfill waste management activities must not extend outside the designated use
                        areas as shown on the approved plans. Signage is to be placed along the northern,
                        eastern, and southern boundaries of the approved use areas to assist in delineating the
                        edge of the approved use areas and surrounding bushland.
                 18.    This approval does not approve any new building or structures within the resource
                        recovery area except for any fencing or signage permitted as part of this approval.
                        Public safety
                 19.    Public signage must be erected along all internal roads to assist the public navigate
                        through the site, in particular the resource recovery area.
                 ECOLOGY AND ENVIRONMENT
                 20.    A detailed Offset Delivery Plan (ODP) must be developed in accordance with the
                        Environmental Offsets Act 2014. The development must offset a minimum 500 non
                        juvenile koala habitat trees (the impact) at the ratio of 6:1 to satisfy the State Government
                        Supported Infrastructure Koala Policy 2017.The ODP shall include details such as
                        species composition, planting density, planting methodology, annual reporting and
                        include a minimum 5-year maintenance for the proposed 1.8ha Offset area.
                 21.    Certification must be submitted to Council from a qualified person* which certifies that
                        the subject works have been undertaken in accordance with the approved Offset
                        Delivery Plan prior to the commencement of the use of the additional area.
                        *(Refer to Advisory Note)
                 22.    Construct a minimum 1.8m temporary fence around the operational areas of the landfill
                        to prevent rubbish from leaving the landfill area and depositing in the adjoining bushland.
                 23.    A Weed Management Plan must be prepared which addresses weed management
                        along the interface of the proposed earthworks footprint with bushland areas, including
                        but not limited to a minimum 5m grassed buffer area between the proposed resource
                        recovery and the adjoining vegetation to the north. Control of all weed species listed in
                        the following standards and legislation must be undertaken:
                        a. Declared plants under the Land Protection (Biodiversity Act 2014 and subordinate
                           Regulation 2016)
                        b. Council’s Biosecurity Plan 2020 pest plants listed in schedule 1 part 3, schedule 2,
                           and nonscheduled invasive species.
                 24.    The requirements and recommendations of the approved weed management plan must
                        be implemented. Certification must be submitted to Council from a qualified person*
                        which certifies that the subject works have been undertaken in accordance with the
                        approved Weed Management Plan.
                        *(Refer to Advisory Note)
                 25.    A Sediment and Erosion Control Plan must be prepared by a suitably qualified person*.




                                                                                                           Page 4 of 24
Document Set ID: 22816452
Version: 8, Version Date: 22/02/2024

Page 5

                 26.    The sites supervising engineer must ensure that the sediment and erosion control
                        measures have:
                        a.      Been duly designed by an RPEQ or CPESC and constructed in accordance with
                                "best practise" methods,
                        b.      Been revised by an RPEQ or CPESC to address the issues raised by changes in
                                the projected construction schedule and/or methods,
                        c.      Been revised to address predicted rainfall events, and
                        d.      Achieve the desired environmental outcomes.
                 27.    The erosion and sediment control measures must be designed, installed, and
                        maintained in accordance with the current best practice standards.
                 28.    Certification must be submitted to Council from a qualified person* which certifies that
                        the subject works have been undertaken in accordance with the Sediment and Erosion
                        Control Plan.
                        *(Refer to Advisory Note)
                 29.    A Vegetation Removal & Fauna Management Plan must be prepared by a suitably
                        qualified person to mitigate the risk of clearing impacts to all native fauna and adjoining
                        vegetation. The sequential clearing requirements specified under the Nature
                        Conservation (Koala) Conservation Plan 2017 are to be adopted in the Plan.
                 30.    A suitably qualified person must be engaged to manage flora and fauna prior and during
                        clearing to ensure works are carried out in accordance with the Vegetation Removal and
                        Fauna Management Plan (required as part of this approval) and the Nature
                        Conservation Act 1992.
                 31.    Certification must be submitted to Council from a qualified person* which certifies that
                        the subject works have been undertaken in accordance with the approved Vegetation
                        Removal & Fauna Management Plan.
                        *(Refer to Advisory Note)
                 32.    An Arborist Assessment must be completed by a suitably qualified and experienced
                        Level 5 consulting arborist of the trees likely to be impacted along the edge of the
                        earthworks footprint and any recommendations made are adopted. Disturbance to
                        retained remnant vegetation and tree root protection zones of large, retained habitat
                        trees (trees with dbh >300mm) that occur next to the clearing area is to be avoided as
                        far as practicable.
                 33.    Certification must be submitted to Council from a qualified person* which certifies that
                        the subject works have been undertaken in accordance with the approved Arborist
                        assessment.
                        *(Refer to Advisory Note)
                        Bushfire management
                 34.    A bushfire hazard assessment must be prepared in accordance with the SPP 2019
                        Guidelines: Natural hazards Risk and Resilience Bushfire 2019 and the QFES Bushfire
                        Resilience Community 2019 for the development.
                 35.    The development must be carried out in accordance with the requirements and
                        recommendations of the Bushfire Management Plan. Certification must be submitted to
                        Council from a qualified person* which certifies that the subject works have been
                        undertaken in accordance with the approved Bushfire Management Plan.
                        *(Refer to Advisory Note)
                 36.    A copy of the Bushfire Management Plan must be provided to the nearest fire authority



                                                                                                         Page 5 of 24
Document Set ID: 22816452
Version: 8, Version Date: 22/02/2024

Page 6

                        and always maintained at the waste management facility site office.
                 37.    Certification must be submitted to Council from a qualified person* which certifies that
                        the development has been undertaken and constructed in accordance with the bushfire
                        management conditions of this Decision Notice.
                        *(Refer to Advisory Note)
                 38.    A review and certification of the Bushfire Management Plan is required every 5 years to
                        ensure its currency and must be submitted to Council from a qualified person*.
                        *(Refer to Advisory Note)
                        Environmental covenant
                 39.    A vegetation protection covenant must be registered against the title/s of the property
                        over the area identified as the 1.8ha Proposed Offset Planting Area as shown on the
                        Approved Plans pursuant to Section 97A of the Land Title Act 1994. The covenant
                        document and a survey plan must be submitted to Council for endorsement prior to
                        lodgement with the relevant titles authority for registration of title. The covenant
                        document must:
                        a.      incorporate the requirements of this Decision Notice
                        b.      include Noosa Council as Covenantee reference Queensland Land Title Registry
                                Standard Terms Document No. 715597513.
                 40.    The vegetation protection covenant document must be registered with the titles office
                        before clearing commences.
                 ENGINEERING
                        Earthworks and Retaining Walls
                 41.    All fill and associated batters must be contained entirely within the approved use area
                        and must be designed and certified by a suitably qualified person.
                        Acid Sulfate Soils
                 42.    An Acid Sulfate Soils Investigation Report must be prepared to mitigate the risk of acid
                        sulfate soils on the adjacent bushland /wetland areas.
                        All requirements and recommendations of the Acid Sulfate Soils Investigation Report
                        must be certified by a suitably qualified person*.
                        *(Refer to Advisory Note)
                 STORMWATER
                 43.    Prior to commencement of works associated with the relocation of the HES basin,
                        provide an updated SWMP, which is based generally on the Noosa Landfill – Stormwater
                        Management Plan (Topo, 7/2/2022) and which addresses the following:
                        a.      Update the report to reflect the approved masterplan for the site and the specific
                                changes for the site encompassed by the application;
                        b.      Specify the final HES basin detail from the range of options presented in the report,
                                including consideration of whether a Type-B HES basin may present a lower-risk
                                option compared to the flap-gated arrangement proposed to prevent back-flows
                                into the Type-A arrangement as currently proposed;
                        c.      Include all details for the sizing and proposed levels of the HES basin within the
                                body of the report, based on recent detailed survey at the point of discharge and
                                downstream; and
                        d.      Include construction-phase erosion and sediment control plans which document




                                                                                                           Page 6 of 24
Document Set ID: 22816452
Version: 8, Version Date: 22/02/2024

Page 7

                                how the transition from the current HES basin location to the ultimate location
                                (including filling for the RRA pad) will be achieved.
                 44.    All future building floor levels and waste management areas are to be provided with
                        surface levels which are a minimum of 300mm above the 1%AEP local flood level,
                        including allowance for climate change by year 2100.
                 45.    Works are to be undertaken generally in accordance with the Noosa Landfill RRA Flood
                        Assessment (J00352R1V2) by Hydrology and Water Management Consulting, dated
                        6/4/2022. In conjunction with detailed design for the project, the design of the fill pad
                        and the Flood Assessment are to be updated to incorporate a system for flow
                        conveyance and distribution along the northern boundary of the fill pad which achieves
                        greater replication of existing flow patterns to the retained vegetation north of the works.
                        This is required in order to mitigate potential changes in wetness resulting from frequent
                        discharges or the risk of erosion during less frequent events.
                 5.     REFERENCE DOCUMENTS

                 Not applicable.
                 6.     REFERRAL AGENCIES

                 The referral agencies applicable to this application are:
                  Referral Status       Referral Agency and Referral Trigger               Response
                                        Address
                  Concurrence           Department of Natural Clearing            native The agency provided
                                        Resources & Mines, PO vegetation                 its response on 1
                                        Box 383, Gympie QLD                              November         2005
                                        4570                                             (Reference        No.
                                                                                         2005/10121697737).
                                                                                         A    copy    of    the
                                                                                         response is attached
                  Concurrence           Department of Main Material change of              The agency provided
                                        Roads, PO Box 183, use of premises near            its response on 3 June
                                        Gympie QLD 4570    a State transport               2005 (Reference No.
                                                           corridor                        2005/638). A copy of
                                                                                           the     response     is
                                                                                           attached
                  Concurrence           Department of State •           Clearing native    The agency provided
                                        Development,                    vegetation         its response on 15
                                        Infrastructure,  Local •        State transport    January         2024
                                        Government        and           corridors and      (Reference No. 2311-
                                        Planning (SARA),                future state       37804 SRA). A copy of
                                        PO       Box     1129,          transport          the    response    is
                                        Maroochydore      QLD           corridors          attached
                                        4558




                                                                                                          Page 7 of 24
Document Set ID: 22816452
Version: 8, Version Date: 22/02/2024

Page 8

                 7.     ADVISORY NOTES

                 The following notes are included for guidance and information purposes only and do not form
                 part of the assessment manager conditions:
                 1.     All clearing of vegetation is to be undertaken in accordance with the recommendations
                        of the Environmental Assessment Report Flora and Fauna study for the proposed
                        expansion of the Noosaville Waste Landfill which include the following protective
                        measures for Fauna

                          PROTECTIVE MEASURE                                     SPECIES AFFECTED

                          Establish a protective buffer of at least 30m around Wallum froglet
                          shallow acidic water bodies

                          Maintain water quality and hydrological patterns Wallum froglet
                          within the habitat of the species

                          No prescribed burns in the winter months around Wallum froglet
                          water bodies

                          Protect the heath where-ever possible                  Ground parrot

                          Mosaic burns should be conducted to maintain the Ground parrot
                          integrity of the heath. Prescribed burns should not be
                          more frequent than every two to three years, but at
                          least every 15 years

                          Retain nectar and fruit-bearing trees                  Grey-headed flying-fox

                          Care should be taken to ensure that no animals are Echidna
                          killed during clearing for the new waste disposal site
                                                                                 Hollow-using species

                          Retain hollow-bearing trees where possible             Hollow-using species

                        Qualified Person
                 2.     For the purpose of preparing an Acid Sulfate Soils Management Plan, a qualified person
                        is considered to be a person who:
                        a.      Is a Registered Professional Engineer of Queensland (RPEQ); or
                        b.      Environmental/Soil Scientist with current professional membership status at a
                                relevant organisation (e.g. ASSSI, AIG; EIANZ; GSA); and
                        c.      Has a minimum of 5 years of professional experience in the field of Acid Sulfate
                                Soils.
                 3.     For the purpose of preparing and certifying in accordance with an offset management
                        plan, a qualified person is considered to be an ecologist with a minimum of 3 years
                        current experience in vegetation offset management.
                 4.     For the purpose of Preparing management plans, certification and managing plant pests,
                        a qualified person is considered to be:
                        a.            an environmental consultant with a minimum of 3 years current experience
                                in the field of pest plant management.




                                                                                                      Page 8 of 24
Document Set ID: 22816452
Version: 8, Version Date: 22/02/2024

Page 9

                 5.     For the purpose of preparing a Fauna Management Plan, a qualified person is
                        considered to be an ecologist with a minimum of 3 years current experience in the field
                        of fauna assessment and management and with a current certification under the
                        Queensland Parks and Wildlife Services.
                 6.     For the purpose of preparing an Arborist Report, a qualified person is considered to be
                        a person with either:
                        a.             ISA certification; or
                        b.           a Diploma of Arboriculture in addition to a minimum of 3 years current
                                experience in the field of arboriculture.
                 7.     For the purpose of preparing a Bushfire Management Plan, and for certifying compliance
                        with the bushfire requirements of this Decision Notice, a qualified person is considered
                        to be an ecologist with a minimum of 3 years current experience in the field of bushfire
                        assessment and management.
                        Advertising Devices
                 8.     All Advertising Devices must comply with Schedule 10 of Subordinate Local Law No.1
                        (Administration) 2015 including both temporary and permanent signage. All
                        freestanding, pylon or pole signs or signage that is illuminated requires approval from
                        Council prior to being installed. All signage identified in s6 of Schedule 10 of Subordinate
                        Local Law No. 1 is prohibited from being erected in the Shire.
                        Resubmission of Amended Plans Required
                 9.     The conditions of this Decision Notice require resubmission of plan/s to Council with
                        amendments. Please address the amended plans to Council’s Development
                        Assessment Branch with the Reference No. 132005.638.03.
                        Nature Conservation Act
                 10.    It is the responsibility of the applicant to ensure compliance with the Nature Conservation
                        Wildlife Management Regulation 2006 which is regulated by the State Government.
                        There may be a requirement to undertake a Flora Survey pursuant to Flora Survey
                        Guidelines prior to any clearing activities pursuant to Chapter 4 of the Nature
                        Conservation Wildlife Management Regulation 2006. Exemptions are listed in Division
                        5 of the same Act. Further information can be obtained at this website
                        https://www.ehp.qld.gov.au/licences-permits/plants-animals/protected-plants/ or by
                        calling the Department of Environment and Heritage Protection on 1300 130 372.
                        There may also be a requirement to obtain State Government Approval of a Species
                        Management Plan prior to any activities that tamper with any place that is being used by
                        a native animal for breeding activities. This is regulated by Section 332 of the Nature
                        Conservation Wildlife Management Regulation 2006. Further information regarding this
                        matter can be obtained at this website https://www.ehp.qld.gov.au/licences-
                        permits/plants-animals/species-management-program/ or by calling the relevant State
                        Department.
                        Infrastructure Charges
                 11.    All developments and/or changes to existing developments may require payment of
                        “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges
                        Resolution” made pursuant to the planning legislation and regulations current at the time
                        of issue. For further information, please refer to https://www.noosa.qld.gov.au/planning-
                        development/development-tools-guidelines/infrastructure-charges
                 8.     PROPERTY NOTES

                 Not applicable.




                                                                                                          Page 9 of 24
Document Set ID: 22816452
Version: 8, Version Date: 22/02/2024

Page 10

                 9.       VARIATION APPROVAL DETAILS

                 Not applicable.
                 10.      FURTHER DEVELOPMENT PERMITS REQUIRED

                 Not applicable.
                 11.      SUBMISSIONS

                 Not applicable.
                 12.      RIGHTS OF APPEAL

                 You are entitled to appeal against this decision. A copy of the relevant appeal provisions from
                 the Planning Act 2016 is attached.
                 During the appeal period, you as the applicant may suspend your appeal period and make
                 written representations to Council about the conditions contained within the development
                 approval. If Council agrees or agrees in part with the representations, a negotiated decision
                 notice will be issued. Only one negotiated decision notice may be given.
                 13.      OTHER DETAILS

                 If you wish to obtain more information about the decision, electronic copies are available on
                 line at www.noosa.qld.gov.au or at Council Offices.
                 Yours faithfully,




                 Patrick Murphy
                 Manager - Development and Regulation


                 Enc:     Referral Agency Response
                          Appeal Rights
                          Approved Plans/Documents

                 cc.      Unitywater
                          SARA

                 DECISION NOTICE HISTORY
                 •     Original Decision Notice – 24 November 2005.

                 •     Generally in Accordance Letter – 132005.638.01 – 29 June 2021.

                 •     Decision Notice – Other Change – 132005.638.02 – 30 August 2023, Withdrawn.

                 •     Decision Notice – Other Change – 132005.638.03 – 15 February 2024, include additional conditions 14 - 45.




                                                                                                                                   Page 10 of 24
Document Set ID: 22816452
Version: 8, Version Date: 22/02/2024

Page 11

                                       Referral Agency Response
                                       PLANNING ACT 2016 & PLANNING REGULATION 2017




                                                                                      Page 11 of 24
Document Set ID: 22816452
Version: 8, Version Date: 22/02/2024

Page 12

Referral Agency Response — Material Change of Use
S$ 3.3 16 Integrated Planning Act 1997

1. Application information

11.
12.
1.3.
14,
15.

16.

Applicant’s name: Noosa Shire Council

Property description: 77 SP177938 - Noosa Shire
Assessment Manager/Reference: Noosa Shire Council

Date application was referred to Department: 26 April 2005

Departmental Reference. eLVAS Case No: 2005/101216, File Ref. No:
GYP/000280, Trackjob No: IR0405NAM0004

Type/s of development sought by the application:
QO Matenal Change of Use

2. Concurrence Agency response:

The Chief Executive of the Department of Natural Resources and Mines directs that the
following conditions must be imposed on any approval given by the Assessment Manager:

2.1

22

23

24

25

26

27

This permit does not authorise the clearing of any native vegetation that 1s on any land
not contained withm the area identified as Permit A on the attached Referral Agency
Response (Vegetation) Pian RARP2005/101216.

Expansion of the area designated for Waste Disposal and Recycling Facility within
Lot 77 on SP177938 is restricted to the area identified as Permit A on the attached
Referral Agency Response (Vegetation) Plan RARP2005/101216.

Prior to clearing for the establishment of additional landfill cells and waste
management facilities, a storm-water management and sediment control plan that
prevents storm-water, sediment and other possible contammants from encroaching into
areas outside of the area of Permit A on RARP2005/101216, must be developed and
inshtuted so as to be effective durmg the operational works stage of the site
preparation and landfill construction

The design and construction of new landfill cells must incorporate a leachate
Management system that prevents the escape of water from the landfill cells into the
surrounding environment

The leachate management system must incorporate a groundwater monitoring system
and response strategy that 1s capable of rapid identification of cell leakage and
rectification measures.

The design and construction of the expanded waste management facility must
weorporate a storm-water control system that will prevent, m perpetuity, storm-water,
sediment and other possible contammants from encroaching into surrounding areas of
remnant vegetation.

All works are to be undertaken im accordance with Environmental Protection Agency
Guidehnes for Landfill siting, design, operation and rebabiltation, Waste Disposal —
ERA 75.

IDAS Referral Agency Response

Document Set ID: 22816452
Version: 8, Version Date: 22/02/2024

Page 12 of 24

Page 13

2.8 All firebreaks necessary to protect infrastructure that is to be developed within the
expanded waste management facility must be contained with the area of Permit A on
RARP2005/101216.

2.9 Prior to the commencement of operational works that is the clearing of remnant
vegetation within the area of Permit A on RARP2005/101216 a remnant vegetation
restoration plan for properties described Table 1 must be developed m accordance with
the NR&M Interim Policy for Vegetahon Management Offsets 3 October 2005
attached to this notice. The restoration plan must apply to a mmimum of 24 ha of land
within the area of properties described 1n Table 1. The restoration plan must achieve as
an outcome the establishment of a mimmum of 19ha of a remnant endangered regional
ecosystem and the establishment of a minimum of Sha of a remnant not of concem
regional ecosystem within 20 years of the date of this notice.

Table 1. Property descriptions subject to remnant vegetation restoration plan - Noosa Shire.

 

 

 

 

 

4TRP170398 3RP138769 ARP149832 2RP 164019
2RP163499 4RP163496 3RP134347 100SP167229
1RP906937 6RP134347 2RP134347 3RP168290
2RP164019 4RP160978 2RP162747 1RP193959
3RP167264 2RP149832 1RP164020 9SP143416

 

 

 

 

 

 

2.10 Prior to the commencement of operational works that 1s the clearing of remnant
vegetation within the area of Permit A on RARP2005/101216 the remnant vegetation
restoration plan must be provided to and approved by the Chief Executrve NR&M as
being consistent with the NR&M Interim Policy for Vegetation Management Offsets 3
October 2005 attached to this notece.

3. Reasons:
A Statement of Reasons 1s attached at Schedule 1

4. Additional comments or information:
Aboriginal Cultural Heritage
Under section 23 of the Aboriginal Cultural Heritage Act 2003 a person who carries out an
activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage (the “cultural heritage duty of care"). Maximum penalties
for breaching the duty of care are $750,000 for a corporation and $75,000 for an individual.

Appheants will comply with the duty of care m relation to Aboriginal cultural heritage 1f they
are acting m compliance with cultural heritage duty of care guidelines gazetted under the
Aboriginal Cultural Heritage Act 2003, available on the Department’s website, or n
accordance with an agreement with the Aboriginal party for the area or a cultural heritage
management plan approved under part 7 of the Aboriginal Cultural Heritage Act 2003.

Applicants should also undertake a search of the Aboriginal Cultural Heritage Database and
the Aborigmal Cultural Hentage Register, admimstered by the Cultural Heritage
Coordination Unit, Department of Natural Resources and Mines Apphcation forms to
undertake a free search of the Cultural Herttage Regyster and the Database may be obtaned
by contacting the Cultural Heritage Coordination Unit on (07) 323 83838 or on the
Department's website www.nrm.qid.gov au/cultural heritage.

Natural Resources and Mines - Referral Agency Response Page 2 7

Document Set ID: 22816452 Page 13 of 24

Version: 8, Version Date: 22/02/2024

Page 14

Definitions
Particular words and terms used in the above conditions are defined as follows:
‘Vegetation’ means vegetation as defined under the Vegetation Management Act 1999

‘Remnant vegetation’ means remnant vegetation as defined under the Vegetation
Management Act 1999.

‘Remnant endangered regional ecosystem,’ means remnant regional ecosystem as defined
under the Vegetation Management Act 1999.

‘Remnant of concern regional ecosystem,’ means remnant regional ecosystem as defined
under the Vegetation Management Act 1999

‘Remnant not of concern regional ecosystem,’ means remnant regional ecosystem as
defined under the Vegetation Management Act 1999

‘Clear’ for vegetation means clear as defined under the Vegetation Management Act 1999
‘ha’ means hectares.

5. Authorised Officer Signature:

hee

Peter Lazzarini
Semor Vegetation Management officer
South East Region

1 November 2005

Attachments:
= Schedule 1 — Statement of Reasons
= NR&M Interim Policy for Vegetation Management Offsets 3 October 2005
- Referral Agency Response (Vegetation) Plan RARP2005/101216

Natural Resources and Mines - Referral Agency Response Page 3 of 7

Document Set ID: 22816452 Page 14 of 24
Version: 8, Version Date: 22/02/2024

Page 15

 

Queensland
Government

SARA reference: 2311-37804 SRA
Council reference: 132005.638.03

15 January 2024

Chief Executive Officer
Noosa Shire Council
PO Box 141

Tewantin QLD 4565

[email protected]

Attention: Mr Samuel Osakwe

Dear Mr Osakwe

SARA referral agency response—561 Eumundi Noosa Road,
Doonan
(Referral agency response given under section 56 of the Planning Act 2016)

The development application described below was confirmed as properly referred by the State
Assessment and Referral Agency (SARA) on 17 November 2023.

 

 

Response
Outcome: Referral agency response — with conditions
Date of response: 15 January 2024
Conditions: The conditions in Attachment 1 must be attached to any
development approval
Reasons: The reasons for the referral agency response are in Attachment 2
Development details
Description: Development permit Material change of use for Expansion of
Utility Installation - Noosa Landfill.
SARA role: Referral agency
SARA trigger: *® Schedule 10, Part 3, Division 4, Table 3, Item 1 (10.3.4.3.1)
(Planning Regulation 2017)
Native Vegetation Clearing
‘South East Queensland (North) regional
office
Level 4, Foundation Place 3 South Sea
Islander Way, Maroochydore
Page 1 of 5 PO Box 1123, jore QLD 4568

Document Set ID: 22816452 Page 15 of 24

Version: 8, Version Date: 22/02/2024

Page 16

2303-33878 SRA

* Schedule 10, Part 9, Division 4, Subdivision 2, Table 4, Item 1
(10.9.4.2.4.1) (Planning Regulation 2017)
Material change of use on a premise that is within 25m of a State
transport corridor and within 100m of a State-controlled road

intersection
SARA reference: 2311-37804 SRA
Assessment manager: Noosa Shire Council
Street address: 561 Eumundi Noosa Road, Doonan
Real property description: Lot 77 on SP298776
Applicant name: Noosa Council
C/- Adamson Town Planning
Applicant contact details: 28 Eenie Creek Rd
Noosaville QLD 4566
[email protected]
Human Rights Act 2019 A consideration of the 23 fundamental human rights protected under
considerations: the Human Rights Act 2019 has been undertaken as part of this
decision. It has been determined that this decision does not limit
human rights

Representations

An applicant may make representations to a concurrence agency, at any time before the application is
decided, about changing a matter in the referral agency response (s.30 Development Assessment
Rules). Copies of the relevant provisions are in Attachment 3.

 

A copy of this response has been sent to the applicant for their information.

For further information please contact Jodie Wilson, Senior Planning Officer, on 5352 9778 or via email
[email protected] who will be pleased to assist.

Yours sincerely

or

Garth Nolan
Manager (Planning)

cc Noosa Council, [email protected]

enc Attachment 1 - Referral agency conditions
Attachment 2 - Reasons for referral agency response
Attachment 3 - Representations about a referral agency response provisions
Attachment 4 - Documents referenced in conditions

State Assessment and Referral Agency Page 2 of 5

Document Set ID: 22816452 Page 16 of 24

Version: 8, Version Date: 22/02/2024

Page 17

Attachment 1—Referral agency conditions

2303-33878 SRA

 

(Under section 56(1)(b)(i) of the Planning Act 2016 the following conditions must be attached to any development
approval relating to this application) (Copies of the documents referenced below are found at Attachment 4)

 

No.

[ Conditions

Condition timing

 

Material change of use

 

10.3.4.3.1 — Clearing native vegetation - The chief executive administering the Planning Act 2016
nominates the Director-General of the Department of Resources to be the enforcement authority for
the development to which this development approval relates for the administration and enforcement of
any matter relating to the following condition(s):

 

1.

Clearing of vegetation must:
(a) only occur within Area A (Part A') as shown on the attached:

i. Vegetation Management Plan, prepared by Queensland
Government, reference VMP 2311-37804 SRA, Sheet 1 of
1, version 1; and

(b) not exceed 0.81 hectares.

At all times

 

 

 

 

 

 

2. er into an agreed delivery arrangement to deliver an environmental a ore a ioe
offset in accordance with the Environmental Offsets Act 2014 to Onthenuiiccct
counterbalance the significant residual impacts on the matter of ,
state environmental significance being: cviies rental

significance
hectares of remnant vegetation intersecting with a wetland within the 9
following regional ecosystems:
i. 0.64 hectares of Least Concern Regional Ecosystem
12.3.13, and
ii, 0.17 hectares of Endangered Regional Ecosystem 12.5.3.
State Assessment and Referral Agency Page 3 of 5

Document Set ID: 22816452
Version: 8, Version Date: 22/02/2024

Page 17 of 24

Page 18

2303-33878 SRA

Attachment 2—Reasons for referral agency response
(Given under section 56(7) of the Planning Act 2016)

 

The reasons for the SARA’s decision are:

*® The proposal is for a development permit ‘other change’ to an existing development approval
(2005/638) for material change of use for use of the premise to expand the existing landfill operation

* The subject site is located within 25 metres of a state-controlled road and involves clearing of
approximately 0.81ha of mapped regulated vegetation category B, of which 0.64 ha is mapped as
wetland and 0.17 ha is within 100 m of the wetland.

* SARA assessed the development application against State code 1: Development in a
state-controlled road environment of the SDAP, version 3.0 and determined that without conditions,
the development achieves compliance with the performance outcomes of the State code.

* SARA assessed the development application against State code 16: Native vegetation clearing
of the SDAP, version 3.0 and determined that the development complies with the relevant
performance outcomes, subject to conditions to ensure:

o Vegetation clearing is limited to 0.81ha of mapped regulated vegetation category B

© Clearing of the mapped wetland and matters of state environmental significance (MSES) is
mitigated through the provision of an environmental offset in accordance with the
Environmental Offsets Act 2014

Material used in the assessment of the application:

the development application material and submitted plans
Planning Act 2016

Planning Regulation 2017

the SDAP (version 3.0), as published by SARA

the Development Assessment Rules

SARA DA Mapping system

State Planning Policy mapping system {delete if not used]
section 58 of the Human Rights Act 2019

Attachment 3—Representations about a referral agency response
provisions

 

(page left intentionally blank)

State Assessment and Referral Agency Page 4 of 5

Document Set ID: 22816452 Page 18 of 24

Version: 8, Version Date: 22/02/2024

Page 19

2303-33878 SRA

Attachment 4—Documents referenced in conditions

 

(page left intentionally blank)

State Assessment and Referral Agency Page 5 of 5

Document Set ID: 22816452 Page 19 of 24

Version: 8, Version Date: 22/02/2024

Page 20

Development Assessment Rules—Representations about a
referral agency response

The following provisions are those set out in sections 28 and 30 of the Development Assessment Rules?
regarding representations about a referral agency response

Part 6: Changes to the application and referral agency
responses

 

28 Concurrence agency changes its response or gives a late response

28.1. Despite part 2, a concurrence agency may, after its referral agency assessment period and any
further period agreed ends, change its referral agency response or give a late referral agency
response before the application is decided, subject to section 28.2 and 28.3.

28.2. A concurrence agency may change its referral agency response at any time before the application
is decided if—

(a) the change is in response to a change which the assessment manager is satisfied is a change
under section 26.1; or

(b)_ the Minister has given the concurrence agency a direction under section 99 of the Act; or

(c) the applicant has given written agreement to the change to the referral agency response?

28.3. A concurrence agency may give a late referral agency response before the application is decided,
if the applicant has given written agreement to the late referral agency response.
28.4. Ifa concurrence agency proposes to change its referral agency response under section 28.2(a),
the concurrence agency must—
(a) give notice of its intention to change its referral agency response to the assessment manager
and a copy to the applicant within 5 days of receiving notice of the change under section 25.1;
and
(b) the concurrence agency has 10 days from the day of giving notice under paragraph (a), or a
further period agreed between the applicant and the concurrence agency, to give an amended
referral agency response to the assessment manager and a copy to the applicant.

‘ Pursuant to Section 68 of the Planning Act 2016

2 In the instance an applicant has made representations to the concurrence agency under section 30,
and the concurrence agency agrees to make the change included in the representations, section
28.2(c) is taken to have been satisfied.

Page 1 of2

Document Set ID: 22816452 Page 20 of 24

Version: 8, Version Date: 22/02/2024

Page 21

Part 7: Miscellaneous

30 Representations about a referral agency response

30.1. An applicant may make representations to a concurrence agency at any time before the application
is decided, about changing a matter in the referral agency response.?

> An applicant may elect, under section 32, to stop the assessment manager's decision period in which
to take this action. If a concurrence agency wishes to amend their response in relation to
representations made under this section, they must do so in accordance with section 28.

Page 2 of2

Document Set ID: 22816452 Page 21 of 24

Version: 8, Version Date: 22/02/2024

Page 22

 

 

 

 

 

 

 
 

PLANS AND DOCUMENTS es
referred to in the REFERRAL
| AGENCY RESPONSE ed

| SARAret, gt 5R4

Date 4 Jerumry 2008

 

 
 

 

  
 

 

 

  
 

 

 
 

 

 

 

 

 

 

 

 

Notes: Derived Reterence Foints are provided to assist in the locaton of ares boundaries. Responsibility tor
7 locating these boundaries les solely with he
TONGA pape cee Watercourse and drainage feature locations shown om the Vegemtion Management Pian are derived trom the
° 20 500 750 1000 mates \Vegetaton Management
only and require ground truthing to identify the exact location of the watercourse or drainage feature.
‘The property boundaries shown on tis pian are APPROXIMATE ONLY. They are NOT an accurate

Projection: GDA2020 MGA Zone 56 Datum: GDA2020 representation of the lege! boundaries.
‘This pian must be read In conjunction with conditions attached to 2311-37804 SRA

 

 

 

 

 

 

 

LEGEND A. .
"&  Deived Reference Stet Points re re Vegetation Management Plan

Fn cee He wait Plan of Area A (Part A’) in Lot 77 on Plan Onmersne

7D.) Wileraurse endive drirage feck er, SP298776 © The State of Queensiand, 2023
A VMP

2311-37804 SRA
Note: Tris is 8 colour map and must be reproduce in colour N version: 1 | eLVAS Case ID: 2023003938 Sheet 1 of 1
VMGE-NA-2S37

 

 

 

Document Set ID: 22816452 Page 22 of 24

Version: 8, Version Date: 22/02/2024

Page 23

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –                                              1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and                                                application; and
                   (b) The person-                                                                (e) each person who may elect to become a co-respondent for the
                                                                                                      appeal, other than an eligible submitter who is not a principal
                         (i)   who may appeal a matter (the appellant); and
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and                 (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and             (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the                 person who the registrar considers appropriate.
                              matter.                                                         (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.                     (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –                                                             Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the          (5) A notice of appeal given to a person who may elect to be a co-
                       agency; or                                                                 respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the         (6) A person elects to be a co-respondent by filing a notice of election,
                       deemed refusal happens; or                                                 in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter            appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of        231 Other appeals
                       premises – 20 business days after a notice us published under
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                       section 269(3)(a) or (4); or
                                                                                                  the Supreme Court decides a decision or other matter under this
                   (d) for an appeal against an infrastructure charges notice – 20                Act is affected by jurisdictional error, the decision or matter is non-
                       business days after the infrastructure charges notice is given             appealable.
                       to the person; or
                                                                                              (2) The Judicial Review Act 1991, part 5 applies to the decision or
                   (e) for an appeal about a deemed approval of a development                     matter to the extent it is affected by jurisdictional error.
                       application for which a decision notice has not been given –
                                                                                              (3) A person who, but for subsection (1) could have made an
                       30 business days after the applicant gives the deemed
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                       approval notice to the assessment manager; or
                                                                                                  decision or matter, may apply under part 4 of that Act for a
                   (f)   for any other appeal – 20 business days after a notice of the            statement of reasons in relation to the decision or matter.
                         decision for the matter, including an enforcement notice, is
                                                                                              (4) In this section –
                         given to the person.
                                                                                                  decision includes-
               Note –
                   See the P&E Court Act for the court’s power to extend the appeal               (a) conduct engaged in for the purpose of making a decision; and
                   period.                                                                        (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard                   (c) the making of a decision or failure to make a decision; and
                   in the appeal.
                                                                                                  (d) a purported decision; and
               (5) If an appeal is only about a referral agency’s response, the
                   assessment manager may apply to the tribunal or P&E Court to                   (e) a deemed refusal.
                   withdraw from the appeal.                                                      non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an                  matter-
                   infrastructure charges notice must not be about-                               (a) is final and conclusive; and
                   (a) the adopted charge itself; or                                              (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-                                      set aside or called into question in any other way under the
                                                                                                      Judicial Review Act 1991 or otherwise, whether by the
                         (i)   the establishment cost of trunk infrastructure identified in           Supreme Court, another court, a tribunal or another entity; and
                               a LGIP; or
                                                                                                  (c) is not subject to any declaratory, injunctive or other order of
                         (ii) the cost of infrastructure decided using the method                     the Supreme Court, another court, a tribunal or another entity
                              included in the local government’s charges resolution.                  on any ground.
               230 Notice of appeal                                                           232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the        (1) A person who is appealing to the P&E Court must comply with the
                   tribunal or P&E Court, a notice of appeal that-                                rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                                                                                              (2) However, the P&E Court may hear and decide an appeal even if
                   (b) succinctly states the grounds of the appeal.                               the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                  Page 23 of 24
Document Set ID: 22816452
Version: 8, Version Date: 22/02/2024

Page 24

Document Set ID: 22816452 Page 24 of 24

Version: 8, Version Date: 22/02/2024

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.