                                                                                             Consult Arborist

                 8.5 R ESTRICTED A CTIVITIES W ITHIN THE TPZ
                 Restricted activities within the TPZ that would cause harm to the retained trees to include, but
                 are not limited to:

                     •    Any non-approved construction works.
                     •    Any non-approved excavation or cultivation of the ground.
                     •    Any non-approved storage.
                     •    Preparation of chemicals, including cement products.
                     •    Parking of vehicles and plant.
                     •    Refuelling.
                     •    Dumping of waste.
                     •    Wash down and cleaning of equipment.
                     •    Placement of Fill.
                     •    Lighting fires.
                     •    Any non-approved soil level changes.
                     •    Temporary or permanent installation of utilities and signs.
                     •    Physical damage to the tree.

                 8.6 TPZ S TANDARD M I TIGATION M EASURES
                 Where groundworks are carried out adjacent to or encroaching into the TPZ areas the
                 following mitigation measures and procedures should be implemented where deemed
                 appropriate and should be supervised by Consult Arborist.

                 •    Where possible the excavated ground, including the cut roots, will be covered/backfilled
                      with quality topsoil locally sourced or a sandy loam/river sand with low organic matter, as
                      guided by AS 4419—2003. Australian Standard™ Soils for landscaping and garden use.
                 •    An application of a seaweed-based soil conditioner/plant food can be applied to the topsoil
                      as per the manufacturer’s guidelines. Monthly applications are recommended for the
                      duration of the project.
                 •    Ground protection measures are to be installed/used when access to the TPZ is required
                      to undertake construction works. All ground protection measures are to be discussed and
                      agreed upon with the Project Arborist prior to installation. These are to include but are not
                      limited to: ply sheets, geo fabric, thick mulch layer.
                 •    When required supplemental watering with a water cart or sprinkler system can be used
                      to retain adequate moisture levels in the soil.
                 •    The Project Arborist is to advise and oversee all mitigation measures works being
                      undertaken to retained trees.

                 All tree works, and tree protection measures, are to be guided by industry best practices and
                 the relative Australian Standards which include but are not limited to:
                  • Australian Standards AS4970-2009 Protection of trees on development sites
                  • Australian Standards AS4373-2007 Pruning of amenity trees




                 23_02_22_AIA_Adapt_2 Arakoon_2                                                       Page 19 of 25
Document Set ID: 22343519
Version: 1, Version Date: 16/03/2023
Log in to download the original file

ECM_22343519_v1_Aboricultural Impact Assessment.pdf · 6.1 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.