ECM_22343519_v1_Aboricultural Impact Assessment
Consult Arborist
4 I NTRODUCTION AND S ITE D ETAILS
The site at 2 Arakoon Crescent, in the Noosa Council coastal suburb of Sunshine Beach. The
existing private dwelling is located on the corner of The Esplanade and behind the foreshore
dunal area.
The project plans to renovate the existing house and realign the driveway alignment that
traverses the Noosa Council road reserve on The Esplanade.
Within the property are trees and palms of differing ages and sizes, most of which were planted
many years ago by the past and current property owner. The more significant vegetation is
located within the Noosa Council verge on the southern side of the property. The most
significant are located towards the south eastern corner of the property, they are the two
mature Cook Island Pines within the property, and one mature Cook Island Pine on the Council
verge; these are proposed to be retained and protected. The fourth Cook Island Pine stands
mid-way along the southern boundary on the Council verge of The Esplanade, this tree is very
close to the property boundary and dwelling.
The Esplanade verge has been maintained by the property owner over many years, who have
cared for it as their own, and they wish to continue to do so. This includes weed control and a
sympathetic planting of local coastal species to maintain a vegetative screen to the property
that enhances the local street scene.
The primary design feature that conflicts with the existing vegetation on The Esplanade verge
is the new driveway alignment. I have been advised that the existing driveway is narrow and
at an unsuitable angle for safe entry and exit close to the road junction. With the road at a
higher elevation to the property, the driveway slopes down requiring either a retaining wall
and/or some reshaping of the verge levels. It is these works that conflict either directly or
indirectly with a number of trees and palms on the council verge.
Engineering solutions and the design plan have been reviewed in an attempt to minimise the
vegetation conflict, however, despite this a number of trees and palms will require removal
and transplanting. It is proposed that the new design will afford a position for replacement tree
and landscaping to be planted as part of the landscape design. This will ultimately replace and
replenish the vegetation for the future.
Mitigation measures and compromised solutions have been assessed to reduce the conflict
with and the reduced size of, the TPZs of retained trees. A Project Arborist will need to be
engaged prior to any site activities commencing to provide onsite guidance to the building
contractor. Regular presence and assistance from a Project Arborist will be needed throughout
the project build.
23_02_22_AIA_Adapt_2 Arakoon_2 Page 6 of 25
Document Set ID: 22343519
Version: 1, Version Date: 16/03/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.