2018-05-29 SM - Attachment 4 (Part 1) to Item 2 - LGIP
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
Table 15.12—Existing and projected demand for the stormwater network
Column 1 Column 2
5
Service catchment Existing and projected demand (imp ha)
Ultimate
2014 2016 2021 2026 2031 development
1. Boreen Point Village (PIA) 11.34 12.43 13.13 13.28 13.35 14.38
2. Kin Kin Village (PIA) 9.56 10.48 11.16 11.56 11.75 13.76
3. Cooroibah Village (PIA) 4.48 4.59 4.91 4.91 4.91 4.95
4. Cooroy Town (PIA) 124.18 128.57 151.01 157.96 174.72 213.91
5. Eastern Beaches (PIA) 252.12 255.39 259.98 271.12 286.34 305.87
6. Cooran Village (PIA) 23.18 24.19 28.92 29.04 31.82 39.65
7. Pomona Town (PIA) 54.42 57.59 68.14 68.38 74.40 110.72
8. Noosa Heads (PIA) 156.37 161.72 169.06 170.85 171.43 183.00
9. Noosaville (PIA) 262.76 274.12 291.25 298.88 302.98 371.39
10. Tewantin (PIA) 247.08 252.05 261.06 264.66 266.06 306.05
Note––5. Table 15.12 Column 1 The service catchments for the stormwater network are identified on Local Government Infrastructure Plan Map LGIP-PFTI Stormwater (Plan for trunk
stormwater infrastructure) in Schedule 9 (local government infrastructure mapping and tables).
- 36-
–