     SC9.2             Schedules of works


Table 15.15—Stormwater network schedule of works

Column 1             Column 2                                        Column 3                 Column 4
Map reference        Trunk infrastructure                            Estimated timing         Establishment
                                                                                              cost 8
                     Pomona , Rifle Street
     SW01                                                                     2016                            $2,687,500
                     Pomona Rifle Street Flood Mitigation
                     Tewantin, Hilton Terrace
     SW02                                                                  2016-2021                           $500,250
                     Hilton Terrace Master Drainage Upgrade
                     Tewantin, Cooroy Noosa Road
                     Noosa Cooroy Road (opposite Tewantin
     SW03                                                                     2016                             $215,000
                     Golf Course) Upgrade of Culverts and
                     auxiliary drainage
                     Tewantin, Daintree Estate – Golf Course
     SW04            Drive                                                    2016                            $1,343,750
                     Upgrade of Stormwater Infrastructure
                     Noosa Heads, Pinaroo Park,
                     Reconstruction of Stormwater outlet
     SW05                                                                 2021 -2026                          $1,440,000
                     including GPT / Bio retention Basin and
                     Dispersion Bund Upgrades
                     Noosa Heads, Cooyar Street Street (East of
                     Noosa Springs Drive)
     SW06                                                                 2021 -2026                           $480,000
                     Bio retention Basin / Infiltration Basin &
                     Dispersion Bund
                     Noosa Heads, Cooyar Street (Opposite
                     Wyandra)
     SW07                                                                 2021 -2026                           $480,000
                     Upgrade existing Bio retention System and
                     Gross Pollutant Trap
                     Noosa Heads, Cooyar Street (Elanora
                     Terrace to Safari Street)
     SW08                                                                 2021 -2026                           $720,000
                     Bio retention Basin / Infiltration Basin &
                     Dispersion Bund
                     Sunshine Beach, Girraween Court
     SW09            Construction of Gross Pollutant Trap and             2021 -2026                           $480,000
                     Bio filtration System
                     Sunrise Beach, Ben Lexcen Drive and
                     Grasstree Court
     SW10                                                                 2021 -2026                           $960,000
                     Bio retention Basin / Infiltration Basin &
                     Dispersion Bund
                     Sunrise Beach, Dame Patti Drive.
     SW11            Stormwater outlet Upgrade / Gross                    2021 -2026                           $360,000
                     Pollutant Trap and Bio retention system
TOTAL                                                                                                     $9,666,500




     Note––8. Table 15.15 Column 4 The establishment cost is expressed in current cost terms as at the base
     date.
Log in to download the original file

2018-05-29 SM - Attachment 4 (Part 1) to Item 2 - LGIP(PDF, 626KB).pdf · 641 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.