23_09_Proposed_Caretakers Accommodation u5_8 Project Ave_08.04.24[82]

of 9

Page text shows just the words. Original shows the document exactly as it was published.

Note:
                                                                                                                                                                                              DRAWING LIST
- the builder and all other trades people/installers are to check
measure all relevant dimensions on site prior to the ordering of
project specific materials and/or commencement of any
construction/building activity
                                                                                                  Proposed Caretakers accom                                                        Sheet Number
                                                                                                                                                                                   01
                                                                                                                                                                                   02
                                                                                                                                                                                                            Sheet Name
                                                                                                                                                                                                  Cover Sheet
                                                                                                                                                                                                  Location Plan
                                                                                                                                                                                   03             Existing Lower Level
- existing bearers/beams, joists and rafters are unknown &                                                                                                                         04             Existing Mezzanie Floor Plan



                                                                                                Mitchell Cabinetmakers
should be checked by the builder prior to construction                                                                                                                             05             Existing Sections
- as no survey plan was conducted, any indicated levels                                                                                                                            08             Proposed Site & Ground Floor Plan
relative to AHD and details of external structures/elements                                                                                                                        09             Proposed Mezzanine Floor Plan
surrounding the existing site are approximations only                                                                                                                              10             Proposed Sections
- all proposed framing, fixings, bracing, concrete slabs,                                                                                                                          11             Proposed Section
footings & piers to engineer's design                                                                                                                                              15             3D Internal view
                                                                                                                                                                                   N1             General Notes
- all surface finishes, fixtures and cabinetry to client selection
                                                                                                                                                                                   N2             Workplace Health & Safety
                                                                                                                                                                                   N3             Sustainability Notes




           Legend

AT        Appliance Tower
CH        Ceiling Height
DN        Down
DP        Downpipe
DRY       Dryer
FFL       Finished Floor Level
FW        Floor Waste
HWS       Hot Water System
P'TRY     Pantry

                                                                                               Unit 5, 8 Project Avenue, Noosaville
REF       Refrigerator
SB        Switch Box
SHR       Shower
SI        Solar Inverter
SNK       Sink
VN        Vanity
WC        Water Closet


                                         JMF DESIGN PTY LTD          CLIENT:                      LOCATION:                Project number                                    NO:   DATE:      AMENDMENTS:
                                         27 Sunhine Beach Road
                                         Noosa Heads Q 4567
                                                                     Mitchell Cabinetmakers                                Project Ave      Cover Sheet                            19/07/23   Proposed
                                                                                                  Unit 5, 8 Project        2023
                                         e: [email protected]                                                                                                            01    18/10/23   Updated Proposed
                                                                                                  Avenue, Noosaville Qld
                                         www.jmfdesign.com.au        PROJECT:                                              Date             Scale         Drawn by     JMF         12/12/23   Issued Proposed
                                                                                                  4567
                                                                                                                                                                                   28/03/24    Revised Proposed
                                         Drafting: Jessica Fleming   MCU - Caretakers Accom.                               June 2023
                                                                                                                                                          Checked by   JMF
                                         QBCC 15200440                                                                                                                             08/04/24    Proposed further updates
Log in to download the original file

23_09_Proposed_Caretakers Accommodation u5_8 Project Ave_08.04.24[82].pdf · 3.9 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.